Allen v. Labsap

Decision Date24 May 1905
Citation188 Mo. 692,87 S.W. 926
PartiesALLEN v. LABSAP et al.
CourtMissouri Supreme Court

Appeal from St. Louis Circuit Court; Warwick Hough, Judge.

Action by William R. Allen against Nettie Labsap and others. From a judgment for plaintiff, defendants appeal. Affirmed.

Sigmund Labsap, for appellants. David Goldsmith, for respondent.

LAMM, J.

This is a suit to enforce the lien of a tax bill, levying the cost of certain street improvements against abutting properties, and, inter alia, against a lot, the property of appellant Nettie Labsap, fronting 28 feet 8 inches on Easton avenue, between Marcus avenue and Kingshighway Boulevard, in St. Louis. The bill was issued to one G. Eyerman, Jr., as original contractor, who assigned to respondent. Tried to the court without a jury, judgment was entered for plaintiff, from which defendants appealed. The pertinent facts will appear in the opinion.

1. It is contended by appellants that the street improvement was not completed by the contractor within the time limit, and hence the tax bill was void. No special or general ordinance of the city of St. Louis was put in evidence making time of the essence of the transaction, or requiring the work to be commenced by a day certain or completed by a given date. The matter relied upon as a defense is contained alone in the contract entered into between the city of St. Louis and the contractor in clauses 10 and 11, as follows:

"(10) The first party shall not be entitled to any claim for damages for any hindrance or delay, from any cause, whatever, in the progress of the work, or any portion thereof; but such hindrance may entitle said first party to an extension of the time for completing this contract sufficient to compensate for the detention, the same to be determined by the Street Commissioner, provided he shall have immediate notice in writing of the cause of detention.

"(11) The work embraced in this contract shall be begun within one week after written notice so to do shall have been given to the contractor by the Street Commissioner, and carried on regularly and uninterruptedly thereafter (unless the said Commissioner shall otherwise, in writing, specially direct), with such a force as to insure its full completion within two and one-half months thereafter—the time of beginning, rate of progress and time of completion being essential conditions of this contract. And if the contractor shall fail to complete the work by the time above specified, the sum of five dollars per day for the first ten days, and the sum of ten dollars per day for each and every day thereafter until such completion, shall be deducted from the moneys payable under this contract."

Clause 11 (differing only in time limit) is precisely the contract provision before this court in Heman v. Gilliam, 171 Mo., loc. cit. 265, 71 S. W. 163 et seq. In that case, as in this, there was no ordinance provision regulating the time; in that case, as in this, there was a contract provision that, if the contractor failed to complete the work within a specified time, deductions should be made from moneys payable under the contract; and in that case, as in this, it was insisted that a violation of the contract time limit was fatal to the tax bills. But we held in the Heman Case that such contract, when all its provisions were construed together, in the absence of a time provision in an ordinance, contemplated that the work might not be completed within the time stated, and made provisions for such contingency, and, upon its happening, for an extension of time upon terms. That an ordinance, prescribing a definite and mandatory time limit under which work is competed for and bid off, stands on a different footing than a contract made under the ordinance, is apparent from our decisions, and is agreeable to the common sense of the thing. So that, in the absence of a city ordinance requiring the work to be completed within a definite time, and in the presence, as here, of a contract provision specifying a definite time for the completion of the work, followed by other provisions, to which effect must be given, providing for deductions from the money due the contractor on a failure to complete the work within that time, the views of this court, on full consideration, have come to be that, if the work is completed within a reasonable time, the tax bills are not void. Heman v. Gilliam, supra; Schibel v. Merrill, 83 S. W. 1069 (not yet officially reported); Barber Asphalt Paving Co. v. Munn, 83 S. W. 1062 (not yet officially reported); Neill v. Gates, 152 Mo., loc. cit. 592, 54 S. W. 460. No sufficient reason is suggested why the reasoning of these cases is unsound, or why the doctrine should not be regarded as settled under the rule of stare decisis, and we accordingly hold the question no longer an open one in this state. In the Schibel Case, supra, the tax bill was canceled on the theory that the contractor, in the absence of an ordinance prescribing a definite time limit, and under such a contract provision, had a reasonable time, but that the time actually used was unreasonable, and hence the bill was void; but in the case at bar there is no contention made that the time used was unreasonable, and, if such contention were insisted upon, it is apparent from the record before us that the delay in completing the work arose from the acts of the city government in compelling the work of reconstructing the street to cease for a fortnight in order to lay water mains and change street railway tracks. In passing the point now in hand, it is well enough to say that in the issues presented below and in this court no contention is made that there should be a deduction from the tax bill because of any delay, but appellants stand squarely on the proposition the tax bill is void, not that it shall be shaved down.

2. The contract contained the following clause: "Dressing of rock, granite or stone within the territorial limits of the State of Missouri—all the work of dressing rock or stone required by this contract shall be done within the territorial limits of the State of Missouri as provided by ordinance No. 18960 approved April 7th, 1897. Said ordinance is hereby made a part of this contract and must be observed in all of its provisions." ...

To continue reading

Request your trial
40 cases
  • St. Louis v. Senter Comm. Co., 32488.
    • United States
    • Missouri Supreme Court
    • 19 February 1937
    ...Natl. Bank v. Richardson, 56 S.W. 1117, 156 Mo. 270, 79 Am. St. Rep. 528; Palmer v. Alexander, 62 S.W. 691, 162 Mo. 127; Allen v. Labsap, 87 S.W. 926, 188 Mo. 692; Baker v. McMurry Contracting Co., 223 S.W. 45, 282 Mo. 685; Huling v. Bandera Flagstone Co., 87 Mo. App. 349; Trustees of Chris......
  • Reeves, Inc v. Stake
    • United States
    • U.S. Supreme Court
    • 19 June 1980
    ...American Yearbook ); State ex rel. Collins v. Senatobia Blank Book & Stationery Co., 115 Miss. 254, 76 So. 258 (1917); Allen v. Labsap, 188 Mo. 692, 87 S.W. 926 (1905); Hersey v. Neilson, 47 Mont. 132, 131 P. 30 (1913); Tribune Printing & Binding Co. v. Barnes, 7 N.D. 591, 75 N.W. 904 (1898......
  • Arkansas-Missouri Power Corp. v. City of Kennett
    • United States
    • Missouri Supreme Court
    • 25 September 1941
    ... ... Hackman, 273 Mo. 670, 202 S.W. 7; ... State ex rel. Kelly v. Hackman, 275 Mo. 636, 205 ... S.W. 161; State ex rel. Columbia v. Allen, 183 Mo ... 283, 82 S.W. 103; St. Louis Quarry & Construction Co. v ... Frost, 90 Mo.App. 677; Curtice v. Schmidt, 202 ... Mo. 703, 101 ... restricted the bidding. [ St. Louis Quarry and ... Construction Co. v. Frost, 90 Mo.App. 677; Allen v ... Labsap, 188 Mo. 692, 87 S.W. 926, 3 Ann. Cas. 306; ... St. Louis Quarry and Construction Co. v. Von Versen, ... 81 Mo.App. 519.] Cases from other ... ...
  • Arkansas-Missouri Power Corp. v. Kennett, 37562.
    • United States
    • Missouri Supreme Court
    • 25 September 1941
    ...and thereby illegally restricted the bidding. [St. Louis Quarry and Construction Co. v. Frost, 90 Mo. App. 677; Allen v. Labsap, 188 Mo. 692, 87 S.W. 926, 3 Ann. Cas. 306; St. Louis Quarry and Construction Co. v. Von Versen, 81 Mo. App. 519.] Cases from other jurisdiction have adopted a sim......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT