Adc Orange, Inc. v. Coyote Acres, Inc.

Decision Date19 October 2006
Citation7 N.Y.3d 484,857 N.E.2d 513
PartiesADC ORANGE, INC., Appellant, v. COYOTE ACRES, INC., Respondent.
CourtNew York Court of Appeals Court of Appeals

Powers & Santola, LLP, Albany (Michael J. Hutter of counsel), and Tarshis, Catania, Liberth, Mahon & Milligram, PLLC, Newburgh, for appellant.

Joseph J. Haspel, PLLC, Goshen (Joseph J. Haspel of counsel), and Errol Blank, West Nyack, for respondent.

OPINION OF THE COURT

ROSENBLATT, J.

This case involves a contract for the sale of land. The buyer seeks specific performance; the seller has kept the down payment, claiming the buyer breached the contract. Pursuant to the contract, the buyer was obligated to make an interim payment of $250,000 by a particular date. Because the buyer made the payment two weeks late, the outcome of the appeal turns in part on whether, in connection with that obligation, time was "of the essence." We hold that in contracts of this type, time of performance is not normally of the essence unless the contract so states or one of the parties has unequivocally declared it upon proper notice.

ADC Orange, Inc. as buyer and Coyote Acres, Inc. as seller entered into a contract in December 2000 for the sale of a parcel of property in the Town of Wallkill, Orange County for $600,000. As required by the contract, ADC made a down payment of $100,000, which Coyote's attorney held in escrow. The agreement contained a condition requiring ADC to obtain subdivision and site plan approval from the town planning board for the construction of at least 25 "residence dwellings upon the Premises and such approvals being received no later than June 30, 2002." Coyote in turn agreed to execute authorizations required for the approvals.

A rider provided that ADC was entitled to a return of the $100,000 down payment if, despite good faith and due diligence, it failed to obtain the approvals. The rider further provided — of pivotal importance here — that ADC make an interim payment of $250,000 "[u]pon the later of the preliminary approval having been received from the applicable authorities for the subdivision or December 31, 2001 but in no event later than December 31, 2001." ADC was to pay the balance on filing the final approval and subdivision map. The contract contained no time-of-the-essence clause and did not provide that ADC's failure to make the interim payment by December 31, 2001 would put it in default.

When Coyote signed the contract, it did not have title to the property. In fact, it did not obtain title until July 12, 2001, some seven months later. Beginning June 22, 2001, the attorneys for the parties corresponded with one another. Writing to Coyote, ADC expressed concern that it would not be able to proceed with its application for subdivision approval in time to appear at a scheduled planning board meeting if it did not immediately receive authorization from the property owner. If ADC did not receive the requested authorization counsel wrote, "the Contract will be deferred accordingly."

Coyote replied that written authorization had been sent to ADC's agents "some time ago." In a June 27, 2001 letter to Coyote, however, ADC insisted that it had still not received written authorization and that "all of the time frames within the contract are suspended until [it] has received the written authorization from the current landowner." That day, Coyote faxed the current owner's authorization to ADC. On December 26, 2001, Coyote's attorney sent ADC a fax reminding ADC "that the contract of sale in the above matter requires an additional deposit of $250,000 to be made no later than December 31, 2001." "I look forward," he continued, "to my timely receipt of such deposit."

By a December 31 fax, ADC's counsel acknowledged the reminder and said that his principal was out of the country but would transfer the funds "upon his return on January 14, 2002." Coyote did not immediately respond to this proposal; its counsel was also away. On January 10, 2002, however, an attorney who was of counsel to Coyote's law firm wrote to ADC's attorney informing him that Coyote considered ADC in default. ADC's attorney responded the next day, enclosing a $250,000 check and insisting that the delay caused by his principal being out of the country did not constitute a default under the contract, inasmuch as it contained no time-of-the-essence provision. Over the next several months, the parties entered into negotiations by which Coyote would drop its objections to the timeliness of the payment if ADC agreed to some changes in the contract. The negotiations stalled and on March 13, 2002, Coyote declared ADC in default and returned the $250,000 check.

On April 10, 2002 ADC brought this action seeking specific performance of the contract. The following month, however, Coyote agreed to forgo its objections to the late payment in exchange for ADC's consent to certain contractual changes. On June 5, 2002, ADC secured preliminary subdivision approval from the town planning board. It would be a year, however, before final approval was granted. The parties exchanged drafts of the amended contract in June 2002, but negotiations again broke down and this litigation ensued.

In answer to ADC's complaint for specific performance, Coyote sought dismissal and raised two affirmative defenses. First, Coyote claimed that ADC breached the contract by its late payment of the $250,000, resulting in its default. This default, Coyote asserted, entitled it to keep the $100,000 down payment, which it sought by counterclaim. Second, Coyote asserted that the contract had been terminated when ADC failed to obtain final subdivision approval by June 30, 2002, and that if it were to return the down payment, Coyote would have no further obligation to ADC.

Both moved for summary judgment. Holding that Coyote improperly repudiated the contract, Supreme Court granted ADC's motion and ordered specific performance. The Appellate Division reversed, ruling that ADC's late payment constituted a material breach of the contract, entitling Coyote to keep the down payment. The Appellate Division additionally stated that ADC was not entitled to specific performance because Coyote had made a prima facie showing that ADC was not ready, willing and able to secure subdivision and site plan approval. ADC, the Court ruled, failed to raise a triable issue of fact on its claim that it could not obtain the approvals because of Coyote's recalcitrance.

We modify and hold that ADC did not materially breach the contract by its late payment, and that there are triable issues of fact as to whether Coyote hindered ADC in its ability to perform.

Time of the Essence

The question whether ADC's late installment payment constitutes a material breach depends on whether time was of the essence with respect to that payment. Unless it was, ADC had a reasonable time in which to tender performance after the specified date of December 31, 2001 (see Grace v. Nappa, 46 N.Y.2d 560, 565, 415 N.Y.S.2d 793, 389 N.E.2d 107 [1979]).

Grace stands for the proposition...

To continue reading

Request your trial
59 cases
  • 1111 Myrtle Ave. Grp. LLC v. Myrtle Prop. Holdings LLC (In re 1111 Myrtle Ave. Grp. LLC)
    • United States
    • U.S. Bankruptcy Court — Southern District of New York
    • 25 d5 Agosto d5 2017
    ...and sale of realty in the absence of a clear provision making it so." (citation omitted)); ADC Orange, Inc. v. Coyote Acres, Inc. , 7 N.Y.3d 484, 489, 824 N.Y.S.2d 192, 857 N.E.2d 513, 516 (2006). Even where a specific closing date is included in a contract for the sale of real property, ti......
  • Random Ventures, Inc. v. Advanced Armament Corp.
    • United States
    • U.S. District Court — Southern District of New York
    • 13 d1 Janeiro d1 2014
    ...frustrated or prevented the occurrence of the condition." MHR Capital Partners LP, 12 N.Y. 3d at 646 (quoting ADC Orange, Inc. v. Coyote Acres, Inc., 7 N.Y. 3d 484, 490 (2006)). For all of these reasons, the Court finds that defendants breached the covenant of good faith and fair dealing.DA......
  • Mills v. Chauvin
    • United States
    • New York Supreme Court — Appellate Division
    • 28 d4 Fevereiro d4 2013
    ...Dev. BR, LLC v. Diamond Dev., LLC, 67 A.D.3d 1112, 1114, 888 N.Y.S.2d 654 [2009], quoting ADC Orange, Inc. v. Coyote Acres, Inc., 7 N.Y.3d 484, 490, 824 N.Y.S.2d 192, 857 N.E.2d 513 [2006];see Whitney v. Perry, 208 A.D.2d 1025, 1026, 617 N.Y.S.2d 395 [1994] ). “ ‘What constitutes a reasonab......
  • Parker Hannifin Corp. v. Properties
    • United States
    • U.S. District Court — Southern District of New York
    • 8 d3 Maio d3 2013
    ...the language is clear and unequivocal, and that it provides reasonable time for the buyer to perform. ADC Orange, Inc. v. Coyote Acres, Inc., 7 N.Y.3d 484, 490, 857 N.E.2d 513, 516 (2006); see In re Southold Dev. Corp., 134 B.R. 705, 708 (E.D.N.Y. 1991). 7. We agree with plaintiff that the ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT