Wright v. Schutt Const. Co.

CourtSupreme Court of Oregon
Writing for the CourtTONGUE
Citation262 Or. 619,500 P.2d 1045
Parties, 69 A.L.R.3d 1260 Dillard E. WRIGHT, dba Dillard Wright and Associates, Real Estate, Appellant, v. SCHUTT CONSTRUCTION CO., Inc., Respondent.
Decision Date08 September 1972

Page 1045

500 P.2d 1045
262 Or. 619, 69 A.L.R.3d 1260
Dillard E. WRIGHT, dba Dillard Wright and Associates, Real
Estate, Appellant,
v.
SCHUTT CONSTRUCTION CO., Inc., Respondent.
Supreme Court of Oregon, In Banc.
Argued and Submitted June 6, 1972.
Decided Sept. 8, 1972.

[262 Or. 620] Ralph D. Barrett, Springfield, argued the cause for appellant. With him on the briefs were Harms & Harold, Springfield.

Max S. Taggart, II, Springfield, argued the cause for respondent. With him on the brief were Sanders, Lively & Wiswall, Springfield.

Page 1046

An amicus curiae brief was submitted by Norman F. Webb, Salem, on behalf of Oregon Assn. of Realtors.

TONGUE, Justice.

This is an action by a real estate broker to enforce a provision in an exclusive listing agreement to the effect that in the event the owner of the listed property withdrew the authority of the broker to sell the property the owner agreed 'to pay you the said commission just the same as if a sale had actually been consummated by you.'

[262 Or. 621] The listing agreement authorized plaintiff to sell defendant's property for the price of $200,000, 'net to owner.' Defendant terminated the agreement prior to its expiration date. Plaintiff's complaint demanded payment of $20,000 as a commission.

The trial court held that the provision for payment of a full commission on withdrawal of authority to sell was a penalty and refused to enforce it, based upon finding that plaintiff did not prove that he would have been able to sell the property for $200,000 'net to owner' so as to earn his commission, but for defendant's breach of the agreement, and that 'to use a prospective commission as a measure of damages would indulge in pure speculation.' Because of the breach of the agreement, however, and because plaintiff offered no proof of actual damages, the trial court awarded nominal damages of $1, plus $4,330 in attorney fees.

Plaintiff appeals, contending that the trial court erred in holding the 'stipulated sum' to be a penalty, and also erred in denying recovery for a 'debt due and owing.' We affirm because we agree with the finding and conclusion of the trial court that the provision of the listing agreement for payment of a full commission on wrongful termination of the agreement was a penalty under the facts and circumstances of this case, although not for the precise reasons given by the trial court.

While the courts cannot create new contract obligations, the courts can, in the interest of public policy, excuse the performance of contractual obligations which are contrary to the public interests. 5 Williston, Contracts (3d ed.) 639, § 769. See also 5 Corbin, Contracts[262 Or. 622] 320, 334, §§ 1055, 1057. Thus, as stated in 1 Restatement 552, Contracts § 339, comment a:

'Punishment of a promisor for breach, without regard to the extent of the harm that he has caused, is an unjust and unnecessary remedy. Therefore, the power of parties to make an enforceable contract for the determination of damages in advance is limited as stated in this Section.'

One reason for this result, as stated in 5 Williston, Supra, 703, § 780, is that:

'* * * experience has shown that dangerous advantage is likely to be taken of a party to a contract if he is allowed to stipulate in advance as a part of the contract that he will pay damages of any amount which the agreement may name, if he breaches the contract.'

On the other hand, much of the hostility formerly expressed by courts to provisions for liquidated damages has moderated in recent years as the courts have come to recognize that contract provisions for liquidated damages, under proper limitations, can save the time of the courts, as well as the parties, and also reduce the expense of litigation. Cf. Secord v. Portland Shopping News et al., 126 Or. 218, 225, 269 P. 228 (1928); and Medak v. Hekimian, 241 Or. 38, 45, 404 P.2d 203 (1965).

Perhaps the most widely accepted modern statement of the requirements which must be satisfied for a valid and enforceable contract provision for liquidated damages is set forth in 1 Restatement, Supra, 552, § 339(1), as follows:

'An agreement, made in advance of breach, fixing the damages therefor, is not enforceable as a contract and does not affect the damages recoverable for the breach, unless

[262 Or. 623]

Page 1047

'(a) the amount so fixed is a reasonable forecast of just compensation for the harm that is caused by the breach, and

'(b) the harm that is caused by the breach is one that is incapable or very difficult of accurate estimation.'

In Medak v. Hekimian, Supra at 44, 404 P.2d 203, this court cited § 339 with approval, although stating these two requirements in somewhat different terms. See also Harty v. Bye, 258 Or. 398, 483 P.2d 458 (1971).

In applying the first of these requirements the primary consideration is one of 'just compensation.' 1 See 1 Restatement, Supra, § 339, comments a and b. See also 5 Williston, Supra, 689, § 778. In deciding whether 'the amount so fixed is a reasonable forecast of just compensation for the harm that is caused by the breach,' there is considerable conflict among the authorities as to whether, and, if so, how, the intention of the parties can have any importance. According to 1 Restatement, Supra, 553, § 339, comment b, 'neither the intention of the parties nor their expression of intention is the governing consideration.' Indeed, most modern authorities appear to agree that whether the parties intend a contract provision to be one for liquidated damages, rather than a penalty is not controlling. See 5 Williston, Supra, 682, § 777, and 5 Corbin, Supra, 340, § 1058, and cases cited therein. But see Krausse v. Greenfield, 61 Or. 502, 512, 123 P. 392 (1912); Strode v. Smith, 66 Or. 163, 175, 131 P. 1032 (1913); [262 Or. 624] Alvord v. Banfield, 85 Or. 49, 57, 166 P. 549 (1917). Cf. Medak v. Hekimian, Supra, 241 Or. at 44, 404 P.2d 203.

It may be, however, as stated in 5 Williston, Supra, 693, § 778, that:

'The only sense in which the intention of the parties can have any meaning * * * is * * * to name a sum that is fixed in good faith as the equivalent of the injury which will probably be caused by the breach of the contract, rather than an attempt to secure performance by a provision for an excessive payment.'

This is consistent with the statement in 5 Corbin, Supra, 345--346, § 1059, that there must be a 'genuine pre-estimate of injury' as of the time when the contract was made, and that it is sufficient if at that time parties in an equal bargaining position make an honest and good faith effort to arrive at such an estimate. This is also consistent with the requirement of 1 Restatement, Supra, 552, § 339(1)(a) that there must be a 'reasonable forecast of just compensation for the harm that is caused by the breach.' See also McCormick, Damages 607, § 149 (1935).

The authorities also are not in complete accord on the question of the effect of evidence that despite such a good faith 'pre-estimate' or 'forecast' of such damages, the parties were mistaken in that no actual damages resulted from the breach, or the amount of the actual damages was much less than the amount of the liquidated damages. There is general agreement, however, with the proposition that a contract provision for liquidated damages will not be declared to be a penalty because the stipulated amount to be paid as damages is more than the amount of the actual damages unless the stipulated amount is 'grossly disproportionate,'[262 Or. 625] or has no 'reasonable relation' to the probable loss, as anticipated at the time of the contract. McCormick, Supra, 606, 623, §§ 149, 157; 5 Williston, Supra, 703, § 780; 5 Corbin, Supra, 362, § 1063. See also Hull v. Angus, 60 Or. 95, 107, 118 P. 284 (1911); Learned v. Holbrook, 87 Or. 576, 585, 170 P. 530, 171 P. 222 (1918); Secord v. Portland Shopping News et al., Supra, 126 Or. at 223--224, 269 P. 228; Elec. Prod. Corp. v. Ziegler Stores, 141 Or. 117, 125, 10 P.2d 910, 15 P.2d 1078 (1932);

Page 1048

Dairy Coop. Ass'n. v. Brandes Cry., 147 Or. 488, 500--501, 30 P.2d 338 (1934); and Medak v. Hekimian, Supra, 241 Or., at 45--46, 404...

To continue reading

Request your trial
21 practice notes
  • Chaffin v. Ramsey
    • United States
    • Supreme Court of Oregon
    • 21 Octubre 1976
    ...the burden. 4 In Oregon the burden has been placed upon the plaintiff, 5 although in the recent case of Wright v. Schutt Construction Co., 262 Or. 619, 629, 500 P.2d 1045, 1050 (1972), the question is treated as still open for decision, the court '* * * (W)e need not decide in this case whe......
  • Jones v. Four Corners Rod and Gun Club, CC 13C12103 (SC S066044)
    • United States
    • Supreme Court of Oregon
    • 30 Enero 2020
    ...of this court to excuse the performance of a contractual obligation that is contrary to the public interest. Wright v. Schutt Const. Co ., 262 Or. 619, 621, 500 P.2d 1045 (1972). We should do so here regarding the contractual obligation that, according to the majority, now subjugates plaint......
  • Layton Mfg. Co. v. Dulien Steel, Inc.
    • United States
    • Supreme Court of Oregon
    • 25 Febrero 1977
    ...to the actual damages, the clause will not be enforced. 8 As [277 Or. 354] was recognized in Wright v. Schutt Construction, 262 Or. 619, 624, 500 P.2d 1045, 1047 (1972), this approach is not universally 'The authorities also are not in complete accord on the question of the effect of eviden......
  • Illingworth v. Bushong
    • United States
    • Supreme Court of Oregon
    • 23 Octubre 1984
    ...in the event of a breach; if it goes beyond just compensation, however, it is unenforceable as a penalty. Wright v. Schutt Construction, 262 Or. 619, 623, 500 P.2d 1045 (1972). The test is " '(a) the amount so fixed is a reasonable forecast of just compensation for the harm that is caused b......
  • Request a trial to view additional results
21 cases
  • Chaffin v. Ramsey
    • United States
    • Supreme Court of Oregon
    • 21 Octubre 1976
    ...the burden. 4 In Oregon the burden has been placed upon the plaintiff, 5 although in the recent case of Wright v. Schutt Construction Co., 262 Or. 619, 629, 500 P.2d 1045, 1050 (1972), the question is treated as still open for decision, the court '* * * (W)e need not decide in this case whe......
  • Jones v. Four Corners Rod and Gun Club, CC 13C12103 (SC S066044)
    • United States
    • Supreme Court of Oregon
    • 30 Enero 2020
    ...of this court to excuse the performance of a contractual obligation that is contrary to the public interest. Wright v. Schutt Const. Co ., 262 Or. 619, 621, 500 P.2d 1045 (1972). We should do so here regarding the contractual obligation that, according to the majority, now subjugates plaint......
  • Layton Mfg. Co. v. Dulien Steel, Inc.
    • United States
    • Supreme Court of Oregon
    • 25 Febrero 1977
    ...to the actual damages, the clause will not be enforced. 8 As [277 Or. 354] was recognized in Wright v. Schutt Construction, 262 Or. 619, 624, 500 P.2d 1045, 1047 (1972), this approach is not universally 'The authorities also are not in complete accord on the question of the effect of eviden......
  • Illingworth v. Bushong
    • United States
    • Supreme Court of Oregon
    • 23 Octubre 1984
    ...in the event of a breach; if it goes beyond just compensation, however, it is unenforceable as a penalty. Wright v. Schutt Construction, 262 Or. 619, 623, 500 P.2d 1045 (1972). The test is " '(a) the amount so fixed is a reasonable forecast of just compensation for the harm that is caused b......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT