Arnell Constr. Corp. v. N.Y.C. Sch. Constr. Auth.

Decision Date09 November 2016
Citation41 N.Y.S.3d 101,144 A.D.3d 714,2016 N.Y. Slip Op. 07282
Parties ARNELL CONSTRUCTION CORPORATION, appellant, v. NEW YORK CITY SCHOOL CONSTRUCTION AUTHORITY, respondent.
CourtNew York Supreme Court — Appellate Division

144 A.D.3d 714
41 N.Y.S.3d 101
2016 N.Y. Slip Op. 07282

ARNELL CONSTRUCTION CORPORATION, appellant,
v.
NEW YORK CITY SCHOOL CONSTRUCTION AUTHORITY, respondent.

Supreme Court, Appellate Division, Second Department, New York.

Nov. 9, 2016.


41 N.Y.S.3d 102

Goldberg & Connolly, Rockville Centre, NY (Tara D. McDevitt, Michael J. Rosenthal, and Henry L. Goldberg of counsel), for appellant.

Zachary W. Carter, Corporation Counsel, New York, NY (Pamela Seider Dolgow, Dona B. Morris, and Max McCann of counsel), for respondent.

JOHN M. LEVENTHAL, J.P., JOSEPH J. MALTESE, HECTOR D. LaSALLE, and VALERIE BRATHWAITE NELSON, JJ.

In an action to recover damages for breach of contract, the plaintiff appeals from an order of the Supreme Court, Queens

144 A.D.3d 715

County (Sampson, J.), entered June 20, 2014, which granted the defendant's motion for summary judgment dismissing the complaint and denied its cross motion for summary judgment on the complaint.

ORDERED that the order is modified, on the law, by deleting the provision thereof granting the defendant's motion for summary judgment dismissing the complaint, and substituting therefor a provision denying that motion; as so modified, the order is affirmed, without costs or disbursements.

The instant action arises out of a contract between the defendant and the plaintiff for the renovation of a public school and the construction of a five-story addition to the school. The plaintiff was the general contractor for the project. On May 21, 2009, the defendant directed the plaintiff to install a sidewalk shed around the existing school building while work was being performed on the roof, and the plaintiff installed the sidewalk shed. A dispute arose concerning whether the plaintiff was responsible under the contract to install the sidewalk shed. The plaintiff asserted that this constituted extra work and requested that the defendant compensate the plaintiff for the cost of the installation, maintenance, and dismantling of the sidewalk shed. The defendant refused to compensate the plaintiff.

The plaintiff commenced this action to recover damages for breach of contract, alleging that it was entitled to compensation for the sidewalk shed that it installed around the existing school building. The defendant asserted that the plaintiff was obligated to install the sidewalk shed because the contract required the plaintiff to “install and maintain sidewalk sheds” in

41 N.Y.S.3d 103

“areas within the property lines ... [where] necessary to provide proper protection to the school population, workers and pedestrians,” and to comply with “the provisions of all applicable State and City laws, rules, regulations and requirements pertaining to building code safety requirements,” including the New York City Building Code. The defendant moved for summary judgment dismissing the complaint, and the plaintiff cross-moved for summary judgment on the complaint. The Supreme Court granted the defendant's motion and denied the plaintiff's cross motion. The plaintiff appeals.

The essential elements of a cause of action to recover damages for breach of contract are (1) the existence of a contract, (2) the plaintiff's performance pursuant to the contract, (3) the defendant's breach of its contractual obligations, and (4) damages resulting from the breach (see Legum v. Russo, 133 A.D.3d 638, 639, 20 N.Y.S.3d 124 ). A contractor may properly recover payment

144 A.D.3d 716

for extra work that is not contemplated by the terms of the original agreement, and which is performed at the direction of the defendant (see Hi–Amp Elec. Contr. Corp. v. Maximum Mech. Corp., 37 A.D.3d 541, 541–542, 829 N.Y.S.2d 679 ). However, a contractor may not recover for any alleged extra work that was actually covered by the terms of the original contract (see Novair Mech. Corp. v. Universal Mgt. & Contr. Co...

To continue reading

Request your trial
26 cases
  • World Ambulette Transp., Inc. v. Kwan Haeng Lee
    • United States
    • New York Supreme Court — Appellate Division
    • May 16, 2018
    ...( W.W.W. Assocs. v. Giancontieri , 77 N.Y.2d at 162, 565 N.Y.S.2d 440, 566 N.E.2d 639 ; see Arnell Constr. Corp. v. New York City Sch. Constr. Auth. , 144 A.D.3d 714, 716, 41 N.Y.S.3d 101 ). "[A] court should determine the intent of the parties from within the four corners of the contract w......
  • Monti v. DiBedendetto
    • United States
    • New York Supreme Court — Appellate Division
    • June 14, 2017
  • Kollatz v. Kos Bldg. Grp., LLC
    • United States
    • New York Supreme Court — Appellate Division
    • November 25, 2020
    ...defendant's breach of its contractual obligations, and (4) damages resulting from the breach" ( Arnell Constr. Corp. v. New York City Sch. Constr. Auth., 144 A.D.3d 714, 715, 41 N.Y.S.3d 101 ; see Legum v. Russo, 133 A.D.3d 638, 639, 20 N.Y.S.3d 124 ). The defendants' submissions conclusive......
  • Manes v. JP Morgan Chase Bank
    • United States
    • U.S. District Court — Southern District of New York
    • March 7, 2022
    ...and (4) damages.” Harsco Corp. v. Segui, 91 F.3d 337, 348 (2d Cir. 1996); accord Arnell Constr. Corp. v. N.Y. City Sch. Constr. Auth., 144 A.D.3d 714, 715 (2d Dep't 2016). Further, to state a claim for breach of contract, a complaint must allege the specific provisions of the contract upon ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT