Andy Floors, Inc. (Tyler Const. Corp.), Matter of

Decision Date31 March 1994
Citation202 A.D.2d 938,609 N.Y.S.2d 692
PartiesIn the Matter of the Arbitration between ANDY FLOORS INC., Appellant, and TYLER CONSTRUCTION CORPORATION, Respondent.
CourtNew York Supreme Court — Appellate Division

Stephen R. Spring (Mark Donahue, of counsel), Albany, for appellant.

Cade & Saunders P.C. (Daniel J. Persing, of counsel), Albany, for respondent.

Before CARDONA, P.J., and MERCURE, CASEY and YESAWICH, JJ.

MERCURE, Justice.

Appeal from an order of the Supreme Court (Conway, J.), entered July 30, 1993 in Albany County, which denied petitioner's application pursuant to CPLR 7503 to stay arbitration between the parties.

Respondent, the general contractor on a construction project at the Albany County Jail, subcontracted with petitioner for the furnishing and installation of flooring. The parties incorporated into their subcontract the arbitration provisions of the general contract between respondent and the owner, which provided in pertinent part that:

Notice of the demand for arbitration shall be filed in writing with the other parties to the dispute who have agreed to arbitrate, and with the American Arbitration Association. The demand for arbitration shall be made within a reasonable time after the claim, dispute or other matter in question has arisen, and in no event shall it be made more than six months after the claim has arisen.

A dispute arose between the parties on December 17, 1992, and on June 17, 1993 respondent served a demand for arbitration upon petitioner by certified mail, return receipt requested. The demand was received by petitioner on June 19, 1993. Petitioner thereafter made the present application to stay arbitration upon the ground, inter alia, that respondent's demand for arbitration, received by petitioner following the expiration of the requisite six-month period, was untimely. Supreme Court denied the application upon the ground that the demand for arbitration was timely served in accordance with CPLR 7503(c). Petitioner appeals.

We reject petitioner's contention that the provision of the contract that the demand be "filed" required actual receipt within the six-month period and accordingly affirm. It is a fundamental tenet of contract law that, "unless a contract provides otherwise, the law in force at the time the agreement is entered into becomes as much a part of the agreement as though it were expressed or referred to therein, for it is presumed that the parties had such law in contemplation when the contract was made and the contract will be construed in the light of such law" (Dolman v. United States Trust Co. of N.Y., 2 N.Y.2d 110, 116, 157 N.Y.S.2d 537, 138 N.E.2d 784; see, Strauss v. Union Cent. Life Ins. Co., 170 N.Y. 349, 356, 63 N.E. 347; 22 NY Jur2d, Contracts, § 202). At all times relevant to this proceeding, including the date of formation of the contract being construed, CPLR 7503(c) expressly prescribed the method of service of a demand for arbitration, i.e., "in the same manner as a summons or by registered or certified mail, return receipt requested". Further, when mail is used as the means of service, the claim is deemed interposed when the mail is posted (see, CPLR 7503[c]; Matter of Knickerbocker Ins. Co. [Gilbert], 28 N.Y.2d 57, 65-66, 320 N.Y.S.2d 12, 268 N.E.2d 758; Siegel, NY Prac § 590 [2d ed]. It thus follows that, if CPLR 7503 applies in this case, respondent's demand for arbitration was timely served and Supreme Court correctly denied petitioner's application to stay arbitration.

It is well established that the parties to an arbitration agreement may...

To continue reading

Request your trial
8 cases
  • New Brunswick Theological Seminary v. Van Dyke
    • United States
    • New York Supreme Court — Appellate Division
    • June 3, 2020
  • Burns v. Burns
    • United States
    • New York Supreme Court — Appellate Division
    • July 25, 2018
    ...Dept. 1997], lv dismissed 91 N.Y.2d 887, 668 N.Y.S.2d 564, 691 N.E.2d 636 [1998] ; Matter of Andy Floors, Inc. [Tyler Constr. Corp.], 202 A.D.2d 938, 938–939, 609 N.Y.S.2d 692 [3d Dept. 1994] ).The statutory scheme corresponding to the agreement in this case is Domestic Relations Law § 236,......
  • N.Y. Merchants Protective Co. Inc. v. Mima's Kitchen Inc.
    • United States
    • New York Supreme Court — Appellate Division
    • April 11, 2011
    ...govern the arbitration and those rules provided for service by [31 Misc.3d 83] mail]; Matter of Andy Floors, Inc. [Tyler Constr. Corp.], 202 A.D.2d 938, 939, 609 N.Y.S.2d 692 [1994] [“It is well established that the parties to an arbitration agreement may prescribe a method of service diffe......
  • Inc. v. Mima's Kitchen, Inc. (In re N.Y. Merchant's Protective Co.)
    • United States
    • New York Supreme Court — Appellate Division
    • February 13, 2014
    ...may prescribe a method of service different from that set forth in the CPLR ( see Matter of Andy Floors, Inc. [Tyler Constr. Corp.], 202 A.D.2d 938, 609 N.Y.S.2d 692). Here, under the terms of their agreement, the parties consented to service by mail of a notice of petition and petition to ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT