Zenith Radio Corp. v. Matsushita Elec. Indus. Co.

CourtU.S. District Court — Eastern District of Pennsylvania
Writing for the CourtPhilip J. Curtis, John Borst, Jr., Glenview, Ill., for Zenith Radio Corp., plaintiff
CitationZenith Radio Corp. v. Matsushita Elec. Indus. Co., 513 F.Supp. 1334 (E.D. Pa. 1981)
Decision Date27 March 1981
Docket NumberCiv. A. No. 74-2451,74-3247. MDL 189.
PartiesZENITH RADIO CORPORATION, Plaintiff, v. MATSUSHITA ELECTRIC INDUSTRIAL CO., LTD., et al., Defendants. NATIONAL UNION ELECTRIC CORPORATION, Plaintiff, v. MATSUSHITA ELECTRIC INDUSTRIAL CO., LTD., et al., Defendants. In re JAPANESE ELECTRONIC PRODUCTS ANTITRUST LITIGATION.

Blank, Rome, Comisky & McCauley by Edwin P. Rome, William H. Roberts, John Hardin Young, Arnold I. Kalman, Kathleen H. Larkin, Norman E. Greenspan, Lawrence S. Bauman, Philadelphia, Pa., for Zenith Radio Corp. and National Union Elec. Corp., plaintiffs.

Philip J. Curtis, John Borst, Jr., Glenview, Ill., for Zenith Radio Corp., plaintiff.

Mudge Rose Guthrie & Alexander by Donald J. Zoeller, John P. Hederman, Thomas P. Lynch, Howard C. Crystal, Robert A. Jaffe, Shelly B. O'Neill, Mark K. Neville, Jr., New York City, Drinker, Biddle & Reath by Patrick T. Ryan, Philadelphia, Pa., for Tokyo Shibaura Elec. Co., Ltd. and Toshiba America, Inc., defendants; defense coordinating counsel.

Duane, Morris & Heckscher by Henry T. Reath, Terry R. Broderick, Philadelphia, Pa., Crummy, Del Deo, Dolan & Purcell by John T. Dolan, Arnold B. Calmann, Newark, N. J., Seki, Jarvis & Lynch by Hoken S. Seki, Richard O. Briggs, Chicago, Ill., for Mitsubishi Elec. Corp. and Mitsubishi Elec. Sales America, Inc.

Reid & Priest by Charles F. Schirmeister, Robert J. Lynch, New York City, L. Peter Farkas, Washington, D. C., for Mitsubishi Corp. and Mitsubishi Intern. Corp., defendants.

Weil, Gotshal & Manges by Ira M. Millstein, A. Paul Victor, Joel B. Harris, Kevin P. Hughes, Robert K. Hood, H. Adam Prussin, Harry M. Davidow, Jeffrey L. Kessler, Stuart Peim, Lenore Liberman, Gayle E. Hanlon, Makoto Matsuo, New York City, Morgan, Lewis & Bockius by Raymond T. Cullen, Philadelphia, Pa., for Matsushita Elec. Indus. Co., Ltd., Matsushita Elec. Corp. of America, Matsushita Electronics Corp., Matsushita Elec. Trading Co., and Quasar Electronics Corp., defendants.

Metzger, Shadyac & Schwarz by Carl W. Schwarz, Michael E. Friedlander, William H. Barrett, Stephen P. Murphy, William B. T. Mock, Jr.; Tanaka, Walders & Ritger by H. William Tanaka, Lawrence R. Walders, B. Jenkins Middleton, Washington, D. C., Hunt Kerr Bloom & Hitchner, by Charles J. Bloom, Philadelphia, Pa., for Hitachi, Ltd., Hitachi Sales Corp. of America, and Hitachi Kaden Hanbai Kabushiki, Kaisha, defendants.

Wender, Murase & White by Peter J. Gartland, Gene Yukio Matsuo, Peter A. Dankin, Lance Gotthoffer, New York City, for Sharp Corp. and Sharp Electronics Corp., defendants.

Whitman & Ransom by Patrick H. Sullivan, Dugald C. Brown, James S. Morris, Kevin R. Keating, Michael S. Press, New York City, Hunt Kerr Bloom & Hitchner, by Charles J. Bloom, Philadelphia, Pa., for Sanyo Elec., Inc., Sanyo Elec. Co., Ltd., Sanyo Mfg. Co., and Sanyo Elec. Trading Co., Ltd., defendants.

Arnstein, Gluck, Weitzenfeld & Minow by Louis A. Lehr, Jr., Stanley M. Lipnick, John L. Ropiequet, Chicago, Ill., for Sears, Roebuck & Co., defendant.

Rosenman, Colin, Freund, Lewis & Cohen by Asa D. Sokolow, Renee J. Roberts, Marc Rowin, Kaye, Scholer, Fierman, Hays & Handler by Joshua F. Greenberg, Randolph S. Sherman, David D. Chazin, New York City, Wolf, Block, Schorr & Solis-Cohen by Franklin Poul, Philadelphia, Pa., for Sony Corp. and Sony Corp. of America, defendants.

Kirkland & Ellis by Thomas P. Coffey, E. Houston Harsha, Karl F. Nygren, Chicago, Ill., for Motorola, Inc., defendant.

MEMORANDUM AND ORDER

(Pretrial Order No. 308)

(Rule 54(b) Certification)

EDWARD R. BECKER, District Judge.

In the accompanying opinion and order, 513 F.Supp. 1100, we have granted summary judgment in favor of the defendants on all of plaintiffs' remaining claims. Still outstanding in the case, however, are defendants' counterclaims alleging: (1) that Zenith violated the Robinson-Patman Act and Sections 1 and 2 of the Sherman Act by horizontal and vertical price-fixing arrangements, market allocations, and "key dealer preferences"; and (2) that Zenith sought to interfere with its competitors, including the counterclaimants, "by every means available, including the submission of complaints, petitions, testimony and other information to various federal governmental agencies and officials, federal courts, and the United States Congress which were based upon sham, false and misleading allegations and information, without regard to the truth or merits of the claims made."1 Given the existence of defendants' counterclaims, we must now decide whether to certify the summary judgment as final under Federal Rule of Civil Procedure 54(b), thereby making it immediately available for appellate review.2

Rule 54(b) provides in pertinent part:

When more than one claim for relief is presented in an action, whether as a claim, counterclaim, crossclaim, or third-party claim, or when multiple parties are involved, the court may direct the entry of a final judgment as to one or more but fewer than all of the claims or parties only upon an express determination that there is no just reason for delay and upon an express direction for the entry of judgment.

The purpose of Rule 54(b) is to reduce the probability that delay will result in substantial hardship and unfairness to the parties in complex multiple-claim actions arising from the liberal federal joinder provisions. The trial court is given the discretion to certify certain claims as final before the ultimate adjudication of all issues, after weighing the dangers of piecemeal review against the necessity of assuring that the interests of judicial administration and equity are served. See 6 Moore's Federal Practice ¶ 54.27, at 325 (2d ed. 1976).

Before Rule 54(b) certification may be granted, several requirements must be satisfied. First, the action must involve multiple claims for relief or multiple parties. Second, the decision involving one or more of the claims and affecting one or more of the parties must be a final judgment. Third, there must be no just reason for delay in appealing the case until all issues are adjudicated. See generally 10 C. Wright & A. Miller, Federal Practice and Procedure.

The first requirement is obviously met here, as this case involves both multiple parties and multiple claims. The second requirement is just as easily fulfilled. The Supreme Court in its recent decision, Curtiss-Wright Corp. v. General Electric Co., 446 U.S. 1, 100 S.Ct. 1460, 64 L.Ed.2d 1 (1980), explained the requirement as meaning that

It must be a "judgment" in the sense that it is a decision upon a cognizable claim for relief, and it must be "final" in the sense that it is "an ultimate disposition of an individual claim entered in the course of a multiple claims action."

