A.L. Huber & Son, Inc. v. Jim Robertson Plumbing, Inc.

Decision Date27 September 1988
Docket NumberNo. WD,WD
Citation760 S.W.2d 496
PartiesA.L. HUBER & SON, INC./Clevenger Homes, Inc., Joint Venture, Appellants, v. JIM ROBERTSON PLUMBING, INC., Respondent. 40210.
CourtMissouri Court of Appeals

J. Michael Cronan, Kansas City, for appellants.

Vincent F. Igoe, Jr., Liberty, for respondent.

Before COVINGTON, P.J., and CLARK and GAITAN, JJ.

GAITAN, Judge.

This is a three-count claim for money damages filed by the plaintiff-appellant, A.L. Huber & Son, Inc./Clevenger Homes, Inc., Joint Venture, regarding an alleged oral contract entered into with the defendant-respondent, Jim Robertson Plumbing, Inc. The plaintiff-appellant appeals the judgment of the trial court finding that: (1) the defendant-respondent did not enter into an agreement with the alleged A.L. Huber/Clevenger Homes Joint Venture for performance of work on the project; (2) any alleged reliance by the Huber/Clevenger Joint Venture was unauthorized and unwarranted; and (3) the defendant-respondent's actions were not tortious, malicious, or intended to injure plaintiff-appellant.

The judgment of the trial court is affirmed.

This action arises out of a series of events concerning plumbing work to be done on the Three Fountains West project. The plaintiffs, A.L. Huber & Son, Inc. (A.L. Huber) and Clevenger Homes Company, Inc. are two separate corporations. Clevenger Homes initially submitted a bid to do construction on the Three Fountains West townhouse complex. All bids submitted to the project owner on February 11, 1986, were rejected. However, since Clevenger Homes was the lowest bidder, it was allowed to revise the project and submit another proposal.

In February of 1986, Clevenger contacted Jim Robertson Plumbing regarding plumbing work in the construction of the Three Fountains West project. Mr. Clevenger spoke with Robertson and gave him information to prepare a bid. The conversation also incorporated a discussion of changes to the original plans and specifications. Jim Robertson Plumbing picked up the original specifications and one set of drawings from Clevenger's office some time after February 11, 1986. The original bid from Jim Robertson Plumbing was for $223,756. However, on March 8, 1986, the bid was reduced to $218,686 because garage floor drains were omitted. Mr. Robertson testified that he was making the bid to Clevenger should Clevenger be awarded the general contract for the Three Fountains West project, and if the plans and specifications came back to Robertson in the form agreed.

The bid and discussion with Jim Robertson Plumbing occurred before negotiations began between A.L. Huber and Clevenger Homes concerning the joint venture. The need for a joint venture arose because Clevenger Homes could not obtain a satisfactory bond to do the work on the Three Fountains West project. Therefore, Clevenger Homes entered into a written joint venture agreement with A.L. Huber in April of 1986.

A.L. Huber signed a contract with the project owner as the general contractor. Clevenger Homes was listed as a subcontractor and received $40,000 for partial supervision of the project, and was to have received $30,000 up front to cover expenses. Clevenger Homes was not a guarantor on the bond that A.L. Huber obtained. The subcontract with A.L. Huber was dated June 1, 1986, but the typed contract date was May 20, 1986.

At around the end of April or beginning of May, 1986, Robertson was contacted by David Dukes, project manager for A.L. Huber. Mr. Dukes confirmed the $223,756 price and the deduction of $5,070 for omitting the garage floor drains. There was no discussion of specific terms other than the price. Mr. Robertson stated that it was not uncommon in the industry for employees of one company to "moonlight" as estimators for another company. However, Dukes testified that he stated to Robertson that he was calling on behalf of a joint venture between A.L. Huber and Clevenger Homes. To the knowledge and recollection of Robertson, Dukes did not tell him that A.L. Huber and Clevenger Homes had entered into a joint venture. Mr. Robertson and Dukes talked again near the end of May, 1986. Each time Dukes called, Robertson confirmed his bid.

In the middle of June, 1986, someone from Dukes' office called Jim Robertson Plumbing to inform them that revised plans and specifications were available. However, neither Robertson nor anyone from his office ever picked up the plans or returned the signed subcontract.

Mr. Robertson learned for the first time that A.L. Huber was the general contractor on the Three Fountains West project in late June. Mr. Robertson had informed his staff, prior to leaving on a trip at the end of June, to not agree to do work for A.L. Huber because of previous bad experiences between A.L. Huber and Jim Robertson Plumbing. Mr. Glover, the on-site superintendent for A.L. Huber, called Jim Robertson Plumbing the week prior to July 7 to inform them that work would be required to begin on July 7, 1986. He was told that Jim Robertson Plumbing was not going to perform the plumbing work on the contract.

A.L. Huber eventually contracted with Superior Plumbing to do the plumbing work on the Three Fountains West project for $252,694 based on the revised plans and specifications.

The question for an appellate court in a court-tried case is whether the findings of the trial court are supported by substantial evidence. Unless the judgment is against the weight of the evidence, or unless the court erroneously declares or applies the law, the judgment will be affirmed. Murphy v. Carron, 536 S.W.2d 30, 32 (Mo. banc 1976).

I. Promissory Estoppel

Appellant's first contention is that the trial court erred in finding that respondent, Jim Robertson Plumbing is not legally liable under a theory of promissory estoppel. This Court agrees with the trial court's finding. The essential elements that need to be proved under a theory of promissory estoppel are: (1) a promise; (2) detrimental reliance on the promise; (3) injustice can be avoided only by enforcement of the promise; and (4) the promisor should have or did in fact clearly foresee the precise action which the promisee took in reliance. Mark Twain Plaza Bank v. Lowell H. Listrom & Company, Inc., 714 S.W.2d 859, 863 (Mo.App.1986); Otten v. Otten, 632 S.W.2d 45, 49 (Mo.App.1982).

The Mark Twain Plaza Bank case is heavily relied on by the appellants. In that case the plaintiff bank obtained both an unconditional oral and written commitment from a stock brokerage firm that certain stock held by the firm would be available as collateral and could be transferred to the bank. The case at bar is distinguishable from the Mark Twain Plaza Bank case in that there was a conditional promise made by Jim Robertson Plumbing that Clevenger Homes be the general contractor on the Three Fountains West project. Here, the facts state that A.L. Huber was the general contractor while Clevenger Homes was a subcontractor. Upon cross-examination, Clevenger confirmed this conditional promise:

Q: Now as to what your agreement was with Mr. Robertson, you didn't get the job did you?

A: I didn't directly contract it.

Q: Well, sir, who signed the contract to build it?

A: Huber did.

Q: All right, sir. So the first condition you made with Robertson, you didn't fulfill--you didn't get the contract, true?

A: That's true.

Since the conditions of the promise were not met, neither Clevenger Homes nor A.L. Huber...

To continue reading

Request your trial
15 cases
  • Danella Southwest, Inc. v. Southwestern Bell Telephone Co.
    • United States
    • U.S. District Court — Eastern District of Missouri
    • October 16, 1991
    ...or did in fact clearly foresee the precise action which the promisee took in reliance. A.L. Huber & Son, Inc./Clevenger Homes, Inc. v. Jim Robertson Plumbing, Inc., 760 S.W.2d 496, 498 (Mo.App.1988). The first essential element of promissory estoppel is that the defendant has made a binding......
  • Mueller v. Abdnor
    • United States
    • United States Courts of Appeals. United States Court of Appeals (8th Circuit)
    • December 24, 1992
    ...and no fact essential to submissibility can be inferred absent a substantial evidentiary basis. A.L. Huber v. Jim Robertson Plumbing, Inc., 760 S.W.2d 496, 499 (Mo.App.1988). Such a rule prevents plaintiff from obtaining a windfall from a contract that might never have been performed even i......
  • Doe v. General American Life Ins. Co., 91-1957C(5).
    • United States
    • U.S. District Court — Eastern District of Missouri
    • March 16, 1993
    ...in fact clearly foresee the precise action which the promisee took in reliance. Cochran, at 289 citing A.L. Huber & Son v. Jim Robertson Plumbing, 760 S.W.2d 496, 498 (Mo.App.1988). The defendant must have made a binding offer in the form of a promise, and the promise must be sufficiently d......
  • Nutreance LLC v. Primark, LLC
    • United States
    • U.S. District Court — Eastern District of Missouri
    • July 10, 2020
    ...Solutions., Inc. v. PDQ Mfg., Inc., 395 F.3d 888, 896 (8th Cir. 2005) (business expectancy); A.L. Huber & Son, Inc. v. Jim Robertson Plumbing, Inc., 760 S.W.2d 496, 499 (Mo. Ct. App. 1988) (contract). Defendants argue that Plaintiffs have failed to show any valid business expectancy or that......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT