PartiesCrafton, Tull, Sparks & Associates, Inc., Appellant v. Ruskin Heights, LLC ; Metropolitan National Bank; William B. Benton, Jr.; J. Kevin Adams; Edward A. Labry, III; John G. Brittingham; Carlen G. Hooker; Edward F. Davis; Dirk W. Van Veen; and David Ruff, in his official capacity as Tax Collector for Washington County, Arkansas, Appellees
CourtArkansas Supreme Court

Matthews, Campbell, Rhoads, McClure & Thompson, P.A., by:

David R. Matth ews, Rogers, and Sarah L. Waddoups, for appellant.

McMullan Law Firm, Little Rock, by: Marian Major McMullan, for appellees.

Opinion

JIM HANNAH, Chief Justice

Appellant Crafton, Tull, Sparks & Associates, Inc. (CTSA) appeals an order of the Washington County Circuit Court granting summary judgment in favor of appellees Ruskin Heights, LLC; Metropolitan National Bank (Metropolitan); William B. Benton, Jr.; J. Kevin Adams; Edward A. Labry, III; John G. Brittingham; Carlen G. Hooker; Edward F. Davis; Dirk W. Van Veen; and David Ruff, in his official capacity as Tax Collector for Washington County. For reversal, CTSA argues that the circuit court improperly refused to grant its lien priority over Metropolitan's mortgage lien that was recorded after construction commenced. CTSA also asserted that its lien should relate back to the commencement of construction. We have jurisdiction pursuant to Arkansas Supreme Court Rule 1–2(a)(7) (2014), as we have dismissed two previous appeals. See Crafton, Tull, Sparks & Assocs. v. Ruskin Heights, LLC, 2013 Ark. 85 (“Crafton II ”) (dismissing without prejudice for lack of a final order); Crafton, Tull, Sparks & Assocs. v. Ruskin Heights, LLC, 2012 Ark. 56, 2012 WL 401611 (“Crafton I ”) (dismissing without prejudice for lack of a final order). We affirm.

An extensive recitation of the facts and procedure was set forth in Crafton I, 2012 Ark. 56, and we provide the relevant facts concerning this appeal. On September 17, 2007, Metropolitan and Ruskin Heights executed a promissory note and loan agreement for $8,606,250 to finance construction of a residential subdivision on real property located in Washington County. As security for the note, Ruskin Heights executed a mortgage on the real property in favor of Metropolitan. In addition, William B. Benton, Jr.; J. Kevin Adams; Edward A. Labry, III; John G. Brittingham; Carlen G. Hooker; Edward F. Davis; and Dirk W. Van Veen executed personal guarantees.

Nabholz Construction Company began construction on the project on the morning of October 1, 2007, and Metropolitan filed its mortgage that afternoon. CTSA subsequently began working on the project for Ruskin Heights. On September 25, 2009, Jim Tull, CTSA's chief financial officer, filed an “Architect's and Engineer's Account and Affidavit of Account” stating that Ruskin Heights owed CTSA $37,239.45. Ruskin Heights received notice of CTSA's lien filing on September 28, 2009. The $37,239.45 balance remained unpaid. Meanwhile, on August 3, 2009, Metropolitan filed a foreclosure complaint alleging breach of note and breach of guaranties against Ruskin Heights; William B. Benton, Jr.; J. Kevin Adams; Edward A. Labry, III; John G. Brittingham; Carlen G. Hooker; Edward F. Davis; Dirk W. Van Veen; and David Ruff in his official capacity as Tax Collector for Washington County.

On November 2, 2009, CTSA filed a complaint asserting an engineer's lien against Ruskin Heights. Thereafter, on December 7, 2009, the circuit court granted CTSA's motion for consolidation and joinder of the two complaints. On December 14, 2009, CTSA filed an amended complaint against Ruskin Heights and Metropolitan. CTSA requested (1) that its lien and that Nabholz's lien be declared superior to any lien or claims by Metropolitan and Ruskin Heights and (2) that CTSA be awarded a monetary judgment against Ruskin Heights and others. On September 10, 2010, CTSA filed a motion for summary judgment as to its claims against Ruskin Heights and Metropolitan, which it amended on September 24, 2010. In addition, Metropolitan filed a cross-motion for summary judgment against CTSA on September 10, 2010. After two hearings on the matter, the court held a final hearing on October 26, 2010, in which it ruled from the bench that CTSA had an engineering and architectural lien against the property at issue; that CTSA's lien did not have priority over Metropolitan's mortgage lien; and that CTSA's lien did not relate back to the date of construction.

On November 29, 2010, the circuit court entered a partial judgment and decree, finding that Ruskin Heights had defaulted and owed Metropolitan damages; that Metropolitan's mortgage lien was valid and enforceable; that Metropolitan had first priority as to any lien claim by Nabholz or CTSA; and that CTSA had a second lien on the property. CTSA filed a notice of appeal from the order on December 10, 2010. Thereafter, on December 13, 2010, the circuit court entered an order granting Metropolitan's motion for summary judgment against CTSA and denying CTSA's motion for summary judgment against Metropolitan. In its order, the circuit court ruled that the “Architect's and Engineer's Liens are not given the same priority under [Arkansas Code Annotated section] 18–44–105 as Materialmen's [sic] and Laborer's Liens,” and further found that “CTSA's Architect's and Engineer's Lien did not attach to the property until August 25, 2009, which [was] the date CTSA's lien was filed of record.”1

CTSA appealed from the November 29, 2010 order finding that CTSA's lien was second in priority to Metropolitan's lien. In Crafton I, 2012 Ark. 56, we dismissed the appeal without prejudice for lack of a final order and identified the outstanding issues. On remand, the circuit court entered an order stating that certain parties and actions remained unresolved. CTSA appealed the November 29, 2010 order finding that CTSA's lien was second in priority to the bank's lien. We again dismissed without prejudice for lack of a final order on the basis that the order still contained unresolved issues and that the record lacked certain relevant pleadings. See Crafton II, 2013 Ark. 85.

On remand, on February 27, 2014, the circuit court entered an order dismissing Nabholz's complaint in intervention and all remaining claims and cross-claims with prejudice. That same day, the court also entered a final judgment finding that the parties had not litigated or pursued any claims since May 2012 and that such claims were deemed to be dismissed for failure to prosecute. CTSA timely filed its notice of appeal, and we now consider the parties' arguments before us.

For the first point on appeal, CTSA argues that the circuit court erred in granting summary judgment on the issue of lien priority. Specifically, CTSA contends that the court failed to grant its engineer's lien priority over a mortgage filed after construction had commenced. CTSA asserts that the circuit court incorrectly interpreted the engineer's lien statute, Arkansas Code Annotated section 18–44–105 (Supp. 2013), in connection with Arkansas Code Annotated section 18–44–110 (Repl. 2003). CTSA further maintains that its September 25, 2009 lien should have related back to the morning of October 1, 2007, when construction commenced, thereby giving it priority over Metropolitan's mortgage lien, which was filed in the afternoon of October 1, 2007. For the second point on appeal, CTSA argues that section 18–44–110 removes any distinction between its engineer's lien and the materialman's lien and reiterates that CTSA's lien should relate back to the commencement of construction and should have priority over Metropolitan's mortgage. Because these are related points, we discuss them together.

Generally, on appeal from a summary-judgment disposition, the evidence is viewed in the light most favorable to the party resisting the motion, and any doubts and inferences are resolved against the moving party. Ark. State Bd. of Election Comm'rs v. Pulaski Cnty. Election Comm'n , 2014 Ark. 236, 437 S.W.3d 80. However, when the parties agree on the facts, we simply determine whether the appellee was entitled to judgment as a matter of law. See id. When parties file cross-motions for summary judgment, as was done in this case, they essentially agree that there are no material facts remaining, and summary judgment is an appropriate means of resolving the case.See id. As to issues of law presented, our review is de novo. See id.

CTSA and Metropolitan present the issue of lien priority as an application of both the materialman's and engineer's lien statutes. As background, engineer's liens were created by the legislature in 1971, enacted by Act 291 of 1971, and are codified at Arkansas Code Annotated section 18–44–105 (Repl. 2003). The distinction between engineer's liens and materialman's liens was first noted by this court in Mahaffey & Assocs. v. Brophy, 249 Ark. 884, 462 S.W.2d 226 (1971), in which this court declined to extend the materialman's lien statute to an engineer who performed engineering and surveying services. This court distinguished the type of services that engineers provide in connection with real estate. See id.

The sole issue on appeal involves our statutory interpretation of sections 18–44–105 and 18–44–110. This court reviews the circuit court's statutory interpretation de novo, because it is for this court to determine the meaning of a statute. Roberson v. Phillips Cnty. Election Comm'n, 2014 Ark. 480, 449 S.W.3d 694. The first rule of statutory construction is to construe the statute just as it reads, giving the words their ordinary and usually accepted meaning in common language. See id. We construe statutes so that, if possible, every word is given meaning and effect. See id. If the language of a statute is clear and unambiguous and conveys a clear and definite meaning, it is unnecessary to resort to the rules of statutory interpretation. See id. When a statute is clear, it is...

To continue reading

Request your trial
8 cases
  • Waters v. Millsap
    • United States
    • Arkansas Supreme Court
    • June 18, 2015
    ...means of resolving the case. See id. As to issues of law presented, our review is de novo. Crafton, Tull, Sparks & Assocs., Inc. v. Ruskin Heights, LLC, 2015 Ark. 1, at 5, 453 S.W.3d 667, 671. The point of law at contention in this appeal is simply stated: What is the proper test for determ......
  • Miss. Cnty. v. City of Osceola
    • United States
    • Arkansas Supreme Court
    • March 2, 2017
    ...as it reads, giving the words their ordinary and usually accepted meaning in common language. Crafton, Tull, Sparks & Assocs., Inc. v. Ruskin Heights, LLC , 2015 Ark. 1, at 5, 453 S.W.3d 667, 671. If the language of a statute is clear and unambiguous and conveys a clear and definite meaning......
  • Gafford v. Allstate Ins. Co.
    • United States
    • Arkansas Supreme Court
    • March 19, 2015
    ...it reads, giving the words their ordinary and usually accepted meaning in common language. Crafton, Tull, Sparks & Assocs., Inc. v. Rusk in Heights, LLC, 2015 Ark. 1, at 5–7, 453 S.W.3d 667, 670–72. We construe statutes so that, if possible, every word is given meaning and effect. See id. W......
  • R&L Carriers Shared Servs., LLC v. Markley
    • United States
    • Arkansas Court of Appeals
    • April 19, 2017
    ...court's conclusion on a question of law is reviewed de novo and is given no deference on appeal. Crafton, Tull, Sparks & Assocs. v. Ruskin Heights, LLC , 2015 Ark. 1, 453 S.W.3d 667. And when the parties agree on the facts, the appellate court simply determines whether the appellee was enti......