446 U.S. at 7, 100 S.Ct. at 1465, quoting Sears Roebuck & Co. v. Mackey, 351 U.S. 427, 436, 76 S.Ct. 895, 900, 100 L.Ed. 1297 (1956). The summary judgment here meets this definition by reaching an ultimate disposition of plaintiffs' claims for relief.

The last requirement — that there be no just reason for delay — is the one about which there is the most controversy (and litigation), and was the requirement primarily under consideration in Curtiss-Wright. The district court in that case had granted summary judgment for the plaintiff on a $19 million claim for the balance due on contracts already performed. Despite the existence of the defendants' counterclaims under a release clause in the contracts that could have resulted in a setoff against the plaintiffs' claim, the district court certified the judgment as final under Rule 54(b). On defendants' appeal, the Third Circuit directed the district court to vacate its certification of finality under Rule 54(b) and dismissed the appeal. 597 F.2d 35 (3d Cir. 1979) (per curiam). The court held that its earlier decision in Allis-Chalmers Corp. v. Philadelphia Electric Co., 521 F.2d 360 (3d Cir. 1975), "dictates that the matter remains in status quo when non-frivolous counterclaims are pending, and in the absence of unusual or harsh circumstances," 597 F.2d at 36, and concluded that plaintiffs' inability to use the money from the judgment while counterclaims were litigated was not a sufficiently harsh circumstance to warrant upsetting the status quo.

The Supreme Court, however, vacated the Third Circuit's decision and upheld the district court's Rule 54(b) certification of finality of the summary judgment. The Supreme Court disagreed with the Third Circuit's conclusion that the possibility of a setoff and the presence of non-frivolous counterclaims prevented Rule 54(b) certification, declaring that

The mere presence of such non-frivolous counter- claims, however, does not render a Rule 54(b) certification inappropriate. If it did, Rule 54(b) would lose much of its utility.... Like other claims, their significance for Rule 54(b) purposes turns on their interrelationship with the claims on which certification is sought.

446 U.S. at 9, 100 S.Ct. at 1465. The Court interpreted Rule 54(b)'s requirement that there be no just reason for delay as involving the consideration of two essential interests: judicial administration and equity. Noting that the district court had taken into account interests of judicial administration by determining the absence of such factors as the nonseverability of the claims and the possibility of repeated appeals on individual claims, the Court pointed out that Rule 54(b) certification could still be granted despite the presence of one of the above factors mitigating against certification as long as the district court found a sufficiently important reason for entering a judgment as final. Once the interests of judicial administration have been considered substantial deference must be given to the district court's reasonable determination of the equities in the case, since the district court is "the one most likely to be familiar with the case...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex
3 cases
  • Zenith Radio Corp. v. Matsushita Elec. Indus. Co.
    • United States
    • U.S. District Court — Eastern District of Pennsylvania
    • May 13, 1981
  • Zenith Radio Corp. v. Matsushita Elec. Indus. Co.
    • United States
    • U.S. District Court — Eastern District of Pennsylvania
    • December 10, 1981
    ...we have certified our grant of summary judgment for appellate review pursuant to Fed.R.Civ.P. 54(b). Zenith Radio Corp. v. Matsushita Elec. Indus. Co., 513 F.Supp. 1334 (E.D.Pa.1981). PTO 311, entered April 8, 1981, by preserving the Court's jurisdiction to consider a number of matters, has......
  • Glaziers and Glassworkers Union v. NEWBRIDGE SEC.
    • United States
    • U.S. District Court — Eastern District of Pennsylvania
    • January 27, 1993
    ...probability that delay will result in substantial hardship and unfairness to the parties." Zenith Radio Corp. v. Matsushita Electric Industrial Co., Ltd. et al., 513 F.Supp. 1334, 1336 (E.D.Pa.1981). The rule grants the district court the discretionary power to afford a remedy in the "infre......