Arcon Const. Co. v. State, By and Through Dept. of Transp.

Decision Date06 January 1982
Docket NumberNo. 13373,13373
Citation314 N.W.2d 303
PartiesARCON CONSTRUCTION COMPANY, Plaintiff and Appellee, v. The STATE of South Dakota, Acting by and Through Its DEPARTMENT OFTRANSPORTATION and the Board of Transportation Consisting of Roger Bernard, JimRothstein, Jim Sharp, Bob Appelwick, Jim Doyle, Pat Beckman, Jerry Leidholdt,Jerry Shoener, DonJacobsen and Gene Rowen, Defendant, Third-Party Plaintiff and Appellant, v. EMPLOYERS MUTUAL LIABILITY INSURANCE COMPANY OF WISCONSIN, a WisconsinCorporation, Third-Party Defendant and Appellee.
CourtSouth Dakota Supreme Court

Gary F. Colwill of Schmidt, Schroyer, Colwill & Zinter, Pierre, for plaintiff and appellee and third-party defendant and appellee.

Carl W. Quist, Asst. Atty. Gen., Pierre, for defendant and third-party plaintiff and appellant; Mark V. Meierhenry, Atty. Gen., Pierre, on brief.

HENDERSON, Justice.

ACTION

A declaratory judgment was brought by Arcon Construction Company (Arcon) against the State of South Dakota through its Department of Transportation and Transportation Commission (Commission) to relieve Arcon from a bid it had submitted on a public construction work project and to obtain discharge of its bid bond. The Commission subsequently filed a third-party complaint against Arcon's surety, Employers Mutual Liability Company of Wisconsin. The trial court ruled that Arcon is entitled to cancellation of its bid and have its bid bond refunded. We affirm.

FACTS

This case stems from bids received for the construction of a state highway project in Yankton County. In conjunction with this project, the Commission provided all prospective bidders with a specific bid proposal form. This bid form contained ninety-seven line items which bidders were required to submit unit prices on. In addition, all prospective bidders received a memo from the Commission prior to bidding informing them that all bids must include a four percent gross receipts tax. No specific line item for this tax, however, was provided for on the aforementioned bid form.

Elwood N. Olsen and John T. Laingen, both engineers for Arcon, were in Pierre, South Dakota, the night of June 25, 1979, for the purpose of computing costs for the Yankton County project. The bids were to be submitted on June 26, 1979. Standard procedure in making this type of bid necessitates last-minute computations so as to reflect the most current price information. Olsen and Laingen computed the bid price by filling in a "spread sheet," which consists of a gridded chart listing all the specific items that the Commission has assigned as bid items.

Since there was no bid item on the Commission's bid form to slot the figure representing the four percent gross receipts tax, Olsen and Laingen intended to slot the tax amount under the bid item referred to as "mobilization." Mobilization is a flexible item in the bid form which is used to reflect last minute changes.

On the spread sheet, the total amount of Arcon's bid, except for mobilization, was $4,463,811.20. Also on the spread sheet, $178,552.45 was listed as the amount for the four percent gross receipts tax on the entire bid, excepting mobilization. Initially, the mobilization figure was $245,000.00, but was subsequently adjusted to $224,200.00. To this figure was added $8,968.00, (which was the four percent gross receipts tax on $224,200.00) to total $233,000.00 (rounded off). This figure of $233,000.00 was then entered as the mobilization figure on the bid form provided by the Commission. Arcon's bid to the Commission totalled $4,875,303.65; this amount reflected inclusion of the $178,552.45 figure of the gross receipts tax. Arcon was also required to submit a bid bond of $243,768.18, which was five percent of the total bid. When the Commission added up all the individual bid items, however, the total was less than Arcon's aggregate bid. This discrepancy was due to Arcon's failure to list the $178,552.45 tax as an individual bid item. The Commission's addition of the individual bid items totalled $4,696,811.20 for Arcon's entire bid and Arcon, being the low bidder, was awarded the contract at this price.

Olsen and Laingen left Pierre for Minnesota immediately after the bid was submitted and, during the morning hours of June 27, 1979, discovered that the $178,552.45 mobilization figure was erroneously excluded from the mobilization bid item on the Commission's bid form. Upon discovering this error, Olsen immediately telephoned Maynard Sommer, a highway engineer for the Commission, and advised him of the error and asked that Arcon be relieved of the bid. At the time of this call, the Commission had not yet met or considered the bids on the Yankton County project. Olsen also sent a letter dated June 27, 1979, to the Commission advising it of the error and requesting that Arcon be relieved of its bid.

After being advised of Arcon's miscomputation, the Commission met on June 27, 1979, and awarded the contract to Arcon at $4,696,811.20; said amount being approximately $178,552.45 below the bid Arcon intended to submit. Arcon refused to sign the contract at the figure reached by the Commission and, consequently, initiated this declaratory judgment action.

ISSUES
I.

Did the trial court err by ruling that Arcon was entitled to have its bid lawfully cancelled and its bid bond refunded? We hold that it did not.

II.

Did the trial court erroneously deny the Commission's motion to disqualify Attorney Gary Colwill from representing both Arcon and its surety, third-party defendant Employers Mutual Liability Company of Wisconsin? We hold that it did not.

DECISION
I.

With respect to declaratory orders, judgments and decrees, an appellant bears the burden of showing that the findings of the trial court are clearly erroneous. SDCL 21-24-13; SDCL 15-6-52(a); Rapid City Area School District No. 51-4 v. Black Hills and Western Tours, Inc., 303 N.W.2d 811 (S.D.1981). From a review of the record, we hold that the Commission did not meet this burden.

Courts will grant equitable relief to a bidder on a public contract where the bidder has made a material mistake of fact in the submitted bid and, upon discovery of that mistake, acts promptly in informing the appropriate public authorities of the mistake and of its intention to withdraw. State Highway Commission v. State Construction Company, 203 Or. 414, 280 P.2d 370 (1955); 64 Am.Jur.2d, Public Works and Contracts, § 84 (1972).

To grant equitable relief to a bidder, however, certain essential conditions must be first established: the mistake must be of such consequence that enforcement would be unconscionable; the mistake must relate to the substance of the consideration, that is, a material feature; the mistake must have occurred regardless of the exercise of ordinary care; and, upon relief, it must be possible to place the other party in status quo. State Board of Control v. Clutter Construction Corporation, 139 So.2d 153 (Fla.App.1962); 52 A.L.R.2d 792 (1957). See SDCL 21-12-1; SDCL 53-11-2; SDCL 21-12-2; SDCL 21-12-3. Relief can be granted if these conditions are established by clear and convincing evidence. State Board of Control v. Clutter Construction Corporation, supra.

Citing specification 3.1 of the South Dakota Specifications for Roads and Bridges, 1977 Edition, which were incorporated into the proposed contract for this particular project, the Commission contends that Arcon should be held to its bid due to the nature of the error involved. We do not agree. Specification 3.1 provides in pertinent part:

The right is reserved to reject any or all proposals, to waive technicalities, to advertise for new proposals, if in the judgment of the board, the best interest of the Department will be promoted thereby.

We do not believe that the mistake herein involved was merely "technical" in nature. Although the amount of the error, $178,552.45, is significantly less than the total amount of the bid (approximately 4.7 million dollars), this disparity does not persuade us that the mistake was not material; hence, the "right of waiver" provision in specification 3.1 cannot be...

To continue reading

Request your trial
4 cases
  • Powder Horn Constructors, Inc. v. City of Florence
    • United States
    • Colorado Supreme Court
    • April 25, 1988
    ...Sarkisian Bros., Inc., 87 A.D.2d 984, 451 N.Y.S.2d 945, aff'd, 57 N.Y.2d 618, 454 N.Y.S.2d 71, 439 N.E.2d 880 (1982); Arcon Constr. Co. v. State, 314 N.W.2d 303 (S.D.1982); State Highway Comm'n v. Canion, 250 S.W.2d 439 (Tex.Civ.App.1952); see also D. Dobbs, Handbook on the Law of Remedies ......
  • Marana Unified School Dist. No. 6 v. Aetna Cas. & Sur. Co., 2
    • United States
    • Arizona Court of Appeals
    • December 3, 1984
    ...(D.Conn.1941); City of Syracuse v. Sarkisian Brothers, Inc., 87 A.D.2d 984, 451 N.Y.S.2d 945 (1982); Arcon Construction Co. v. State Department of Transportation, 314 N.W.2d 303 (S.D.1982); Wil-Fred's Inc. v. Metropolitan Sanitary District, 57 Ill.App.3d 16, 14 Ill.Dec. 667, 372 N.E.2d 946 ......
  • Bankers Trust of South Carolina v. Bruce
    • United States
    • South Carolina Court of Appeals
    • September 4, 1984
    ...In the Interest of H.W.E., 613 S.W.2d 71 (Tex.Civ.App.1981); Unified Sewerage Agency v. Jelco, supra; see also Arcon Construction Co. v. State, 314 N.W.2d 303 (S.D.1982) (no conflicting or hostile interests). There is very little possibility, if any, Sanders possessed any special insight, a......
  • City of Florence v. Powder Horn Constructors Inc.
    • United States
    • Colorado Court of Appeals
    • October 17, 1985
    ...Md. 62, 375 A.2d 237 (1977); Cataldo Construction Co. v. County of Essex, 110 N.J.Super. 414, 265 A.2d 842 (1970); Arcon Construction Co. v. State, 314 N.W.2d 303 (S.D.1982). A small minority of jurisdictions have denied relief in all cases. See Triple A Contractors, Inc. v. Rural Water Dis......
4 books & journal articles
  • Table of Cases
    • United States
    • ABA General Library Construction Law
    • June 22, 2009
    ...n.101 Aragona Constr. Co. v. United States, 165 Ct. Cl. 382 (1964) 451 n.78 Arcon Constr. Co. v. State, by and through Dept. of Transp., 314 N.W.2d 303 (S.D. 1982) 208 n.111 Argonaut Ins. Co. v. Commercial Standard Ins. Co., 380 So. 2d 1066 (Fla. App. 1980) 552 n.8 Argonaut Ins. Co. v. Town......
  • Table of Cases
    • United States
    • ABA General Library Construction Law
    • January 1, 2009
    ...n.101 Aragona Constr. Co. v. United States, 165 Ct. Cl. 382 (1964) 451 n.78 Arcon Constr. Co. v. State, by and through Dept. of Transp., 314 N.W.2d 303 (S.D. 1982) 208 n.111 Argonaut Ins. Co. v. Commercial Standard Ins. Co., 380 So. 2d 1066 (Fla. App. 1980) 552 n.8 Argonaut Ins. Co. v. Town......
  • Contractor Selection
    • United States
    • ABA General Library Construction Law
    • June 22, 2009
    ...include a last-minute $130 increase by one of the subcontractors). 111. See Arcon Constr. Co. v. State, by and through Dept. of Transp., 314 N.W.2d 303 (S.D. 1982) (relieving the contractor from its bid on the grounds of unconscionability when the bid recipient “knew of the mistake prior to......
  • Contractor Selection
    • United States
    • ABA General Library Construction Law
    • January 1, 2009
    ...include a last-minute $130 increase by one of the subcontractors). 111. See Arcon Constr. Co. v. State, by and through Dept. of Transp., 314 N.W.2d 303 (S.D. 1982) (relieving the contractor from its bid on the grounds of unconscionability when the bid recipient “knew of the mistake prior to......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT