Arrow Plumbing v. N. AMERICAN MECHANICAL SERVICES, C.A. No. 92-372L.

Decision Date25 January 1993
Docket NumberNo. C.A. No. 92-372L.,C.A. No. 92-372L.
Citation810 F. Supp. 369
PartiesARROW PLUMBING AND HEATING, INC., Plaintiff, v. NORTH AMERICAN MECHANICAL SERVICES CORP., d/b/a North American Construction Corp. and St. Paul Fire and Marine Insurance Company, Defendants.
CourtU.S. District Court — District of Rhode Island

Geoffrey A. Regan, McGovern Noel & Benik, Providence, RI, for plaintiff.

Michael A. Kelly, W. Mark Russo, Adler Pollock & Sheehan, Providence, RI, for defendants.

MEMORANDUM AND ORDER

LAGUEUX, Chief Judge.

This matter is presently before the Court on the motion of defendants to transfer this action to the United States District Court for the Western District of Texas, pursuant to 28 U.S.C. § 1406(a).

This action arises out of a construction project at the Advanced Weapons Research Facility, Naval Underwater Systems Center in Newport, Rhode Island. Defendant North American Mechanical Services Corp., d/b/a North American Construction Corp. ("North American") was the prime contractor on the job under contract with the United States government. North American engaged plaintiff Arrow Plumbing and Heating, Inc. ("Arrow") to perform certain work and provide materials under a "Subcontract Agreement" which contained the following provision:

The Subcontract Agreement and any claims arising under it shall be governed by the laws of the State of Texas and exclusive venue shall be proper in Bexar County, Texas.

Defendant St. Paul Fire and Insurance Co. ("St. Paul") issued performance and payment bonds for the project as required under the Miller Act, 40 U.S.C. § 270a.

Arrow performed work on the project until May 1, 1992, when a dispute as to payment under the subcontract resulted in the termination of Arrow's involvement in the project. On July 1, 1992, Arrow filed for bankruptcy protection in the United States Bankruptcy Court for the District of Rhode Island.

Arrow filed the instant action in this Court on July 7, 1992, seeking payment under the subcontract, damages for breach of contract and recovery in quantum meruit from North American, and payment under the bond against North American and St. Paul. Jurisdiction was claimed under the diversity statute, 28 U.S.C. § 1332(a), and the Miller Act, 40 U.S.C. § 270b.

Defendants moved for transfer of the action to the United States District Court for the Western District of Texas pursuant to the forum selection provision in the subcontract. Plaintiff has objected on the ground that the Miller Act requires that this action be heard in the District of Rhode Island, and that it would be unreasonable to enforce the forum selection provision. The parties engaged in oral argument on October 9, 1992, and the matter was taken under advisement. It is now in order for decision.

Discussion

Defendants move to transfer this case under 28 U.S.C. § 1406(a) which provides:

The district court of a district in which is filed a case laying venue in the wrong division or district shall dismiss, or if it be in the interest of justice, transfer such case to any district or division in which it could have been brought.

A motion under § 1406(a) for improper venue, rather than under § 1404(a) for inconvenience, is appropriate where the moving party seeks to enforce a contractual forum selection clause. D'Antuono v. CCH Computax Systems, Inc., 570 F.Supp. 708 (D.R.I.1983).

Plaintiff seeks to avoid the contractual forum on two grounds. First, it argues that the Miller Act vests exclusive venue in this Court. Second, he argues that enforcement of the forum selection clause is unreasonable given plaintiff's present circumstances.

A. The Miller Act

Plaintiff argues that this case may not be transferred because the Miller Act vests exclusive venue in this Court. The relevant provision, 40 U.S.C. § 270b(b) provides:

Every suit instituted under this section shall be brought in the name of the United States for the use of the person suing, in the United States District Court for any district in which the contract was to be performed and executed and not elsewhere ...

Although the language of this subsection appears to support plaintiff's contention, decisional law in this area makes clear that the statutory venue may be overridden by a valid contractual forum selection provision.

The Supreme Court has held that Section 270b is not jurisdictional, but rather is only a venue provision. F.D. Rich Co. v. United States, 417 U.S. 116, 94 S.Ct. 2157, 40 L.Ed.2d 703 (1974). Venue may be waived by a failure to timely object, Commercial Casualty Ins. Co. v. Consolidated Stone Co., 278 U.S. 177, 49 S.Ct. 98, 73 L.Ed. 252 (1929), or may be waived or varied in advance by contract. National Equipment Rental, Ltd. v. Szukhent, 375 U.S. 311, 84 S.Ct. 411, 11 L.Ed.2d 354 (1964). Furthermore, the Miller Act venue provision is intended to benefit defendants, not plaintiffs. See United States ex rel. Aurora Painting, Inc. v. Fireman's Fund Ins. Co., 832 F.2d 1150, 1152 (9th Cir.1987) (Miller Act venue provision intended to protect the surety from liability beyond the amount of the bond that might result from multiple suits in several different jurisdictions.); United States ex rel. Capolino Sons, Inc. v. Electronic & Missile Facilities, Inc., 364 F.2d 705, 707 (2d Cir.1966); Electronic & Missile Facilities, Inc. v. United States ex rel. Moseley, 306 F.2d 554, 556 (5th Cir. 1962), rev'd on other grounds, Moseley v. Electronic & Missile Facilities, Inc., 374 U.S. 167, 83 S.Ct. 1815, 10 L.Ed.2d 818 (1963).

The Fifth Circuit has specifically held that a valid forum selection clause can override the Miller Act venue provision. In In re Fireman's Fund Ins. Cos., 588 F.2d 93 (5th Cir.1979), the Court stated,

The Miller Act venue provision exists for the convenience of the parties. Such a provision is subject to variation by their agreement which should especially be given effect in a case such as this, where the defendants, for whose special protection the venue clause exists, themselves have moved for transfer in accord with the forum selection clause.

Id. at 95. Other courts have followed that reasoning in upholding the enforceability of arbitration clauses in subcontract agreements. See, e.g., United States ex rel. Capolino Sons, Inc. v. Electronic & Missile Facilities, Inc., 364 F.2d 705 (2d Cir. 1966).

Plaintiff suggested at oral argument that even if the contractor could invoke the forum selection clause the surety cannot do so, presumably because the surety was not a party to the subcontract agreement. The Court does not agree with this reasoning. A surety generally stands in the shoes of its principal. United States ex rel. Fireman's Fund Ins. Co. v. Frank Briscoe Co., 462 F.Supp. 114, 116 (E.D.La. 1978). It may avail itself of any defense which is available to its principal except those that are purely personal, such as bankruptcy or infancy. 72 C.J.S. Principal & Surety § 189 at 318-19 (1987). Although a surety is not a party to a subcontract agreement, its liability under a payment bond is determined by the agreements between its principal and the subcontractor. The surety therefore should have all the benefits and suffer all the disadvantages that would accrue to the general contractor under those agreements. 462 F.Supp. at 117. See also In re Fireman's Fund Ins. Cos., 588 F.2d 93 (5th Cir.1979) (holding that forum selection clause in subcontract overrides Miller Act venue provision and warrants transfer of action against contractor and surety).

The Miller Act does not require that this action be heard in this Court. The motion to transfer must therefore be decided on the standard for determining the enforceability of any other contractual forum selection clause.

B. Enforceability of the forum selection clause

The enforceability of a forum selection clause is governed by the standard enunciated by the Supreme Court in The Bremen v. Zapata Off-Shore Co., 407 U.S. 1, 92 S.Ct. 1907, 32 L.Ed.2d 513 (1972). In that case the Court gave effect to a forum selection clause, holding that such a clause is "prima facie valid and should be enforced unless enforcement is shown by the resisting party to be `unreasonable' under the circumstances." 407 U.S. at 10. In applying that standard, the First Circuit has stated that "to establish that a particular choice-of-forum clause is unreasonable, a resisting party must present evidence of fraud, undue influence, overweening bargaining power or such serious inconvenience in litigating in the selected forum that it is effectively deprived of its day in court." Fireman's Fund American Insurance Co. v. Puerto Rican Forwarding Co., 492 F.2d 1294, 1297 (1st Cir.1974). A forum selection clause is also unenforceable "if enforcement would contravene a strong public policy of the forum in which suit is brought." The Bremen, 407 U.S. at 15, 92...

To continue reading

Request your trial
21 cases
  • In re N. Parent, Inc., Bankruptcy No. 97-42411-HJB
    • United States
    • U.S. Bankruptcy Court — District of Massachusetts
    • June 26, 1998
    ...a heavy burden in showing that trial in the selected forum is so `seriously inconvenient.'" Arrow Plumbing and Heating, Inc. v. North Am. Mechanical Serv. Corp., 810 F.Supp. 369, 372 (D.R.I. 1993). Under the Supreme Court's reasoning in Bremen the Debtor must demonstrate that "trial in the ......
  • MIDDLEBROOK TECH v. Moore
    • United States
    • Court of Special Appeals of Maryland
    • May 7, 2004
    ...his principal, he may not raise personal defenses, including the defense of bankruptcy); Arrow Plumbing and Heating, Inc. v. North American Mechanical Services Corp., 810 F.Supp. 369, 372 (D.R.I.1993). Middlebrook first contends that the circuit court erred in granting summary judgment to M......
  • In re Manchester, Inc.
    • United States
    • U.S. Bankruptcy Court — Northern District of Texas
    • June 1, 2009
    ...day in court." M/S Bremen, 407 U.S. at 17, 92 S.Ct. 1907. See also Afram Carriers, 145 F.3d at 301; Arrow Plumbing & Heating, Inc. v. N. Am. Mech. Servs., 810 F.Supp. 369, 372 (D.R.I.1993). Within a bankruptcy context, "the mere fact that Debtor/Plaintiff is in bankruptcy is not sufficient ......
  • Bavaria Yachts United States, LLLP v. GMBH (In re Bavaria Yachts United States, LLLP)
    • United States
    • U.S. Bankruptcy Court — Northern District of Georgia
    • October 6, 2017
    ...action would deprive the party of its day in court"—filing for bankruptcy alone is insufficient. Arrow Plumbing & Heating, Inc. v. N. Am. Mech. Servs. Corp. , 810 F.Supp. 369, 373 (D.R.I. 1993) ; see also Manchester Inc. v. Lyle (In re Manchester Inc.) , 417 B.R. 377, 387 (Bankr. N.D. Tex. ......
  • Request a trial to view additional results
1 books & journal articles
  • Annual survey of fidelity and surety law, 1993.
    • United States
    • Defense Counsel Journal Vol. 61 No. 1, January 1994
    • January 1, 1994
    ...due its principal on a separate contract from the one on which the surety suffered its loss. (1.)995 F.2d 656 (6th Cir. 1993). (2.)810 F.Supp. 369 (D. R.I. 1993). (3.)995 F.2d. 515 (4th Cir. 1993). (4.)988 F.2d. 88 (10th Cir. 1993). (5.)140 F.2d 115 (10th Cir. 1944). (6.)20 Cal.Rptr.2d 200 ......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT