United States v. Anthony Grace Sons, Inc

Decision Date06 June 1966
Docket NumberNo. 439,439
Citation86 S.Ct. 1539,16 L.Ed.2d 662,384 U.S. 424
PartiesUNITED STATES, Petitioner, v. ANTHONY GRACE & SONS, INC
CourtU.S. Supreme Court

Louis F. Claiborne, Washington, D.C., for petitioner.

David Fromson, Garden City, N.Y., for respondent.

Mr. Justice WHITE delivered the opinion of the Court.

In United States v. Carlo Bianchi & Co., 373 U.S. 709, 83 S.Ct. 1409, 10 L.Ed.2d 652, we held that, aside from questions of fraud, a reviewing courts is limited to the administrative record made below in determining the finality to be given departmental decisions and findings made by a Board of Contract Appeals pursuant to a standard government disputes clause. In the present case we are called upon to decide whether the reviewing court or the Board of Contract Appeals should make the original record on an issue which the Board did not resolve because it erroneously dismissed the appeal before it as untimely.

The question is framed by the following facts. The Department of the Air Force issued an invitation for bids for the construction of a military housing project at Topsham Air Force Station, Maine. The invitation included a tentative minimum wage schedule which the contractor would have to meet. It also advised that the wage schedule would be finally redetermined by the Secretary of Labor not more than 90 days prior to the commencement of construction and that the Federal Housing Commissioner would then adjust the contract price to reflect any changes made in the wage schedules.1 In addition, the successful bidder was required to complete certain preparatory acts in order to close the contract and to post a $25,000 deposit to ensure the closing of the contract. Respondent, Anthony Grace & Sons, Inc., was the low acceptable bidder and a letter of acceptability was sent to it. That letter reminded respondent that failure to close the contract within a specified number of days was sufficient justification to warrant the Department of the Air Force in cancelling the bid and letter of acceptability, in retaining the deposit for liquidated damages and in determining additional liability for actual damages. A disputes clause in the letter of acceptability made such decision by the Department of the Air Force final unless, within 30 days from the receipt of the decision, respondent appealed to the Armed Services Board of Contract. Appeals, whose decision would be final and conclusive unless fraudulent or capricious or arbitrary, or so grossly erroneous as necessarily to imply bad faith, or not supported by substantial evidence.2 After receiving subsequent wage schedules from the Secretary of Labor, respondent concluded that certain work was being placed in higher wage categories than was provided in the specifications which accompanied the bid invitation. On the basis of this alleged deviation from the original specifications respondent asked first the Housing Commissioner and then the Department of the Air Force to raise the contract price. These requests were refused and respondent then notified the Air Force that it would be unable to complete the closing until this matter was cleared up. In the ensuing exchange of letters, the contracting officer informed respondent that its bid and the letter of acceptability were being canceled and its deposit was being retained. Pursuant to the disputes clause, respondent appealed this decision to the Armed Services Board of Contract Appeals, which dismissed the appeal as out of time without considering the merits of the case. Respondent then sued in the Court of Claims to recover its deposit and for damages resulting from the Government's alleged wrongful cancellation. That court concluded that the appeal to the Board was timely and that the Board had erred in not reaching the merits of the case. With Judges Davis and Laramore dissenting, the court then decided to remand the case to its own trial commissioner, rather than to the Board of Contract Appeals, to make a record and consider the case on its marits. The Government asked us to grant certiorari to consider whether this was in violation of the principles announced in the Wunderlich Act3 and United States v. Carlo Bianchi & Co., supra. We granted certiorari, 382 U.S. 901, 86 S.Ct. 234, 15 L.Ed.2d 154, and we now reverse.

This question was anticipated in Bianchi, supra, where we considered what a reviewing court should do when the administrative record is defective, or inadequate or reveals the commission of a prejudicial error. Two suggestions were given:

'First, there would undoubtedly be situations in which the court would be warranted, on the basis of the administrative record, in granting judgment for the contractor without the need for further administrative action. Second, in situations where the court believed that the existing record did not warrant such a course, but that the departmental determination could not be sustained under the standards laid down by Congress, we see no reason why the court could not stay its own proceedings pending some further action before the agency involved. Cf. Pennsylvania R. Co. v. United States, 363 U.S. 202, 80 S.Ct. 1131, 4 L.Ed.2d 1165. Such a stay would certainly be justified where the department had failed to make adequate provision for a record that could be subjected to judicial scrutiny, for it was clearly part of the legislative purpose to achieve uniformity in this respect.' 373 U.S. 709, 717—718, 83 S.Ct. 1409, 1415, 10 L.Ed.2d 652.

The policy reflected in this language, which requires utilization of the administrative procedures contractually bargained for was clearly intended by Congress, see H.R.Rep.No.1380, 83d Cong., 2d Sess. (1954), U.S.Code Congressional and Administrative News 1954, p. 2191; United States v. Carlo Bianchi & Co., supra, at 715—718, 83 S.Ct. at 1413—1415; and it has been consistently reflected in a long line of decisions by this Court. See United States v. Wunderlich, 342 U.S. 98, 72 S.Ct. 154, 96 L.Ed. 113; United States v. Moorman, 338 U.S. 457, 70 S.Ct. 288, 94 L.Ed. 256; United States v. Joseph A. Holpuch Co., 328 U.S. 234, 66 S.Ct. 1000, 90 L.Ed. 1192; United States v. Blair, 321 U.S. 730, 64 S.Ct. 820, 88 L.Ed. 1039; United States v. Callahan Walker Construction Co., 317 U.S. 56, 63 S.Ct. 113, 87 L.Ed. 49; Kihlberg v. United States, 97 U.S. 398, 24 L.Ed. 1106. Pre-eminently, this policy is grounded on a respect for the parties' rights to contract and to provide for their own remedies. See United States v. Utah Construction & Mining Co., 383 U.S. 394, 86 S.Ct. 1545; United States v. Moorman, supra, 338 U.S. at 461—462, 70 S.Ct. at 290—291. But, beyond that, there is also a belief that resort to administrative procedures is an expeditious way to settle disputes, conducive to speed and economy.4 United States v. Blair, supra, 321 U.S. at 735, 64 S.Ct. at 822. Such procedures also facilitate a department's supervisory control over contracting officers and perhaps enhance the possibility of harmonious agreement. Ibid. Further, reliance upon a few expert agencies to make the records and initially to pass on the merits of the claims properly presented to them will lead to greater uniformity in the important business of fairly interpreting government contracts.

There can be no doubt that the dispute here over the decision by the Department of the Air Force to cancel respondent's commitments under the bid and letter of acceptability and to retain the deposit is one which the parties contractually provided should be heard and decided by the administrative process. Barring some compelling policy reason to disregard this provision, the contractor should be held to its contractual agreement even at this stage in the litigation.

It is true that this Court has said on several occasions that the parties will not be required to exhaust the ad- ministrative procedure if it is shown by clear evidence that such procedure is 'inadequate or unavailable.' United States v. Joseph A. Holpuch Co., supra, 328 U.S. at 240, 66 S.Ct. at 1003; United States v. Blair, supra, 321 U.S. at 736—737, 64 S.Ct. at 823. It may be that the contracting officer, H. B. Zachry Co. v. United States, 344 F.2d 352, 170 Ct.Cl. 115, or the Board of Contract Appeals, Southeastern Oil Florida, Inc. v. United States, 115 F.Supp. 198, 127 Ct.Cl. 480, so clearly reveals an unwillingness to act and to comply with the administrative procedures in the contract that the contractor or supplier is justified in concluding that those procedures have thereby become 'unavailable.' Similarly, there may be occasions when the lack of authority of either the contracting officer or the administrative appeals board is so apparent that the contractor or supplier may justifiably conclude that further administrative relief is 'unavailable.'5 But these circumstances are clearly the exceptions rather than the rule and the inadequacy or unavailability of administrative relief must clearly appear before a party is permitted to circumvent his own contractual agreement. When the Board fails to reach and decide an issue because it disposes of the appeal on another ground—here the untimeliness of the appeal which the Court of Claims later rejects, there is no sound reason to presume that the Board will not promptly and fairly deal with the merits of the undecided issue if it is given the chance to do so.6

The Court of Claims in this case attempted to justify bypassing the Board of Contract Appeals because it felt the dispute could be resolved more speedily if its Trial Commissioner made the record and initially passed on the merits. The dissenting judges question the factual accuracy of the premises.7 Even if the premises were sound, however, this argument falls substantially short of establishing that the administrative route is inadequate or unavailable.8

Nor is it persuasive to say that the administrative remedy is inadequate in this case because the Board of Contract Appeals considers...

To continue reading

Request your trial
120 cases
  • Nager Electric Company, Inc. v. United States
    • United States
    • U.S. Claims Court
    • 14 Octubre 1966
    ...United States v. Utah Constr. & Mining Co., 384 U.S. 394, 86 S.Ct. 1545, 16 L.Ed.2d 642 (1966); and United States v. Anthony Grace & Sons, 384 U.S. 424, 86 S.Ct. 1539, 16 L.Ed.2d 662 (1966) — and we see no practical difference whatever between having them held in the administrative tribunal......
  • Technograph Printed Circuits, Ltd. v. United States
    • United States
    • U.S. Claims Court
    • 17 Febrero 1967
    ...Anthony Grace & Sons, Inc. v. United States, 345 F.2d 808, 810, 170 Ct.Cl. 688, 691-692 (1965), rev'd on other grounds, 384 U.S. 424, 86 S.Ct. 1539, 16 L.Ed.2d 662 (1966). If the defendant wishes to preserve this defense, the pertinent facts can be established at the A trial will be necessa......
  • JL Simmons Company v. United States
    • United States
    • U.S. Claims Court
    • 16 Julio 1969
    ...September 15, 1959. These events all occurred prior to the interpretations of the Wunderlich Act by the Supreme Court in Bianchi, Utah, and Grace,8 and the parties thereafter engaged in a series of procedures looking forward to a trial of the case in this court. Some of those procedures are......
  • Bethlehem Steel Corporation v. Grace Line, Inc., 21050.
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • 6 Marzo 1969
    ...1958). 39 Grace rejoins that Bethlehem failed to inform Grace of the effect of the changes. 40 United States v. Anthony Grace & Sons, Inc., 384 U.S. 424, 430, 86 S.Ct. 1539, 16 L.Ed.2d 662 (1966); United States v. Joseph A. Holpuch Co., 328 U.S. 234, 240, 66 S.Ct. 1000, 90 L.Ed. 1192 (1946)......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT