H. Sand & Co., Inc. v. Airtemp Corp.

Decision Date30 August 1990
Docket NumberNo. 83 Civ. 5722 (IBC).,83 Civ. 5722 (IBC).
Citation743 F. Supp. 279
PartiesH. SAND & CO., INC., Plaintiff, v. AIRTEMP CORPORATION, Defendant.
CourtU.S. District Court — Southern District of New York

Berman, Paley, Goldstein & Berman (Stuart Moskovitz, of counsel), New York City, for plaintiff H. Sand & Co., Inc.

Weissman, Celler, Spett & Modlin (John B. Sherman, of counsel), New York City, for defendant Airtemp Corp.

MEMORANDUM

IRVING BEN COOPER, District Judge.

Defendant moved for summary judgment, pursuant to Fed.R.Civ.P. 56(b), dismissing plaintiff's amended complaint. Plaintiff opposed defendant's motion; additionally, plaintiff moved for partial summary judgment pursuant to Fed.R.Civ.P. 56(a). In an opinion dated May 30, 1990, we granted defendant's motion for summary judgment and dismissed as moot plaintiff's motion for partial summary judgment. H. Sand & Co., Inc. v. Airtemp Corp., 738 F.Supp. 760 (S.D.N.Y.1990) ("the May 30 Opinion"). Plaintiff timely moved for reargument of the May 30 Opinion pursuant to Rule 3(j) of the Civil Rules for the United States District Courts for the Southern and Eastern Districts of New York ("Local Rule 3(j)"). Defendant opposes the motion.

The facts of this case are set forth at length in the May 30 Opinion; familiarity with them is assumed.

DISCUSSION
Reargument

Local Rule 3(j) provides, in pertinent part, that "there shall be served with the notice of motion for reargument a memorandum setting forth concisely the matters or controlling decisions which counsel believes the court has overlooked." (emphasis ours).

The standards governing motions for reargument are well established: they are to be granted only under limited circumstances. The "only proper ground on which a party may move to reargue an unambiguous order is that the court overlooked `matters or controlling decisions' which, had they been considered, might reasonably have altered the result reached by the court." Brignoli v. Balch Hardy & Scheinman, Inc., 735 F.Supp. 100, 101 (S.D.N.Y.1990) (quoting Adams v. United States, 686 F.Supp. 417, 418 (S.D.N.Y. 1988)). "Alternatively, the moving party may establish that the court failed to consider `factual matters that were put before the court on the underlying motion.'" The Travelers Ins. Co. v. Buffalo Reinsurance Co., 739 F.Supp. 209, 211 (S.D.N.Y.1990) (quoting Ashley Meadows Farm, Inc. v. American Horse Shows Ass'n, Inc., 624 F.Supp. 856, 857 (S.D.N.Y.1985). See also Suggs v. Capital Cities/ ABC, Inc., 122 F.R.D. 430, 432 (S.D.N.Y.1988). "The standard for granting a motion for reargument is strict in order to dissuade repetitive arguments on issues that have already been considered fully by the Court." Ruiz v. Commissioner of D.O.T. of City of New York, 687 F.Supp. 888, 890 (S.D.N.Y.), aff'd, 858 F.2d 898 (2d Cir.1988); B.A.M. Brokerage Corp. v. New York, 724 F.Supp. 146, 147 (S.D.N.Y.1989); Caleb & Co. v. E.I. DuPont De Nemours & Co., 624 F.Supp. 747, 748 (S.D.N.Y.1985). "Motions for reargument will be granted only if the Court overlooked `matters or controlling decisions' which, if considered by the Court, would have mandated a different result." Durant v. Traditional Investments Ltd., 1990 U.S. Dist. LEXIS 4768 (S.D.N.Y. April 25, 1990). See also, Ruiz, 687 F.Supp. at 890; Caleb, 624 F.Supp. at 748; Northberry Concrete Corp. v. The Hartford Ins. Group, 1990 WL 139638, 1990 U.S. Dist. Lexis 6840 (S.D.N.Y. June 6, 1990).

1. Controlling Decisions

In its memorandum in support of its motion for reargument, plaintiff does not claim that we overlooked any controlling decisions in arriving at our conclusion; indeed, plaintiff does not make any attempt to introduce any new controlling law. Plaintiff relies on one case to support its first argument that the fourth refrigeration unit ("Chiller 4") was not delivered until January, 1979. However, we addressed that case, City of New York v. Pullman, Inc., 662 F.2d 910 (2d Cir.1981), in detail in the May 30 Opinion. 738 F.Supp. at 766-69. Also in the May 30 Opinion, we comprehensively discussed and rejected plaintiff's contention as to when Chiller 4 was delivered, for that same argument, which was raised in the supporting papers to plaintiff's motion for reargument, was also raised in plaintiff's memorandum submitted in opposition to defendant's motion for summary judgment. Id. at 765-66.

We conclude we cannot grant plaintiff's motion for reargument on "controlling decisions" grounds for the simple reason that no new "controlling decisions" were introduced.

2. Factual Matters

Plaintiff asserts "that the Court misunderstood the nature of the March 31, 1978 shipment of Chiller 4." (Plaintiff's Memorandum In Support of Motion For Reargument, 1 ("Plaintiff's Memo")) Plaintiff maintains that this Court "ignored substantial unrefuted evidence submitted by the plaintiff" (Id. at 3), and specifically directs our attention to Exhibits 3, 4, and 5 ("the exhibits") to the Affidavit of Stuart J. Moskovitz In Opposition To Motion By Defendant ("Moskovitz Affidavit") as the evidence that we overlooked when considering the disposition of the earlier motions.

We set out plaintiff's position regarding the delivery of Chiller 4 in our statute of limitations discussion in the May 30 Opinion:

Sand's first contention is based upon the undisputed fact that the four chillers were shipped to its agent Associated between January and March 1978, yet chiller #4 was returned to Airtemp in November 1978 because defendant did not conduct a test run of the chiller prior to shipping it. Chiller #4 was shipped to Sand in January 1979 after it was tested. Thus, plaintiff avers, "tender of delivery" occurred in January 1979. As a result, Sand's cause of action would be saved since it initiated litigation in December 1982, which falls within the four year statute of limitation imposed by the U.C.C.

738 F.Supp. at 765-66 (emphasis ours).

The exhibits were before us prior to the issuance of the May 30 Opinion, and they were all thoroughly considered, explicitly or implicitly, when we made our final determination in the May 30 Opinion. We did not overlook or ignore the exhibits; we rejected plaintiff's argument based on those and other exhibits and supporting documents. Indeed, we would not have been able to recite the above-cited passage had we not considered the exhibits.

Assuming, arguendo, that we did fail to consider exhibits 3, 4 and 5 in our determination of the original motions, a review of those exhibits does not lead us to alter our original finding that the four chillers were delivered, and the statute of limitations commenced running, by March, 1978.

Plaintiff's second argument in its moving papers, claiming that defendant failed to establish a genuine issue of material fact, is introduced as follows: "as we explained in our memorandum originally submitted in opposition to defendant's motion for summary judgment...." (Plaintiff's Memo, 8) "A request for reargument is not an occasion to reassert arguments previously raised, but dismissed by the court." Bozsi Ltd. Partnership v. Lynott, 676 F.Supp. 505, 509 (S.D.N.Y.1987) (quoting Morgan Guar. Trust Co. of New York v. Garrett Corp., 625 F.Supp. 752, 756 (S.D. N.Y.1986), aff'd, 875 F.2d 307 (2d Cir. 1989)). See also Rosen v. Dick, 83 F.R.D. 540, 544 (S.D.N.Y.1979), modified on other grounds, 639 F.2d 82 (2d Cir.1980). Thus, since plaintiff's second argument was asserted and dismissed in the May 30 Opinion, and since pla...

To continue reading

Request your trial
3 cases
  • Eisert v. Town of Hempstead
    • United States
    • U.S. District Court — Eastern District of New York
    • March 6, 1996
    ...controlling decisions" which, if it had considered such issues, "would have mandated a different result." H. Sand & Co., Inc. v. Airtemp Corp., 743 F.Supp. 279, 280 (S.D.N.Y.1990), aff'd in part and rev'd in part, 934 F.2d 450 (2d Cir.1991), citing Durant v. Traditional Investments, Ltd., 1......
  • US v. All Right, Title & Interest In Property
    • United States
    • U.S. District Court — Southern District of New York
    • December 12, 1990
    ...888, 890 (S.D.N.Y.1988); B.A.M. Brokerage Corp. v. New York, 724 F.Supp. 146, 147 (S.D.N.Y. 1989); H. Sand & Co., Inc. v. Airtemp Corp., 743 F.Supp. 279 (S.D.N.Y.1990) (Cooper, J.), we granted, on September 25, 1990, the government's motion for In 141st Street Corp., the claimant, the corpo......
  • H. Sand & Co., Inc. v. Airtemp Corp.
    • United States
    • U.S. Court of Appeals — Second Circuit
    • June 3, 1991
    ...fact--whether the shipment of chiller # 4 in 1978 was a "tender of delivery" sufficient to trigger the statute of limitations. 743 F.Supp. 279 (S.D.N.Y.1990). From these several orders, Sand I Tender of Delivery We first consider whether the district court properly granted summary judgment ......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT