American Contracting Co. v. Norton
Decision Date | 11 June 1923 |
Docket Number | 23457 |
Parties | AMERICAN CONTRACTING CO. v. NORTON, HEAD & DENNEEN |
Court | Missouri Supreme Court |
Motion for Rehearing Overruled July 14, 1923.
Appeal from St. Louis Circuit Court; Charles B. Davis, Judge.
Affirmed.
Action by the American Contracting Company against Norton, Head & Denneen, a partnership. Judgment for defendants, and plaintiff appeals. Affirmed.
Kinealy & Kinealy, of St. Louis, for appellant.
Bates Williams & Baron, of St. Louis, for respondents.
The appeal is from a judgment in the circuit court of St. Louis in favor of the defendants, in an action by the American contracting Company to recover compensation for constructing a part of Mill Creek joint district sewer in said city.
The Carter Construction Company, August 15, 1914, entered into a contract with the city of St. Louis to construct the Mill Creek joint district sewer; the company, upon completion of the work, to be paid by tax bills for the work and material. The prices for the materials and for the work and labor in constructing the sewer are set out in detail and classified in the contract. The Carter Construction Company sublet this work to the defendants here, Norton, Head & Denneen a partnership, who also were to be paid in tax bills. Norton, Head & Denneen in turn sublet a part of the work to the plaintiff corporation, the American Contracting Company, to be paid for in cash.
The petition is in two counts. In the first count the American Contracting Company demands compensation in the sum of $ 281,338.71 for the full performance of its contract.
The petition alleges performance of the contract, setting forth in an attached statement the items, and admits payment of 85 per cent., $ 222,809.30, leaving a balance of $ 58,529.41, the amount demanded.
For a second count it alleges that at the special instance and request of defendants plaintiff performed work and furnished materials in addition to what was required in the contract, and that the reasonable value of such extras is $ 115,119.47: that defendant has paid on account of the same $ 69.234.97, and is entitled to another credit for $ 3,399.72, leaving balance due plaintiff $ 42,484.78, the amount demanded in the second count of the petition.
The defendant claims that the plaintiff has been paid in full; that the credits applied on the second count of the petition should be applied on the first count in excess of the amount sued for; that in fact nearly all the items claimed by the plaintiff as extras were in fact not extras, but were matters contemplated by the contract.
There was no dispute that under the contract the plaintiff had performed work and furnished material of the value of $ 281,338.71 charged in the first count, and was entitled to that amount.
The largest item of extras set forth in the second count of the petition relates to steel sheet piling left in the trench, 9,201,603 square feet at 62 cents, $ 57,049.94. The contract provided for the use of steel sheet instead of wood piling when deemed necessary by the city engineer, and plaintiff was to furnish it at 40 cents per square foot. This piling consisted of sheets 35 feet long and 14 inches wide, grooved and fitted into the sides of the trench so as to exclude fine sand and water.
As the work progressed some of this steel sheet piling was "pulled" and used again in the progress of the work. Some of it remained in the trench after the work was completed, and it is for that the defendant claims this extra compensation on the ground that it was not contemplated by the contract that any of it should be left in. About a year after the completion of the sewer, the principal contractor, the Carter Construction Company, obtained permission from the city to "pull" a considerable portion of this steel sheet piling, and pulled it. The controversy as to that will be noticed later in the opinion. Other items claimed as extras will be noticed also in the proper place.
Plaintiff's contract with Norton, Head & Denneen mentioned the contract of Carter Construction Company with the city as the "principal contract"; Norton, Head & Denneen are called the "contractor," and plaintiff the "subcontractor." The plaintiffs contract then provided that--
It would perform and complete the contract in workmanlike and substantial manner "to the satisfaction and approval of the sewer commissioner, as provided in the principal contract hereinafter mentioned, and in conformity in all particulars and respects with, and subject at all times and all respects to each and every of the requirements, conditions, restrictions, limitations and provisions contained in the principal contract hereinafter referred to and which are expressly made a part of this contract, all of the work required by the said principal contract to be performed. * * *"
The contract then proceeded:
In the classification of the items of work and materials, this appears:
"For steel sheet piling for bracing, per square foot, $ .40."
Other important provisions follow:
To continue reading
Request your trial