Wyoming Game and Fish Com'n v. Mills Co.

Decision Date19 June 1985
Docket NumberNo. 84-101,84-101
Citation701 P.2d 819
PartiesWYOMING GAME AND FISH COMMISSION, State of Wyoming, Appellant (Defendant), v. The MILLS COMPANY, a Wyoming Corporation, Appellee (Plaintiff).
CourtWyoming Supreme Court

A.G. McClintock, Atty. Gen., Allen C. Johnson, Sr. Asst. Atty. Gen. (argued) and Roger C. Fransen, Asst. Atty. Gen., for appellant.

Dan B. Riggs (argued) and Haultain E. Corbett of Lonabaugh & Riggs, Sheridan, for appellee.

Before THOMAS, C.J., ROSE, ROONEY and CARDINE, JJ., and JOHNSON, D.J.

CARDINE, Justice.

This is an appeal from a summary judgment granting damages to the Mills Company in a breach of contract action. We reverse and direct judgment to be entered in favor of the state of Wyoming but that the State's counterclaim be denied.

Appellant, Wyoming Game and Fish Commission, raises the following issue concerning breach of contract:

"Did the Appellant breach its contract with Appellee by refusing to purchase game and fish licenses from Appellee at the prices Appellee claimed it was due under the governing contract, where those prices are from ten to sixteen times higher than prices as contemplated by the contract generally and were ten to sixteen times higher than Appellee's actual costs of production?"

Appellee restates the issue as:

"1. Did a valid and enforceable requirements contract exist between Appellant and Appellee for the printing of game and fish licenses as of May 18, 1983?

"2. After placing an order for additional hunting licenses with Appellee on May 18, 1983, did Appellant breach its agreement with Appellee by refusing to allow Appellee to fill Appellant's order of May 18, 1983?

"3. Is Appellant entitled to unilaterally void its agreement with Appellee for the purchase of game and fish licenses as ordered by Appellant from Appellee on the grounds that Appellee was dissatisfied with the prices it was required to pay for those licenses when those prices had been approved in writing by the parties prior to Appellant's withdrawal from the agreement and when Appellant continued thereafter to make purchases from Appellee at the prices and terms stated in the parties' requirements contract?"

Each essentially contends that the other party first breached the contract thereby justifying their respective subsequent actions--the Game and Fish in placing its order with another printing firm and Mills in filing suit to recover damages. Our initial inquiry must be whether summary judgment was appropriate.

In October 1980, appellant Game and Fish and appellee Mills agreed to a requirements contract for the printing of game and fish licenses. These parties had been involved in a business relationship for over fifty years; the dealings between them had been largely informal with orders placed over the telephone and price increases confirmed without the supporting information requested by the contract. This business relationship has been singularly trouble free until the contract of 1980. It is perhaps significant that management of the Mills Company changed in 1979.

The contract was for one year with options for two one-year extensions. The options were exercised by Game and Fish, and the contract was in effect on May 18, 1983 when Game and Fish ordered 49,250 supplemental licenses from appellee Mills. Mills would have charged $80,843.88 1 for these licenses under the contractual provision for supplemental licenses, 2 although the cost to Mills for these licenses would have been $5,259. Game and Fish informed appellee that the price was too high. After negotiations failed, Game and Fish placed the order with another printing firm. Mills filed suit claiming that placing the order with another firm was a breach of the contract resulting in damages to Mills in the amount of $80,843.88. Game and Fish counterclaimed for the amount of money it contends was mistakenly overpaid in 1981 and 1982.

The appellate standard on a review of summary judgment is that:

"When a motion for summary judgment is before the supreme court, we have exactly the same duty as the district judge; and, if there is a complete record before us, we have exactly the same material as did he. We must follow the same standards. The propriety of granting a motion for summary judgment depends upon the correctness of a court's dual findings that there is no genuine issue as to any material fact and that the prevailing party is entitled to judgment as a matter of law. This court looks at the record from the viewpoint most favorable to the party opposing the motion, giving to him all favorable inferences to be drawn from the facts contained in affidavits, depositions and other proper material appearing in the record." Reno Livestock Corporation v. Sun Oil Company (Delaware), Wyo., 638 P.2d 147, 150 (1981). See also, Roth v. First Security Bank of Rock Springs, Wyoming, Wyo., 684 P.2d 93 (1984), and Blackmore v. Davis Oil Company, Wyo., 671 P.2d 334, 336 (1983).

A summary judgment is appropriate if there are no issues of material fact. Johnson v. Soulis, Wyo., 542 P.2d 867 (1975). A fact is material for purposes of a summary judgment if proof of that fact would effectively establish an essential element of the claim asserted or would refute an essential element as a defense. Schepps v. Howe, Wyo., 665 P.2d 504 (1983), and Hyatt v. Big Horn School Dist. No. 4, Wyo., 636 P.2d 525 (1981). It is improper to grant a summary judgment if there is a dispute of material fact. Wood v. Trenchard, Wyo., 550 P.2d 490 (1976). If the evidence leads to conflicting interpretations or if reasonable minds might differ, summary judgment is improper. Weaver v. Blue Cross-Blue Shield of Wyoming, Wyo., 609 P.2d 984 (1980). Summary judgment is only appropriate for cases sounding in contract when the language of the contract is clear and unequivocal because then the contract construction is a matter of law. Kuehne v. Samedan Oil Corp., Wyo., 626 P.2d 1035 (1981).

Applying these principles to this case, we must conclude that there are no genuine issues of material fact. Both parties agree that the facts are undisputed and that summary judgment is proper, although each contends that it should be granted in its favor. It is undisputed that the parties entered into a contract and that the bid prices were based upon an initial estimated lot of 1,000 with estimated supplemental lots of 100. It is undisputed that before appellee Mills submitted its bid, it obtained a price list from Eagle Printing and Business Forms, Inc. in Montana. The bid submitted equalled the prices of Eagle Printing and Business Forms, Inc. plus a one-third markup. Mills stated on the bid application that 100 percent of the printing was to be done in the state of Wyoming. None of the licenses were ever printed in Wyoming. All were printed by Eagle Printing and Business Forms, Inc. in Montana.

The contract provided for price adjustments during the term of the contract. Section 11, Price Adjustments, provided:

"(a) If, during the term of the contract, the bidder's net prices to their customers for items like those listed herein are reduced below the price quoted herein, it is understood and agreed that the benefits of such reduction shall be extended to the State of Wyoming.

"(b) If, during the term of the contract, the bidder's cost for materials, labor, transportation, etc. are increased, the bidder may apply to the Purchasing Administrator for a corresponding contract price adjustment. Such application must be accompanied by sufficient information to justify approval, provided, however, no application for upward price adjustments will be approved during the first thirty (30) days of the contract period."

The intent of the contracting parties together with common sense and good faith are the most important considerations in construing a contract. Busch Development, Inc. v. City of Cheyenne, Wyo., 645 P.2d 65 (1982). Courts must construe a contract as a whole, avoiding constructions which would render a provision meaningless. A presumption exists that a particular provision is placed there for a purpose. Sunburst Exploration, Inc. v. Jensen, Wyo., 635 P.2d 822 (1981), and Shepard v. Top Hat Land & Cattle Company, Wyo., 560 P.2d 730 (1977).

We recently reiterated the basic rules of contract interpretation in Cheyenne Mining and Uranium Company v. Federal Resources Corp., Wyo., 694 P.2d 65, 70 (1985) (quoting from Amoco Production Company v. Stauffer Chemical Company of Wyoming, Wyo., 612 P.2d 463, 465 (1980)):

" 'Our basic purpose in construing or interpreting a contract is to determine the intention and understanding of the parties. If the contract is in writing and the language is clear and unambiguous, the intention is to be secured from the words of the contract. And the contract as a whole should be considered, with each part being read in light of all other parts. The interpretation and construction is done by the court as a matter of law.' " (Citations omitted.)

The intent of the involved parties is determined by an objective approach. "A party's intention will be held to be what a reasonable man in the position of the other party would conclude his manifestations to mean." Shrum v. Zeltwanger, Wyo., 559 P.2d 1384, 1387 (1977).

Twice during the contract period Mills applied for and was granted a price increase according to these contract provisions. For supplemental orders of large quantities, Eagle Printing and Business Forms, Inc. based its price to Mills on the larger numbers; however, Mills charged the Game and Fish according to the 100 lot estimates. Appellant...

To continue reading

Request your trial
28 cases
  • Walsh v. Walsh
    • United States
    • Wyoming Supreme Court
    • November 20, 1992
    ...leads to conflicting interpretations or if reasonable minds might differ, then summary judgment is improper. Wyoming Game and Fish Com'n v. Mills Co., 701 P.2d 819, 821 (Wyo.1985). On the other hand, a motion for summary judgment brought by a defendant "should be sustained in the absence of......
  • Roussalis v. Wyoming Medical Center, Inc.
    • United States
    • Wyoming Supreme Court
    • April 20, 2000
    ...would conclude his manifestations to mean. Shrum v. Zeltwanger, 559 P.2d 1384, 1387 (Wyo.1977); accord, Wyoming Game and Fish Comm'n v. Mills Co., 701 P.2d 819, 822 (Wyo.1985). As the doctors have correctly pointed out, we have embraced these While it is essential that the mutual assent of ......
  • State v. Davis Oil Co.
    • United States
    • Wyoming Supreme Court
    • November 25, 1986
    ...p. 632. Wyoming cases, although not specifically directed to an exception criterion are not inapposite. Wyoming Game & Fish Commission v. Mills Company, Wyo., 701 P.2d 819 (1985); State Highway Commission of Wyoming v. Brasel & Sims Construction Co., Inc., Wyo., 688 P.2d 871 (1984); Nationa......
  • Sinclair Wyo. Ref. Co. v. A & B Builders, Ltd.
    • United States
    • U.S. Court of Appeals — Tenth Circuit
    • February 22, 2021
    ...parts. Mountain W. Mines, Inc. v. Cleveland-Cliffs Iron Co. , 470 F.3d 947, 951 (10th Cir. 2006) (quoting Wyo. Game & Fish Comm'n v. Mills Co. , 701 P.2d 819, 822 (Wyo. 1985) ). Wyoming courts give contracts their "common sense and plain meaning," and "[t]he language of a contract is constr......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT