Adams v. Smith

Decision Date02 December 1957
Docket NumberNo. 22633,22633
PartiesGeorge L. ADAMS, Respondent (Plaintiff), v. Clyde M. SMITH, Appellant (Defendant).
CourtMissouri Court of Appeals

Francis G. Hale, Robert E. Coleberd, Liberty (Arthur R. Kincaid and William B. Waters, Liberty, of counsel), for appellant.

Harry v. Jenkins, Liberty, for respondent.

CAVE, Judge.

This is an action for the alleged balance due plaintiff for the construction of a building for the defendant. Because of the issues raised on appeal, we state the material allegations of the petition.

It alleges that plaintiff is a building contractor; that on or about November 24, 1954, defendant employed plaintiff to build and construct a one-story building in Liberty, Missouri; that plans were presented to plaintiff, and plaintiff agreed to construct said building, as provided and required by said plans, for $7,850; that a written contract was executed by plaintiff and defendant; that said contract contemplated the building be constructed according to the plans furnished; that accordingly, plaintiff commenced work on said building and immediately thereafter, 'defendant in consultation with plaintiff decided to make certain and elaborate changes and alterations in the original contract and plans and as the work progressed, defendant did continue to make changes in the plans and construction. That the original contract based upon the original plans, was abandoned by both parties and plaintiff proceeded to construct and erect said building, according to the wishes and desires of defendant and as ordered, directed and supervised by defendant. That said changes and additions and alterations and the extra charges thereby incurred are set out on the attached list and made a part hereof. That plaintiff agreed to construct said building as originally planned and submitted to him for $7850.00, but said contract and agreement was abandoned and plaintiff proceeded to construct the building as ordered and directed by defendant, on a basis of labor and material furnished, a statement to be furnished defendant weekly or thereabouts. That settlement was made each week based upon the statements and estimates furnished by plaintiff to defendant, covering the current bills for labor and material furnished, and payment was made accordingly by defendant. That on February 16, 1955, defendant suddenly terminated the work and ordered defendant (plaintiff) to cease work, stating that he was not going to spend any more on the job and building. That defendant failed and refused to pay the amount then currently due on said building at that time which was, February 7, 1955, $645.21, and February 16, 1955, $1324.64. That defendant is entitled to a credit of $195.00 being the Liberty Plumbing Company bill, which he had paid, and also a credit of $500.00, being the advance which was paid to plaintiff when the work started, leaving an unpaid balance due the plaintiff of $1274.85, for labor, work and material, all done and placed into said building, as ordered and directed by defendant.'; for which amount plaintiff prays judgment.

Copies of the original written contract, and of the items of February 7th and February 16th claimed to be due were attached to the petition. The items claimed are as follows:

                "Payroll ending February 4, 1955           $ 100.25
                 6% Social Security and Insurance (26.00)      1.56
                                                           ---------
                                                           $ 101.81
                 Materials
                 Liberty Lumber Co. invoices delivered       484.74
                 Contractor's overhead and commission
                   10%                                        58.66
                                                           ---------
                                                    Total  $ 645.21
                 Payroll ending February 15, 1955          $  76.00
                 6% Soc. Sec. and Ins.                         1.92
                                                           ---------
                                                              77.92
                 Materials and sub-contracts
                 Leo Adams Plumbing and Heating Co.          585.26
                 Liberty Plbg. Co.                           195.00
                 Material and labor for laying asphalt
                   tile and base                             336.00
                 Anderson Hardware                             4.23
                 Liberty Lumber Co.                           15.81
                                                           ---------
                                                           $1204.22
                 Contractor's overhead and 10% commission    120.42
                                                           ---------
                                                           $1324.64"
                

The total of these two items is $1,969.85, but plaintiff gives credit for $695, as shown in the petition, leaving the claimed balance $1,274.85.

Defendant's answer alleged that plaintiff's petition failed to state facts upon which any relief could be granted, and asked for dismissal of the petition. The answer admitted that defendant 'did some work on and furnished some material for the construction of a business building * * * for defendant'; but denies all other allegations of the petition.

The defendant also filed a counterclaim in two counts. The first alleges that the defendant had inadvertently and by oeversight paid the plaintiff the sum of $5,810.96 in excess of the amount of work done and materials furnished by plaintiff. The second court alleges that defendant had employed plaintiff to construct a certain building and to furnish the labor and material therefor; that plaintiff was to construct said building in a workmanlike manner with sound material; that plaintiff did some work and furnished some material for the construction of said building, but failed to perform said work in a good workmanlike manner, and alleges certain specific deficiences, and prays for judgment of $5,000 on the second count. The reply was a general denial.

The jury returned a...

To continue reading

Request your trial
8 cases
  • Williams v. Cass
    • United States
    • Missouri Court of Appeals
    • October 24, 1963
    ...the burden is on the claimant to plead, prove, and have the jury instructed, that his charges are fair and reasonable.' Adams v. Smith, Mo.App., 307 S.W.2d 525, 527(1); Rodgers v. Levy, Mo.App., 199 S.W.2d 79, 82(8). See also Fitzgerald v. Schaefer, Mo.App., 216 S.W.2d 939(3). Bluntly put, ......
  • Bybee v. Dixon
    • United States
    • Missouri Court of Appeals
    • June 18, 1964
    ...he has deserved." Hoyt v. Buder, 318 Mo. 1155, 1168, 6 S.W.2d 947, 951; Rodgers v. Levy, Mo.App., 199 S.W.2d 79, 82(8); Adams v. Smith, Mo.App., 307 S.W.2d 525, 527(1). Indeed, where one at the request of the owner renders services or furnishes materials in connection with construction or r......
  • Johnson v. Girvin's Estate
    • United States
    • Missouri Court of Appeals
    • August 13, 1963
    ...v. Poinsett, Mo.App., 164 S.W.2d 124; Rodgers v. Levy, Mo.App., 199 S.W.2d 79, 82; Kick v. Doerste, 45 Mo.App. 134, 140; Adams v. Smith, Mo.App., 307 S.W.2d 525. For the foregoing reasons the judgment is reversed and the case is remanded for STONE and HOGAN, JJ., concur. 1 How the jury got ......
  • Rolla Lumber Co. v. Evans, 9106
    • United States
    • Missouri Court of Appeals
    • June 20, 1972
    ...have the jury instructed, that his charges are fair and reasonable.' Rodgers v. Levy, Mo.App., 199 S.W.2d 79, 82(5); Adams v. Smith, Mo.App., 307 S.W.2d 525, 527(1); Williams v. Cass, Mo.App., 372 S.W.2d 156, 161(10, 11); Woodley v. Esslinger, Mo.App., 458 S.W.2d 869, 873. See Otte v. McAul......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT