Adams v. Nelsen, 833DC359

Decision Date20 March 1984
Docket NumberNo. 833DC359,833DC359
Citation312 S.E.2d 896,67 N.C.App. 284
CourtNorth Carolina Court of Appeals
PartiesW.J. ADAMS v. Robert J. NELSEN and wife, Alice E. Nelsen.

Darden & Pierce by R.D. Darden, Jr., Morehead City, for plaintiff-appellant.

Bennett, McConkey & Thompson by Thomas S. Bennett, Morehead City, for defendants-appellees.

VAUGHN, Chief Judge.

Plaintiff contends that the trial court erred in granting defendants' 12(b)(6) motion to dismiss. We agree. The only situations warranting a 12(b)(6) dismissal are:

(1) when the complaint on its face reveals that no law supports plaintiff's claim;

(2) when the complaint on its face reveals that some fact essential to plaintiff's claim is missing; and

(3) when some fact disclosed in the complaint defeats plaintiff's claim.

Advertising Co. v. City of Charlotte, 50 N.C.App. 150, 152, 272 S.E.2d 920, 922 (1980).

Plaintiff's complaint, which, in essence, alleged that plaintiff performed services for which defendants still owe him money pursuant to a valid contract entered into between the parties, was sufficient to withstand defendants' motion to dismiss. We find no defect on the face of plaintiff's complaint.

The trial court, was, furthermore, without authority to cancel plaintiff's claim of lien. Defendant does not dispute that plaintiff was entitled to file a claim of lien pursuant to G.S. 44A-8. The right to file and enforce a lien claim and the right to resolve a dispute through arbitration are mutually exclusive rights. Plaintiff, by contractually agreeing to arbitration, did not thereby waive his right to file a lien claim and institute court action to enforce such lien. See Mills v. Robert Gottfried, Inc., 272 So.2d 837 (Fla.App.1973); Frederick Contr. v. Bel Pre Med., 274 Md. 307, 334 A.2d 526 (1975). Plaintiff is entitled to enforce any award in his favor through a judgment enforcing his lien claim. G.S. 44A-13 and 14. See Mills v. Robert Gottfried, Inc., supra; Frederick Contr. v. Bel Pre Med., supra.

Plaintiff's complaint, valid on its face, was not, as defendants suggest, rendered invalid by the fact that the parties had, prior to the time plaintiff instituted this suit, contractually agreed to arbitrate all disputes. Attached to plaintiff's complaint and incorporated therein by reference was the parties' contract, containing the following arbitration provision:

All claims, disputes and other matters in question between the parties to this Agreement, arising out of, or relating to this Agreement or the breach thereof, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise. No arbitration, arising out of, or relating to this Agreement shall include, by consolidation, joinder or in any other manner, any additional party not a party to this Agreement except by written consent containing a specific reference to this Agreement and signed by all the parties hereto. Any consent to arbitration involving an additional party or parties shall not constitute consent to arbitration of any dispute not described therein or with any party not named or described therein. This Agreement to arbitrate and any agreement to arbitrate with an additional party or parties duly consented to by the parties hereto shall be specifically enforceable under the prevailing arbritration law. In no event shall the demand for arbitration be made after the date when such dispute would be barred by the applicable statute of limitations. The award rendered by the arbitrators shall be final.

We are aware of the legislative intent underlying the recently adopted Uniform Arbitration Act, G.S. 1-567.1, et seq., favoring arbitration as a means of dispute resolution. We recognize, moreover, that the parties' contractual agreement to resolve disputes through arbitration was valid, enforceable and irrevocable. G.S. 1-567.2; see Sims v. Ritter Construction, Inc., 62 N.C.App. 52, 302 S.E.2d 293 (1983). Nevertheless, the right to arbitration is contractual, and, thus, in accordance with traditional contract principles, may be impliedly waived through the conduct of a party to the contract clearly indicating such purpose. See Campbell v. Blount, 24 N.C.App. 368, 210 S.E.2d 513 (1975). There is no question but that plaintiff, by pursuing an action in court, clearly indicated his intent to waive his right to arbitration.

There is furthermore no question but that defendants, by failing to demand arbitration as provided by the parties' contract, waived their right as well. According to the contract's arbitration provision, to avoid waiver, it was necessary for a party to demand arbitration within the applicable statutory time limit. The statute of limitations governing contract disputes is three years. G.S. 1-52. Defendants, therefore, to have invoked their right to arbitration should have demanded such within three years from the time plaintiff breached the contract's arbitration provision by instituting court action. See Rawls v. Lampert, 58 N.C.App. 399, 293 S.E.2d 620 (1982). Because of their own inaction, defendants are now barred from invoking their arbitration rights.

We find no merit in defendants' suggestion that their 12(b)(6) motion was equivalent to a demand for arbitration. Defendants' motion, which alleged that plaintiff stated no facts warranting relief, made no reference to and did not invoke the arbitration process. Had defendants wished to assert their contractual right to arbitration, the proper procedure would have been a motion to stay litigation and order arbitration. G.S. 1-567.3(d); Cf. Mills v. Robert W. Gottfried, Inc., supra; Eisel v. Howell, 220 Md. 584, 155 A.2d 509 (1959) (motions to dismiss for lack of jurisdiction in actions concerning contracts with arbitration clauses were improper); but cf. Walter L. Keller & Associates v. Health Management Foundation, 438 So.2d 1076 (Fla.App.1983).

Although defendants in this case waived their arbitration rights as a matter of law, we note that had the statute of limitations not run its course, it would have been within the trial judge's discretion to...

To continue reading

Request your trial
4 cases
  • Rustad v. Rustad
    • United States
    • North Carolina Court of Appeals
    • April 17, 1984
    ...a contractual agreement to resolve disputes through arbitration is valid, enforceable, and irrevocable. G.S. 1-567.2; Adams v. Nelsen, --- N.C. ---, 312 S.E.2d 896 (1984); Sims v. Ritter Construction, Inc., 62 N.C.App. 52, 302 S.E.2d 293 (1983). In Crutchley v. Crutchley, 306 N.C. 518, 293 ......
  • Servomation Corp. v. Hickory Const. Co.
    • United States
    • North Carolina Court of Appeals
    • September 4, 1984
    ..."may be impliedly waived through the conduct of a party to the contract clearly indicating such purpose." Adams v. Nelsen, 67 N.C.App. 284, 287, 312 S.E.2d 896, 899 (1984). The contract between plaintiff and defendant provided for mandatory arbitration of disputes thereunder, and the questi......
  • Miller Bldg. Corp. v. Coastline Associates Ltd. Partnership, 915SC280
    • United States
    • North Carolina Court of Appeals
    • January 7, 1992
    ...demanded arbitration within a reasonable time and Miller was not prejudiced by the delay in the demand. We agree. In Adams v. Nelsen, 67 N.C.App. 284, 312 S.E.2d 896 (1984), modified and aff'd, 313 N.C. 442, 329 S.E.2d 322 (1985), plaintiff professional engineer entered a contract to perfor......
  • Adams v. Nelsen, 166PA84
    • United States
    • North Carolina Supreme Court
    • June 5, 1984
    ...ADAMS v. Robert J. NELSEN and Wife, Alice E. Nelsen. No. 166PA84. Supreme Court of North Carolina. June 5, 1984. Case below: 67 N.C.App. 284, 312 S.E.2d 896. Bennett, McConkey & Thompson, Morehead City, for Darden & Pierce, Morehead City, for plaintiff. Defendants' petition for discretionar......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT