104 Contractors, Inc. v. RT GOLF ASSOCIATES, LP

Decision Date29 March 2000
Citation705 N.Y.S.2d 752,270 A.D.2d 817
Parties104 CONTRACTORS, INC., Respondent,<BR>v.<BR>R.T. GOLF ASSOCIATES, L.P., et al., Appellants, et al., Defendants. (Appeal No. 2.)
CourtNew York Supreme Court — Appellate Division

Present — Pine, J. P., Hayes, Scudder and Lawton, JJ.

Amended judgment unanimously affirmed with costs.

Memorandum:

R.T. Golf Associates, L.P. and R.T. Golf, Inc. (defendants) appeal from an amended judgment after a bench trial awarding plaintiff $92,920.88 on a mechanics' lien filed against property owned by defendants. Plaintiff subcontractor filed the mechanics' lien after defendants terminated the general contractor and required both plaintiff and the general contractor to cease all work on the job site. The lien was for site work for a golf driving range and included 9,816 cubic yards of fill dirt and 480 tons of stone for a road and building pad. Defendants contend that the amended judgment must be reversed because, at the time the lien was filed, there was nothing owed by defendants to the general contractor to which the lien could attach. We disagree.

It is well settled that the rights of a subcontractor are derivative of the rights of the general contractor and that a subcontractor's lien "must be satisfied out of funds due and owing from the owner to the general contractor" at the time the lien is filed (DiVeronica Bros. v Basset, 213 AD2d 936, 937; see also, Lien Law § 4 [1]; Strain & Son v Baranello & Sons, 90 AD2d 924, 925; Bunce v Fahey, 73 AD2d 632).

The general contractor, defendant Michael Valle, had no formal contract with defendants but their informal arrangement provided for payments based on a cost plus percentage basis. A mechanics' lien may be based on such a cost plus percentage price (see, e.g., Fyfe v Sound Dev. Co., 235 NY 266, 269). Revised cost estimates were made as the project plans were revised but no ceiling price was established. Some progress payments were made during the course of the work. Supreme Court determined that, based on that informal arrangement, money became due and owing to Valle when he presented a bill for $78,528 to defendants shortly before he was discharged. We conclude that money became due and owing under this cost plus agreement when plaintiff established that defendants owed Valle for the work performed by plaintiff while Valle was the general contractor (see generally, DiVeronica Bros. v Basset, supra, at 938). The record supports the court's finding that the parties understood that cost could not be determined until the work had been performed by Valle or his subcontractors. Although defendants may not have been aware of the cost of the work being performed by plaintiff, the court found that they requested changes in the grade that required the quantity of fill...

To continue reading

Request your trial
5 cases
  • Joel Shafferman, the Liquidating Tr. of JMK Constr. Grp., Ltd. v. Queens Borough Pub. Library (In re JMK Constr. Grp., Ltd.)
    • United States
    • U.S. Bankruptcy Court — Southern District of New York
    • December 20, 2013
    ...of funds due and owing from the owner to the general contractor’ at the time the lien is filed.” 104 Contractors, Inc. v. R.T. Golf Assocs., L.P., 270 A.D.2d 817, 705 N.Y.S.2d 752, 754 (2000) (quoting DiVeronica Bros. v. Basset, 213 A.D.2d 936, 624 N.Y.S.2d 296, 297 (1995)). Thus, “[u]nder ......
  • Price Trucking Corp. v. Norampac Indus., Inc.
    • United States
    • U.S. Court of Appeals — Second Circuit
    • March 18, 2014
    ...Assocs., Inc. v. DiNardi Constr. Corp., 917 F.2d 1332, 1335 (2d Cir.1990); 104 Contractors, Inc. v. R.T. Golf Assocs., L.P., 270 A.D.2d 817, 818, 705 N.Y.S.2d 752, 754 (4th Dep't 2000). In light of our conclusion that CERCLA does not expressly create the liability that the plaintiff seeks t......
  • NYU Hosp. Ctr. v. HRH Constr. LLC (In re HRH Constr. LLC)
    • United States
    • U.S. Bankruptcy Court — Southern District of New York
    • August 2, 2011
    ...vested upon filing and subsequent failure to perform does not preclude or reduce recovery. 104 Constr., Inc. v. R.T. Golf Assocs., L.P., 270 A.D.2d 817, 819 (N.Y. App. Div. 4th Dep't 2000) (citations omitted). A mechanic's lien will not be defeated by the subsequent abandonment of the proje......
  • SR City Entm't. LLC v. Yoon & Guy Elec.
    • United States
    • New York Supreme Court
    • July 21, 2011
    .... See Davidson Pipe Supply Co. v. Wyoming County Indus. Dev. Agency, 85 N.Y.2d 281,' 285 (1995); 104 Contra, v. R.T. GolfPage 3Assocs., 270 A.D.2d 817, 818 (4th Dep't 2000); Town & Country Linoleum & Carpet Co. v. Tropea, 262 A.D.2d 1045, 1046 (4th Dep't 1999). Although already provided rep......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT