Dennison Const. Co. v. McKenna
Decision Date | 13 February 1912 |
Citation | 204 N.Y. 404,97 N.E. 859 |
Parties | DENNISON CONST. CO. v. McKENNA et al. |
Court | New York Court of Appeals Court of Appeals |
OPINION TEXT STARTS HERE
Appeal from Supreme Court, Appellate Division, Second Department.
Action by the Dennison Construction Company against Patrick H. McKenna and others. From a judgment of the Appellate Division (129 App. Div. 600,113 N. Y. Supp. 1071) modifying a judgment of the Special Term, defendants McKenna and Wood appeal. Both judgments reversed, and new trial ordered.
This action was brought to foreclose a mechanic's lien filed by the plaintiff as contractor against certain premises belonging to the defendant Manneschmidt and the complaint is in the form usual in such cases. The owner answered, alleging, among other things, that the plaintiff failed to perform the contract entered into between them for the construction of a building on the premises in question in many respects, whereby she sustained damages to the amount of $4,453 for which sum she demanded judgment against the plaintiff. A reply was served. The answer of the defendants McKenna and Wood is not printed in the record, although it is stated that they served one, appeared by counsel upon the trial, and without objection from any party furnished evidence tending to show that they, as subcontractors, performed work and furnished material worth $1,254.44 in erecting the building. No part of this sum has been paid, and they filed a lien therefor in due time and form.
The trial court found, in substance, that on the 30th of January, 1906, the plaintiff entered into a contract with the defendant Manneschmidt whereby it agreed to furnish the materials, do the work, and erect a brick dwelling for her according to certain plans and specifications. In consideration thereof, she agreed to pay the plaintiff the sum of $11,800 in five payments as the work progressed; the fourth and fifth being set forth as follows: Among the provisions of the contract were the following:
written notice to the contractors, to provide any such labor or materials, and to deduct the cost thereof from any money then due or thereafter to become due to the contractor under this contract; and if the architect shall certify that such refusal, neglect or failure is sufficient ground for such action, the owner shall also be at liberty to terminate the employment of the contractors for the said work and to enter upon the premises and take possession, for the purpose of completing the work included under this contract, of all materials, tools and appliances thereon, and to employ any other person or persons to finish the work, and to provide the materials therefor; and in case of such discontinuance of the employment of the contractors they shall not be entitled to receive any further payment under this contract until the said work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid under this contract shall exceed the expense incurred by the owner in finishing the work, such excess shall be paid by the owner to the contractors; but if such expense shall exceed such unpaid balance, the contractors shall pay the difference to the owner. The expense incurred by the owner as herein provided, either for furnishing materials or for finishing the work, and any damage incurred through such default, shall be audited and certified by the architect, whose certificate thereof shall be conclusive upon the parties. * * *
The trial court further found that the owner made the first, second, and third payments mentioned in the contract, amounting to the sum of $5,700; that on June 30, 1907, the plaintiff demanded the fourth payment, but the owner refused to make it; ‘that on the 5th of July, 1907, the plaintiff ceased furnishing materials and performing work under the contract, and refused to perform any further work or furnish any other materials, for the reason that it had not received the fourth payment of $3,500; that at the time the plaintiff demanded the fourth payment, and at the time it refused to do any further work or furnish any other materials in the performance of the said contract, the plaintiff had not performed its contract up to the period of performance which would entitle it to the fourth payment thereunder, and the work already done by it and materials already furnished were inferior and different from those called for by the contract in the following particulars.’ The findings then specified 26 separate and independent items of defective work, defective materials, and failures to comply with the plans and specifications. Some of the defects apparently could not be remedied without taking down the building or a part thereof, such as the use of 2 by 6 inch rafters instead of 3 by 6; wall plate 3 by 10 instead of 4 by 12; 1 1/4 bridging on beams instead of 2 by 3. although ‘the specifications required the owner to furnish to the plaintiff a survey of the property on which the...
To continue reading
Request your trial- Stevens v. Laub
-
Plowden & Roberts, Inc. v. Conway, 220
...the contract with Conway and not merely to terminate Conway's employment under the terms of the contract. Dennison Construction Co. v. McKenna, 1912, 204 N.Y. 404, 97 N.E. 859. The contract did not prevent Plowden from thus asserting against Conway its common law remedy of an action for dam......
-
Schmidt v. Duggan
... ... That the owner had a right to complete the contract has been well established in Dennison Construction Co. v. Mannerschmidt, 204 N.Y. 404, 97 N.E. 859; Van Clief v. Van Vechten, 130 N.Y ... ...
-
Farrell v. Farrell
... ... Dennison Construction Co. v. Manneschmidt, 204 N. Y. 404, 97 N. E. 859.It is to be regretted that this long ... ...