Artesian Water Co. v. State, Dept. of Highways and Transp.

Decision Date03 December 1974
Citation330 A.2d 441
CourtSupreme Court of Delaware
PartiesARTESIAN WATER COMPANY, a corporation of the State of Delaware, Plaintiff below, Appellants, v. STATE of Delaware, DEPARTMENT OF HIGHWAYS & TRANSPORTATION, Defendant below, Appellee.

Upon appeal from Superior Court. Affirmed as modified.

Richard J. Abrams and Stephen E. Herrmann of Richards, Layton & Finger, Wilmington, for plaintiff below, appellant.

Aubrey B. Lank and Christopher S. Flanagan of Theisen, Lank & Mulford, Wilmington, for defendant below, appellee.

Before DUFFY and McNEILLY, JJ., and BROWN, Vice-Chancellor.

McNEILLY, Justice:

This is an appeal from a decision of the Superior Court granting defendant's cross-motion for summary judgment in a declaratory judgment action. See Artesian Water Company v. State of Delaware, Department of Highways and Transportation, Del.Super., 330 A.2d 432 (1973).

In a learned discussion of the interplay between recent state and federal relocation assistance statutes, the Superior Court concluded that the plaintiff had no right to full relocation cost compensation since the highway project here involved had less than ninety percent federal funding. Compare State Highway Dept. v. Delaware Power and Light Co., Del.Supr., 39 Del.Ch. 467, 167 A.2d 27 (1961).

We agree with the Court's rationale, and we further agree with the Court's conclusion as to the eminent domain issue, that is to say, plaintiff held no compensable interest in defendant's real property. We disagree, however, with the Court's conclusion as to the applicability of certain franchise agreements.

In 1955 and 1956, plaintiff and defendant entered into franchise agreements whereby the former was permitted to install a water distribution system in and along Delaware Route 141 (Basin Road).

In 1958 and 1959, highway constrution in this area forced the plaintiff to relocate substantially all (95%) of its water line from the area covered by the 1955--56 agreements to an adjacent location. 1

This realigned right-of-way was not within the geographic boundaries delineated by these agreements, and they were never amended to specifically include the metes and bounds of this relocated right-of-way. In 1971, the relocation here involved, stirred this case to issue by reason of defendant's refusal to reimburse plaintiff for its relocation costs. 2

The 1955--56 agreements are expressly made subject to an attached schedule of conditions and restrictions. By its terms the schedule applies to '. . . the laying of all electric conduits, water, steam and gas pipes upon or in any of the State Highways or upon any portion thereof.' Clause 5 thereof provides:

'Whenever it becomes necessary to relocate any pole or poles, pipes, conduits or other construction permitted, which interferes unreasonably with entrance to land abutting on said Highways, or interferes with changes of said Highways, the Chief Engineer of the Highway Department shall designate and approve new and suitable locations for such poles, pipes, conduits or other construction, and, upon reasonable notice from said Chief Engineer or his representative, the holder of the permit shall relocate such pole or poles, pipes, conduits or other construction, according to such designation, at its sole cost and expense.'

The Court below correctly stated that 'These agreements if applicable would clearly place the burden on Artesian to absorb all expenses for the relocation of its facilities from the areas over which the franchises were granted.' However the Court determined that due to the 1958--59 relocation, only 5% Of the original right-of-way specifically encompassed by the franchise agreements was still being used by the plaintiff and therefore the agreements applied only to that portion. That is, Clause 5, supra, does not dispose of the relocation compensation issue as to the bulk of the relocated water pipe. We disagree with this conclusion.

The record shows no evidence of rescission, termination, cancellation or abandonment of the 1955--56 franchise agreements following the first relocation. The general rule is that a contract remains in force until and unless it has been terminated according to its terms or by actions of the parties. 17A C.J.S., Contracts § 385(1). Clearly the contracts here did not expire by their own terms, a thirty-year period being specified therein. The actions of the parties indicate that both regarded the contracts as still controlling, most notably in that plaintiff continued to pay, and the defendant to accept, the precise per mile/per year franchise fee specified in the...

To continue reading

Request your trial
20 cases
  • Haft v. Dart Group Corp.
    • United States
    • U.S. District Court — District of Delaware
    • 30 Diciembre 1993
    ...force until and unless it has been terminated according to its terms or by actions of the parties." Artesian Water Co. v. State Dep't of Highways & Transp., 330 A.2d 441, 443 (Del.1974) (citing 17A C.J.S. Contracts § 385(1) (1963)). Abandonment, however, may constitute one of those actions.......
  • Oglesby v. Penn Mut. Life Ins. Co., Civ. A. No. 93-224 MMS.
    • United States
    • U.S. District Court — District of Delaware
    • 16 Febrero 1995
    ...such as the actions of the parties, to ascertain the meaning of ambiguous contractual language. Artesian Water Co. v. State Dep't of Highways and Transp., 330 A.2d 441, 443 (Del.1974) (citations omitted); see generally 3 Corbin on Contracts §§ 543, 558 An agreed interpretation of the clause......
  • Verizon Delaware, Inc. v. At & T Communications
    • United States
    • U.S. District Court — District of Delaware
    • 16 Julio 2004
    ...ISP-bound traffic but rather had intended to deal with it simply as local traffic. (See id.) Citing Artesian Water Co. v. State Dept. of Highways & Transp., 330 A.2d 441 (Del.1974), the examiner the parties' course of dealing to be particularly persuasive because, "the conduct of the partie......
  • Homac, Inc. v. DSA Financial Corp., Civ. A. No. 87-CV-70142-DT.
    • United States
    • U.S. District Court — Western District of Michigan
    • 23 Marzo 1987
    ...parties to determine their contractual intent should not be undertaken by the Court. See e.g. Artesian Water Co. v. State Department of Highways and Transportation, 330 A.2d 441, 443 (Del.1974). In such unambiguous cases, the court must give the contract "the force and effect which the lang......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT