AMERICAN SURETY COMPANY OF NEW YORK v. United States

Decision Date03 November 1966
Docket NumberNo. 20710.,20710.
PartiesAMERICAN SURETY COMPANY OF NEW YORK, a corporation, and J. L. McBride dba Mac Exploration Company, Defendants/Appellants, v. UNITED STATES of America FOR the Use and Benefit of B & B DRILLING COMPANY, a corporation, Plaintiff/Appellee.
CourtU.S. Court of Appeals — Ninth Circuit

Morton Galane, Las Vegas, Nev., for appellants.

Singleton, DeLanoy & Jemison, Rex Jemison, Las Vegas, Nev., for appellee.

Before POPE, MERRILL and KOELSCH, Circuit Judges.

POPE, Circuit Judge.

This was an action brought under the Miller Act, 40 U.S.C. §§ 270a and 270b, to recover sums owing to the use plaintiff B & B Drilling Company, for equipment, labor and supplies furnished to the defendant McBride.

On March 15, 1960, United States, acting through the Atomic Energy Commission, entered into a written contract with McBride whereby the latter agreed to furnish all necessary materials, equipment and labor to drill seven well holes at the atomic test site at Camp Mercury, Nevada. On May 9, thereafter, McBride subcontracted a portion of the work under a written contract to the use plaintiff. The contract provided that the use plaintiff would drill holes to an estimated 6150 linear feet in depth and would furnish all equipment, labor and supplies necessary in connection therewith and in accordance with specifications and accepted drilling practices. It was provided that the work should be covered by a performance bond but the amount thereof was not specified. Payments for the work were to be made on or about the 15th day following the end of the month in which the work was performed, at stated amounts per lineal feet.

The use plaintiff entered the test site on May 18, 1960, and after several days spent in obtaining security clearance and setting up drilling equipment it began drilling on May 24 with McBride's approval although a performance bond had not been posted. On June 23, approximately one month after work commenced, an addendum was made to the original subcontract to the effect that the use plaintiff would obtain a performance and payment bond in the amount of $25,000. On July 28, thereafter, use plaintiff learned that it could not secure such a bond and communicated the information to McBride. The reason for this inability was that surety companies will not issue such bonds on work that is already in progress. Use plaintiff continued to drill until August 10, 1960, on which date it had not received payments for drilling previously done. On August 15, use plaintiff again demanded payment of the amount then due on the contract. This payment was refused because of the failure of use plaintiff to post the payment bond. McBride ordered the use plaintiff off the test site.

Upon trial to the court sitting without a jury, the court found that the failure of use plaintiff to obtain the bond was not a material breach of the contract but only a partial breach of such character that McBride was not validly excused from performing; that such failure did not give McBride the right to rescind the contract; that McBride was not justified in refusing to make the payments due for the work performed; that McBride had suffered no loss in consequence of the failure to furnish the bond; that he had not been required to pay for any of the use plaintiff's materials or labor and suffered no damages in consequence thereof. It found that the use plaintiff had substantially complied with the requirements of the contract. The court found that the amount due from the defendant to the use plaintiff under the written contract for two holes drilled was $22,149. After allowing two items of set-off against this sum1 it entered judgment for use plaintiff for the balance of $16,065 plus interest.

The defendants then took this appeal. Their first and principal contention is that the failure of the use plaintiff to obtain the bond was a material and substantial breach of contract on its part which operated to excuse McBride from any performance on his part and to render him not liable for the payment of the sums here awarded.

If we assume, as has been held, that the materiality of a breach of contract is primarily a factual question, Associated Lathing and Plastering Co. v. Louis C. Dunn, Inc., 135 Cal.App.2d 40, 286 P.2d 825, 830, and if the court's finding that the failure of the use plaintiff to obtain the bond was not a material breach, going to the essence of the contract, but was only a partial breach of contract, then authorities may be cited which hold that a slight breach will not necessarily end further duties of the injured person for the performance of the contract.2

Although the trial court's decision supporting a suit upon the contract was based upon the court's finding of substantial performance on the part of the use plaintiff, it is plain that recovery upon the contract might also have been allowed on the ground that since the performance of the condition relating to a payment bond was impossible from the beginning the non-performance of that condition could not be a defense for McBride.3

We think, however, that this case may be disposed of upon grounds which do not require us to inquire into the materiality or substantiality of the use plaintiff's failure to furnish the bond — grounds which disclose that in any event the use plaintiff was entitled to recover the judgment which was here awarded to him. We now refer to the rule set forth in Restatement of the Law of Contracts, § 357, which in material part reads as follows: "§ 357. Restitution in Favor of a Plaintiff Who Is Himself In Default. (1) Where the defendant fails or refuses to perform his contract and is justified therein by the plaintiff's own breach of duty or non-performance of a condition, but the plaintiff has rendered a part performance under the contract that is a net benefit to the defendant, the plaintiff can get judgment, except as stated in Subsection (2), for the amount of such benefit in excess of the harm that he has caused to the defendant by his own breach, in no case exceeding a ratable proportion of the agreed compensation, if

(a) the plaintiff\'s breach or non-per-performance is not wilful and deliberate; or
(b) the defendant, with knowledge that the plaintiff\'s breach of duty or non-performance of condition has occurred or will thereafter occur, assents to the rendition of the part performance, or accepts the benefit of it, or retains property received although its return in specie is still not unreasonably difficult or injurious.

(2) (Not material here) * * *

(3) The measure of the defendant's benefit from the plaintiff's part performance is the amount by which he has been enriched as a result of such performance unless the facts are those stated in Sub-section (1b), in which case it is the price fixed by the contract for such part performance, or, if no price is so fixed, a ratable proportion of the total contract price."

Appellant asserts and we assume that the law here applicable would be the law of Nevada. See Continental Casualty Company v. Schaefer, 9 cir., 173 F.2d 5, 7 to 8. While we find no Nevada cases dealing with problems of this kind, the rule stated in the last quotation from § 357 of the Restatement has been so universally approved that we take it for granted that the Supreme Court of Nevada would follow it.4 Particularly significant here is the fact that McBride knew of the use plaintiff's inability to procure the payment bond and yet he permitted the work to proceed. It is obvious that the use plaintiff's failure to supply the bond was not wilful or deliberate. Because McBride assented to the performance of the work by the use plaintiff notwithstanding his knowledge that the bond had not been supplied, he would be liable here even if the use plaintiff's breach had been wilful and without semblance of excuse.5

It is plain that if use plaintiff is permitted to recover under the rules set forth in Restatement § 357, supra, his recovery would be essentially one based on unjust enrichment of the defendant. If it be assumed that use plaintiff in failing to furnish the payment bond was guilty of a substantial default in the performance of the contract, then the recovery by the plaintiff would be upon the theory that he has rendered a part performance of value; or, as stated by Corbin on Contracts, § 1124, Vol. 5A, upon the theory "that he has done more good than harm to the defendant, and that the defendant will be unjustly enriched and the plaintiff unjustly penalized if the defendant is allowed to retain the beneficial part performance without paying anything in return."6

Since the trial court based its judgment upon the contract itself and not upon any theory of quasi-contractual liability, it of course based its award of damages upon the prices and rates of payment stated in the contract itself. The question arises whether, if we affirm the judgment for use plaintiff upon grounds stated in § 357 of the Restatement, supra, the measure of defendant's benefit is the price fixed by the contract for the part performance.

One answer to this question is to be found in ...

To continue reading

Request your trial
12 cases
  • United States v. Western Casualty and Surety Co.
    • United States
    • U.S. Court of Appeals — Ninth Circuit
    • June 4, 1974
    ...as to subcontracts to which the United States is not a party. American Surety Co. v. United States for the use of B & B Drilling Co., 368 F.2d 475, 478 (9th Cir. 1966); United States for the use of J. W. Briggs v. Grubb, 358 F.2d 508, 515 (9th Cir. 1966); Wells Benz, Inc. v. United States f......
  • Alvarez v. Insurance Co. of North America
    • United States
    • U.S. District Court — Northern District of California
    • August 4, 1987
    ...Corp. v. Western Casualty and Surety Co., 498 F.2d 335, 338 n. 4 (9th Cir.1974); American Surety Co. v. United States For the Use and Benefit of B & B Drilling Co., 368 F.2d 475, 478 (9th Cir.1966). Neither the alleged comprehensiveness of the regulatory scheme, nor the regulations, evidenc......
  • Fluor Corp. v. United States ex rel. Mosher Steel Co.
    • United States
    • U.S. Court of Appeals — Ninth Circuit
    • February 11, 1969
    ...P.2d 652, 663 (1954); Sam Macri & Sons, Inc. v. United States, 313 F.2d 119, 129-130 (9th Cir. 1963); American Sur. Co. of New York v. United States, 368 F.2d 475, 479-480 (9th Cir. 1966); 5 Corbin, Contracts § 1046, p. 286, § 1051, pp. "In short," Professor McCormick states, "it is the cha......
  • Ralston Purina Co. v. Parsons Feed & Farm Supply, Inc.
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • August 27, 1969
    ...counterclaim. Other cases where interest on the entire claim has been allowed are American Sur. Co. of New York v. United States for Use and Benefit of B & B Drilling Co., 368 F.2d 475, 479-480 (9 Cir. 1966); Fluor Corp. v. United States ex rel. Mosher Steel Co., 405 F.2d 823, 830 (9 Cir. 1......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT