Patton Wrecking & Dem. Co. v. Tennessee Valley Auth.
Decision Date | 08 September 1972 |
Docket Number | No. 71-2363.,71-2363. |
Citation | 465 F.2d 1073 |
Parties | PATTON WRECKING AND DEMOLITION CO., Inc., and Patton Bros., Inc., a joint venture, Plaintiffs-Appellees, v. TENNESSEE VALLEY AUTHORITY, Defendant-Appellant. |
Court | U.S. Court of Appeals — Fifth Circuit |
Robert H. Marquis, Gen. Counsel, Tennessee Valley Authority, Thomas A. Pedersen, Sol., Charles W. Van Beke, Knoxville, Tenn., for defendant-appellant.
Clayton J. Swank, III, J. Murray Akers, Robertshaw, Merideth & Swank, Greenville, Miss., for plaintiffs-appellees.
Before JOHN R. BROWN, Chief Judge, and INGRAHAM and RONEY, Circuit Judges.
The issue on this interlocutory appeal is whether a government contractor's suit for a declaratory judgment of the government's asserted anticipatory breach of contract was barred by virtue of the contractor's failure to exhaust the contractually established disputes procedure.
The contract, let after competitive bidding and inspection, was for the resurfacing of one of the Tennessee Valley Authority's dams. The bid invitation was based upon 2700 square feet of chipping and cleaning eroded concrete surfaces and 2700 cubic feet of drilling and setting steel anchors and placing concrete aggregate and intrusion grout. The unit price provided in the contract for each kind of work brought the total estimated contract amount to $197,100. While the contract allowed for upward adjustments of the cost of additional units of work, it was silent on decreases in quantities.
Appellee Patton Wrecking, the successful bidder, undertook and completed a substantial portion of the available work when it discovered that the total amount of work was far less than that specified (approximately 49% of the bid invitation quantity). Patton halted further performance and sought a declaratory judgment that the government's projected failure to supply adequate work constituted an anticipatory breach of contract freeing Patton from further performance on its part and entitling it to damages on the theory of quantum meruit. Tennessee Valley Authority answered and asserted Patton's failure to submit the dispute to the contracting officer under the contract's dispute clause.1
The district court in an opinion reported as Patton Wrecking and Demolition Co., Inc. v. TVA, 324 F.Supp. 143 (N.D., Miss.1971) sustained Patton's complaint against TVA's motion to dismiss and motion for summary judgment. The district court certified TVA's interlocutory appeal and a panel of this court accepted that appeal. 28 U.S.C. § 1292(b). We reverse and remand.
The district court, after studiously tracing the development of the "standard" dispute clause,2 found the dispute clause here at issue for clarity hereafter called "amended" or all disputes clause to be ambiguous in the scope of the jurisdiction that the parties had contractually conferred upon the contracting officer. The court, therefore, construed the amended dispute clause against its proponent TVA and pro tanto held that the dispute provision was inapplicable when the claim for anticipatory relief was not redressable under some other specific contract article. United States v. Utah Construction & Mining Co., 384 U.S. 394, 86 S.Ct. 1545, 16 L.Ed.2d 642 (1966).
The presence of a "standard" dispute clause in government contracts has a long history. See annotation, Government Contracts—"Dispute" Clause, 2 A.L.R.Fed. 691. In Edward R. Marden Corporation v. United States, 442 F.2d 364 (Ct.Cl., 1971), the court said:
The role and meaning of the "standard" clause has been extensively considered by the Supreme Court in United States v. Utah, supra; United States v. Anthony Grace & Sons, 384 U.S. 424, 86 S.Ct. 1539, 16 L.Ed.2d 662 (1966) and Crown Coat Front Co. v. United States, 386 U. S. 503, 87 S.Ct. 1177, 18 L.Ed.2d 256 (1966). In Utah the Supreme Court distinguished between claims "arising under" the contract contract claims for which some other contractual article provided avenues for redress and breach of contract claims. In holding administrative remedies available only for contract claims, the Court said:
United States v. Utah Construction & Mining Co., supra, 384 U.S. at 412-413, 86 S.Ct. at 1553. The primacy of the role of administrative resolution of contract claims through the dispute process requires that those remedies be exhausted before suit may be brought. The remedy, however, must be an available one, as the Supreme Court in United States v. Anthony Grace & Sons, supra, noted:
This learning was succinctly restated in Crown Coat, supra:
To continue reading
Request your trial-
OMEN CONST. CO. v. Tennessee Valley Authority
...e. g., United States v. Carlo Bianchi & Co., 373 U.S. 709, 83 S.Ct. 1409, 10 L.Ed.2d 652 (1963); Patton Wrecking & Dem. Co. v. Tennessee Valley Authority, 465 F.2d 1073, 1076 (5th Cir. 1972); Tennessee Valley Authority v. U. S. Carbon Prods., Inc., 427 F.Supp. 474, 478 (E.D.Ill.1976). In fa......
-
Brown & Root Development, Inc. v. Tennessee Valley Authority, 81-7390
...under 28 U.S.C. § 1292(a)(1). The district court granted certification which this court accepted. II. In Patton Wrecking & Demolition Co. v. TVA, 465 F.2d 1073 (5th Cir. 1972), the former Fifth Circuit 5 held that a district court may not entertain an action on a contract dispute between a ......
-
Gary Aircraft Corp., Matter of
... ... See, e.g., Patton Wrecking and Demolition Co. v. TVA, 465 F.2d 1073 ... ...
-
Martin K. Eby Const. v. Dallas Area Rapid Transit
...this court has enforced a contractually established disputes procedure in a federal government contract. See Patton Wrecking & Demolition Co. v. TVA, 465 F.2d 1073 (5th Cir.1972). (Several years after we decided Patton Wrecking, Congress enacted the Contract Disputes Act of 1978, as amended......
-
18 C.F.R. § 1308.4 Coverage of Certain Excluded Contractors
...If the disputes clause in the contract is not an "all disputes" clause (see Patton Wrecking & Dem. Co. v. Tennessee Valley Authority, 465 F.2d 1073 (5th Cir. 1972)), a Contractor's election under this section shall cause the provisions of the first two sentences of section 6(a) of the Act t......