Hill's Pet Nutrition, Inc. v. Fru-Con Const. Corp.

Decision Date02 January 1997
Docket NumberFRU-CON,No. 96-1476,96-1476
Citation101 F.3d 63
PartiesHILL'S PET NUTRITION, INC., Plaintiff-Appellee, v.CONSTRUCTION CORPORATION and Fru-Con Engineering Inc., Defendants-Appellants.
CourtU.S. Court of Appeals — Seventh Circuit

Terrill D. Albright, John Joseph Tanner, Baker & Daniels, Indianapolis, IN, Sherman A. Botts, Lathrop & Gage, Kansas City, MO, for Plaintiff-Appellee.

Donald J. Graham, Paul A. Bokota, Bingham, Summers, Welsh & Spilman, Indianapolis, IN, Andrew W. Manuel, Michael E. Wilson, Greensfelder, Hemker & Gale, St. Louis, MO, for Defendants-Appellants.

Before CUMMINGS, BAUER, and EASTERBROOK, Circuit Judges.

EASTERBROOK, Circuit Judge.

Parties who have ongoing business relations can establish a contract even when they have not been able to agree on all terms, and the mirror-image rule applicable to executory agreements therefore has not been satisfied. See Roberts & Schaefer Co. v. Merit Contracting, Inc., 99 F.3d 248 (7th Cir.1996); Restatement (2d) of Contracts § 34(2) (1981); E. Allan Farnsworth, I Farnsworth on Contracts § 3.8c (1990). A corollary to this principle is that the contract contains only the agreed-on terms; one side cannot use partial agreement to enforce proposals to which the other side did not assent. Venture Associates Corp. v. Zenith Data Systems Corp., 96 F.3d 275 (7th Cir.1996). That corollary is dispositive today.

Hill's Pet Nutrition hired Fru-Con Construction and Fru-Con Engineering to renovate and enlarge its pet food plants. Fru-Con agreed to do the work on a cost-plus basis, with incentive payments for keeping total costs down. While corporate executives and their lawyers were negotiating the precise terms of a master agreement to govern the $200 million deal, Fru-Con commenced one large project and a few smaller ones under oral understandings. Work began in March 1994. Negotiations over basic terms went smoothly, but the parties ultimately could not agree on some fundamental issues: how "cost" would be defined (specifically, what percentage of salaried employees' wages would be deemed to represent the cost of fringe benefits such as pensions and health care); whether certain costs would be estimated from a schedule or calculated exactly; and whether Hill's would guarantee Fru-Con a minimum profit even if, because of cost overruns, the incentive clauses could expose Fru-Con to loss. Hill's discharged Fru-Con in November 1995, and each believes that the other owes it money. Hill's commenced litigation under the diversity jurisdiction, and Fru-Con demanded arbitration--which Hill's resisted on the ground that the parties' inability to complete their negotiations meant that it is not obliged to arbitrate. After receiving testimony, the district judge concluded that each side had signed a different version of the proposed master agreement and held that they had therefore not agreed on anything at all, precluding the possibility of arbitration. Fru-Con took an immediate appeal under 9 U.S.C. § 16(a)(1)(A).

One of Fru-Con's arguments on appeal--that Hill's and Fru-Con really finished the master agreement, and that what the district judge saw as deal-breakers were just typographical errors that it was entitled to correct without need of further approval from Hill's--misconceives the role of an appellate court. Unless the district court's findings of fact are clearly erroneous, we must accept them. Anderson v. Bessemer City, 470 U.S. 564, 105 S.Ct. 1504, 84 L.Ed.2d 518 (1985). These findings are well supported, so we must take it that the parties never came to closure on all terms of the master agreement. The district judge thought that lack of agreement on a single term means that there is no contract on any term. That may be so when the negotiations are wholly anticipatory, but the parties have not given us any reason to believe that Kansas and Indiana (the two states whose law might govern; we need not decide which does) depart from the rule that, when the parties commence performance with some issues still to be resolved, their agreement includes all of the terms that have been mutually approved. See International Creative Management, Inc. v. D & R Entertainment Co., 670 N.E.2d 1305 (Ind.App.1996); Butler v. Westgate State Bank, 3 Kan.App.2d 403, 596 P.2d 156 (1979). Both sides signed drafts of the master agreement...

To continue reading

Request your trial
7 cases
  • Linea Navira De Cabotaje v. Mar Caribe
    • United States
    • U.S. District Court — Middle District of Florida
    • 7 Mayo 2001
    ...to negate the unequivocally expressed intent of both parties to submit disputes to arbitration"); Hill's Pet Nutrition, Inc. v. Fru-Con Constr. Corp., 101 F.3d 63, 65 (7th Cir.1996)(compelling arbitration where parties each signed draft agreements with an arbitration clause and began to per......
  • Bahoor v. Varonis Sys., Inc.
    • United States
    • U.S. District Court — Northern District of Illinois
    • 28 Diciembre 2015
    ...scope of the arbitration provision, ordinary state law contract principles are applied.” (citing Hill's Pet Nutrition, Inc. v. Fru–Con Construction Corp ., 101 F.3d 63, 65–66 (7th Cir.1996) )). Here, the Agreement contains an expansive arbitration provision that covers “any and all controve......
  • Towers v. City of Chicago
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • 16 Abril 1999
    ... ... Const. amend. VIII. The parties have not disputed ... v. Kelco Disposal, Inc., 492 U.S. 257, 265, 109 S.Ct. 2909, 106 L.Ed.2d ... ...
  • Wisconsin v. Ho-Chunk Nation
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • 14 Enero 2008
    ...to the Compact, the district court was charged with determining the scope of this arbitration agreement. Hill's Pet Nutrition v. Fru-Con Constr. Corp., 101 F.3d 63, 65 (7th Cir.1996). In determining whether the Nation and State agreed to arbitrate the claims brought by the State in its amen......
  • Request a trial to view additional results
1 books & journal articles
  • The inadvertent waiver of mandatory construction arbitration clauses.
    • United States
    • Florida Bar Journal Vol. 71 No. 9, October 1997
    • 1 Octubre 1997
    ...be interpreted as part of the writing." [30] Omega Construction, 382 N.W.2d at 841. See, Hills Pet Nunecian, Inc. v. Fur-Lon Construction, 101 F.3d 63 (7th Cir. 1996). The Seventh Circuit Court of Appeals held that although the parties agreed to an arbitration clause, the scope of that clau......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT