Zulla Steel, Inc. v. A & M Gregos, Inc.

Decision Date13 May 1980
Citation174 N.J.Super. 124,415 A.2d 1183
PartiesZULLA STEEL, INC., a corporation of the State of New Jersey, Plaintiff-Respondent, v. A & M GREGOS, INC., a corporation of the State of New Jersey, Defendant-Appellant.
CourtNew Jersey Superior Court — Appellate Division

Giordano, Halleran & Crahay, Middletown, for defendant-appellant (Martin J. Arbus, Middletown, on the brief).

Himelman, Siegfried, Schneider & Freiberger, Red Bank, for plaintiff-respondent (William Himelman, Red Bank, on the brief).

Before Judges BISCHOFF, BOTTER and MORTON I. GREENBERG.

The opinion of the court was delivered by

MORTON I. GREENBERG, J. A. D.

Plaintiff brought this action against defendant alleging that defendant had breached a contract by not making progress payments when due on a subcontract for structural work being performed by plaintiff for defendant. The prime contract was for the expansion of the Elizabeth postoffice. Defendant was the prime contractor. Defendant counterclaimed for breach of contract, asserting that plaintiff had improperly performed under the contract. The case was tried without a jury. The trial judge in an oral opinion found in favor of plaintiff on the complaint and awarded damages in the amount of $39,075. The counterclaim was dismissed, the judge finding that the proofs supporting it were "totally inadequate." Defendant appeals.

The facts concerning execution of the contract are not disputed. Defendant was the prime contractor on the Elizabeth postoffice expansion project. On June 16, 1975 plaintiff and defendant entered into a written subcontract for structural steel and related work on the project. The agreed price was $340,000, to be paid in installments. Specifically, the contract provided that payment would be made as follows:

90% of the value of the work completed and approved by Owner and/or the General Contractor, during the progress of the work, which shall be paid on or about the fifteenth day of each succeeding month. The retained percentage shall be paid thirty days after the completion and acceptance of the captioned job and receipt of final payment thereof by the General Contractor.

Defendant's contract with the postoffice provided for installment payments. It was required to submit periodic applications and certificates for payment. These applications included a "Trade Payment Tabulation" showing a description of the work performed for the postoffice. The tabulation reflected the scheduled value of the work for each item as agreed between defendant and the postoffice, the work completed on each item shown on previous applications for payment, the additional work done reflected on the current application, the total of all work completed expressed both in terms of money and percentages for each item, and the money amount left to be earned on completion of each item. The scheduled value of plaintiff's work as between defendant and the postoffice reflected in the tabulation was $370,000.

The evidence showed that the following procedure was adopted for defendant to obtain payment from the postoffice. There was a monthly job meeting of a postoffice representative, a construction manager, an architect's representative and defendant's project manager. These four persons would review the items on the tabulation and agree on what work had been completed. This included work performed by plaintiff. After agreement was reached defendant would prepare the formal application and certificate for payment with the tabulation and submit them to the postoffice for payment.

It is not disputed that plaintiff started performing under the contract in the summer of 1975. It continued working into 1976 but at that time left the job. By telegram from defendant on March 23, 1976 plaintiff was told to return to the job or its contract would be terminated. Plaintiff did not return. Plaintiff was paid $260,712 on the contract price and an undisputed extra of $1,480. It is not disputed that plaintiff did not compete the contract.

The record makes it clear that from defendant's own submissions to the postoffice plaintiff was not paid the progress payments in accordance with its contract. Defendant's first tabulation and certificate dated August 14, 1975 shows nothing due for plaintiff's work. Certificate two, dated September 5, 1975, shows $10,000 for plaintiff's work. Certificate three, dated October 2, 1975, shows $212,195 for plaintiff's work after the previous $10,000 application. Certificate three was erroneous because certificate four, dated November 4, 1975, deleted the $212,195 but provided for a new figure of $120,000 on that application so that with the original $10,000 the work valued to the postoffice to date had been $130,000. Certificate five, dated November 14, 1975, reflected $174,000 on that application for plaintiff's work, so that plaintiff had completed $304,000 work by no later than November 14, 1975. This figure was 82.16% of $370,000. Thus, since plaintiff was to be paid $340,000 on the contract, plaintiff should have been paid $279,344, which is 86.16% of $340,000, by on or about December 15, 1975 for work done by November 14, 1975, less retainage of 10%, or $251,410. In fact, by December 15, 1975 plaintiff was paid $118,792 against invoices of $276,508. Plaintiff was next paid $133,352 on January 9, 1976. Certificate six, dated November 25, 1979, showed that plaintiff had done $10,500 more work. Additional money was due plaintiff by December 15, 1975 for this work as well. Certificate seven, dated January 6, 1976, showed that plaintiff had performed $7,000 more work. Finally certificate eight, dated March 5, 1976, showed plaintiff had done $2,700 more work. As noted, by December 15, 1975 plaintiff had been paid $118,792. Plaintiff received additional payments of $133,352 on January 9, 1976 and $8,568 on February 24, 1976 and thus was paid $260,712 overall.

The trial judge held that defendant, by reason of its delinquencies in payments, had breached the contract with plaintiff, and we agree. The submissions by defendant to the postoffice require this holding. We do note, however, that the trial judge related defendant's obligation to pay plaintiff to the rendering of invoices by plaintiff to defendant. We do not agree with that analysis because payment was required only after approval by the postoffice and/or defendant, and then on or about the fifteenth day of the following month following approval. But nevertheless we concur in the result reached that defendant breached the contract. In fact, defendant has never paid plaintiff for the full amount of work performed by plaintiff by November 14, 1975 and has been materially in default since December 15, 1975 or thereabouts. Plaintiff presented substantial credible evidence that defendant's failure to pay plaintiff meant that plaintiff could not pay its subcontractor and thus could not complete its contract with defendant. The trial judge accepted this testimony and so do we. Rova Farms Resort v. Investors Ins. Co., 65 N.J. 474, 483-484, 323 A.2d 495 (1974). Under the circumstances there can be no question but that defendant's breach of contract was material. Defendant's failure to pay was not justified by any alleged shortcomings in plaintiff's performance. The trial judge found that the assertion by defendant that plaintiff improperly performed had not been substantiated. We accept and affirm these findings which resulted in the dismissal of the counterclaim. Ibid.; R. 2:11-3(e)(1)(A).

Since defendant breached its contract we must determine whether the breach justified plaintiff in abandoning the project. It is true that it has been held that where a contract is entire so that the payment of the consideration in installments is not for a particular performance, nonpayment does not justify the contractor in failing to complete the work. Magliaro v. Modern Homes, Inc., 115 N.J.L. 151, 155, 178 A. 733 (E. & A. 1935); McGraw v. Johnson, 42 N.J.Super. 267, 126 A.2d 203 (App. Div. 1956). But there is contrary authority. Watson v. Auburn Iron Works, Inc., 23 Ill.App.3d 265, 318 N.E.2d 508 (1974). Certainly the current approach in contract construction is to honor the expressed or presumed intention of the parties. Fidelity Land Develop. Corp. v. Rieder & Sons Bldg. & Develop. Co., 151 N.J.Super. 502, 377 A.2d 691 (App. Div. 1977). We find it impossible to believe that in a major construction project the parties would expect that a subcontractor would be obliged to continue working even though there were material delays in payment to it. Ordinarily the parties would expect that the subcontractor...

To continue reading

Request your trial
15 cases
  • J.L. Davis & Associates v. Heidler
    • United States
    • New Jersey Superior Court — Appellate Division
    • March 30, 1993
    ... ... On June 10, 1988, Davis removed its steel support equipment which had been under Juckett's house ... -22, 405 A.2d 393 (1979); Atlantic Northern Airlines, Inc. v. Schwimmer, 12 N.J. 293, 301, 96 A.2d 652 (1953); ... 324, 327, 84 A.2d 628 (App.Div.1951); accord Zulla Steel, Inc. v. A. & M. Gregos, Inc., 174 N.J.Super. 124, ... ...
  • In re Technology for Energy Corp.
    • United States
    • U.S. Bankruptcy Court — Eastern District of Tennessee
    • May 12, 1992
    ... ... SERVICE ELECTRIC & GAS CO., & Bechtel Engineering Co., Inc., Plaintiffs, ... TECHNOLOGY FOR ENERGY CORP., & American ... 83, 134 A. 771 (1926); Zulla Steel, Inc. v. A & M Gregos, Inc., 415 A.2d 1183 ... ...
  • John F. Harkins Co., Inc. v. Waldinger Corp.
    • United States
    • U.S. Court of Appeals — Third Circuit
    • August 20, 1986
    ... ... See also United States v. Cleveland Electric Co., 373 F.2d 585 (4th Cir.1967); Central Steel Erection Co. v. Will, 304 F.2d 548 (9th Cir.1962). They suggest that there is no necessary ... See, e.g., Zulla Steel, Inc. v. O. & M. Gregos, Inc., 174 N.J.Super. 124, 415 A.2d 1183 (App.Div.1980). In that ... ...
  • Linan-Faye Const. v. Housing Authority of Camden
    • United States
    • U.S. District Court — District of New Jersey
    • March 4, 1998
    ...995 F.Supp. 520 ... LINAN-FAYE CONSTRUCTION CO., INC., Plaintiff, ... HOUSING AUTHORITY OF THE CITY OF CAMDEN ... Cf. Zulla ... Cf. Zulla Steel ... Cf. Zulla Steel, Inc. v. A & M Gregos ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT