ATACS Corp. v. Trans World Communications, Inc.

Decision Date08 September 1998
Docket Number97-1813,Nos. 97-1812,s. 97-1812
Citation155 F.3d 659
PartiesATACS CORPORATION; AIRTACS Corporation, Appellants in 97-1812, v. TRANS WORLD COMMUNICATIONS, INC., Appellant in 97-1813.
CourtU.S. Court of Appeals — Third Circuit

Mark A. Dombroff (Argued), Courtney R. Bateman, Dombroff & Gilmore, Washington, DC, for Appellants/Cross Appellees.

Barbara W. Mather (Argued), Robert L. Hickcok, L. Suzanne Forbis, Matthew J. Hamilton, Pepper Hamilton LLP, Philadelphia, PA, for Appellee/Cross Appellant.

Before: SCIRICA, NYGAARD and SEITZ, Circuit Judges.

OPINION OF THE COURT

SEITZ, Circuit Judge.

This appeal and cross-appeal primarily present two novel issues for review. The first question is whether the parties entered into a legally enforceable "teaming agreement." If the answer is in the affirmative, we must address how to calculate, if at all possible, the damage resulting from a breach of that agreement. The district court exercised diversity jurisdiction pursuant to 28 U.S.C. § 1332, and our jurisdiction arises under 28 U.S.C. § 1291 to consider the district court's final orders. The parties agree that the substantive contract law of Pennsylvania governs the issues raised in this case.

I. Factual Background
A. The Parties and Related Entities

For the most part, the parties do not dispute the relevant facts as described by the district court in its detailed findings of fact set forth on May 28, 1997 after a bench trial. To summarize, ATACS Corporation and AIRTACS Corporation ("plaintiffs") engaged in the business of integrating or customizing mobile enclosures with communications or other equipment for military use. Trans World Communications ("defendant") is a subsidiary of Datron, Inc., a publicly traded company. Defendant engages in designing, manufacturing, and selling of high frequency radio equipment into communications shelters and for other uses.

B. The Greek Request for Proposal and the Parties' Agreements

The history underlying the transactions subject to dispute in this case begins in October of 1989, when the Greek government opened bidding to manufacture 61 communication shelters for the Hellenic Army General Staff. A Request for Proposal ("RFP") prepared by the Greek government outlined various specifications for the communications shelters as well as certain financial requirements for all bidders. Plaintiffs considered bidding on the contract as the prime contractor, but they lacked the requisite assets to meet the financial obligations enumerated in the Greek RFP. Defendant also investigated bidding on the project as prime contractor, but it did not command significant technical experience in this particular field and generally lacked foreign government contracting knowledge to bid and perform the contract on its own.

Given the comparative strengths of the parties, a strategic alliance was born on February 26, 1990, where defendant wrote plaintiffs stating that "[t]his letter will serve as confirmation that Trans World Communications intends to team with ATACS Corporation on the Greek Shelter program." App. at 1671. While defendant professed that the "details need[ed] to be worked out," and that "this [letter] is only a preliminary look at our various responsibilities," defendant sought a commitment from plaintiffs before any quotations were issued. Id. Further discussions proved fruitful, and the parties agreed that defendant would bid for the Greek RFP as the prime contractor and plaintiffs would be the major subcontractor. App. at 1913. By April 25, 1990, defendant communicated to plaintiffs a basic outline for the new arrangement whereby defendant agreed to assume the role of prime contractor, assume complete responsibility for the financial requirements of the Greek RFP, and give plaintiffs a subcontract for the shelter and generator systems. In return, plaintiffs were expected to "assist in the final proposal preparation," submit a price quotation on their portion of the program, and introduce defendant to their Greek agent who would facilitate the bid. App. at 1913. The parties agreed to circulate a draft contract and initiate the process of formalizing this agreement.

For the next three months, the parties circulated draft subcontracts, none of which were executed. In the exchange of drafts, however, the parties had substantially agreed to the basic understanding of the transaction. In particular, the parties agreed that:

1. Transworld will be the Prime Contractor and will assume complete responsibility for the Program including any Letters of Credit which may be required. ATACS will be a sub-contractor to Transworld and will be responsible for the shelters and generators. 1

2. Axon Inc. will be the sole agent for this program. ATACS will introduce Transworld to Axon May 1, 1990.... 2

3. ATACS has accomplished significant work developing a Technical Proposal. In addition, ATACS has also reviewed the agent's Consulting Agreement and the Offset Agreement. This information will be made available to Transworld. Transworld will reimburse ATACS for their cost associated with our Technical Proposal and for legal expenses associated with the review of Offsets and Consulting Agreements. 3

4. ATACS will submit a quotation to Transworld for the shelters and generators. It is agreed that Transworld will flow down to ATACS no less favorable payment terms and conditions than it receives from the Greek Government. ATACS will in turn flow down these same terms and conditions to its Prime vendors.

5. ATACS agrees to work exclusively with Transworld on this project. Transworld agrees to work exclusively with ATACS relative to the ATACS Scope of Work set forth in paragraph 1 above.

....

7. ATACS agrees to assist Transworld as needed in the final proposal preparation.

App. at 1914-15; see also App. at 1948-49, 1966-69, 2047-50, 2059-62. In accordance with their understanding, plaintiffs introduced defendant to their Greek agent who ultimately proved to be influential in getting defendant the final contract.

After more draft subcontracts and price quotations, none of which were executed by the parties, plaintiffs submitted their final price proposal to defendant, which totaled approximately $3.8 million. On July 16, defendant submitted its own proposal to the Greek government. As the prime contractor bidding for the Greek RFP, defendant represented that plaintiffs would be "the primary subcontractor in our proposal," as well as a member of the "team" working on the project. App. at 2144-45. It is not disputed on appeal that defendant included in its bid plaintiffs' final prices plus a 30% profit margin.

C. Post-Submission Conduct

Several months after the submission of the bid for the Greek RFP, defendant learned that its proposal for the project remained competitive. Nevertheless, in early December of 1990, defendant contacted Craig Systems ("Craig"), a manufacturer of bare shelters, shelter integrator, and competitor to plaintiffs. When Craig expressed an interest in performing the shelter integration work on the Greek project--the same work that had been promised to plaintiffs--defendant sent to Craig all of the information, design notes, general correspondence, and plaintiffs' technical proposal regarding the Greek RFP. Defendant then asked Craig to submit a bid for the shelter work, and Craig ultimately submitted its final proposal and price quotation in late January of 1991.

On January 24, 1991, plaintiffs' Greek agent forwarded defendant the results of the Greek government's review of the various bids, which indicated that the defendant's bid was the lowest among the competitors. Although defendant at this point was confident that it would win the contract, it realized that the final award would require further negotiations with the Greek government. 4 For the next several months, defendant negotiated with Greek authorities to determine the final technical specifications and price concessions. Then, on May 13, 1991, defendant sent all its potential subcontractors, including plaintiffs, a form letter which stated:

We have recently been called by the Greek government to negotiate the final terms and conditions for this shelter contract. Therefore, we ask that your firm please REQUOTE YOUR OFFER to us as soon as possible, and extend the quote validity date to at least August 31, 1991.

...

... All outside vendor equipment and service is being bid in a competitive environment and Trans World will chose the supplier, based on the price of goods, quality, service and technical/manufacturing capabilities.

App. at 2413 (emphasis in original). On the same date, defendant sent plaintiffs another letter which, "encourage[d] you to make your bid as competitive as possible. While we were encouraged in our earlier preliminary discussions by the cost estimates you provided us for planning purposes, your later formal proposal was disappointingly high and was not competitive with other proposals which we have received." App. at 2412. This letter was the first communication to plaintiffs by defendant indicating that defendant had in fact been soliciting other proposals for the shelter integration and air conditioning portions of the project. It was also the first time plaintiffs had learned that defendant considered plaintiffs' proposal "disappointingly high," even though defendant's bid for the Greek RFP was the lowest of all bidders.

Shocked at defendant's position, plaintiffs responded to these letters by confirming the validity of their price proposals submitted on June 28, 1990. Although plaintiffs indicated that they were "not and never have been unwilling to discuss with you an equitable adjustment to our proposed pricing if such an adjustment is required in obtaining the award," App. at 2432, they emphasized that "[t]here was an agreement between Trans World and ATACS that ATACS would be the sole source shelter integrator and supplier, and ... AIRTACS ...

To continue reading

Request your trial
232 cases
  • Charleswell v. Chase Manhattan Bank, N.A.
    • United States
    • U.S. District Court — Virgin Islands
    • 27 Febrero 2004
    ...promise and to the consideration for it." Morton v. Hewitt, 202 F.Supp.2d 394, 396 (D.Vi.2002) (quoting ATACS Corp. v. Trans World Communications, Inc., 155 F.3d 659, 665 (3d Cir.1998)) (internal quotations omitted). "It is well-settled law that the test for enforceability of an agreement i......
  • Cook Techs., Inc. v. Panzarella, CIVIL ACTION NO. 15-CV-1028
    • United States
    • U.S. District Court — Eastern District of Pennsylvania
    • 17 Diciembre 2018
    ...evidence from which damages may be calculated to a 'reasonable certainty.'" Ware, at 226 (quoting ATACS Corp. v. Trans World Communications, Inc., 155 F.3d 659, 668 (3d Cir. 1998). "At a minimum, reasonable certainty embraces a rough calculation that is not 'too speculative, vague or contin......
  • Charleswell v. Chase Manhattan Bank, N.A.
    • United States
    • U.S. District Court — Virgin Islands
    • 27 Febrero 2004
    ...promise and to the consideration for it.” Morton v. Hewitt, 202 F.Supp.2d 394, 396 (D.Vi.2002) (quoting ATACS Corp. v. Trans World Communications, Inc., 155 F.3d 659, 665 (3d Cir.1998)) (internal quotations omitted). “It is well-settled law that ‘the test for enforceability of an agreement ......
  • Montich v. Miele USA, Inc.
    • United States
    • U.S. District Court — District of New Jersey
    • 27 Marzo 2012
    ... ... Nov. 4, 2009); In re Whirlpool Corp. FrontLoading Washer Prods. Liab. Litig., 684 F.Supp.2d ... , 378 F.Supp.2d 1200, 1207 (E.D.Cal.2005); Westways World Travel v. AMR Corp., 182 F.Supp.2d 952, 964 ... be implied because of the Plaintiff's direct communications with Miele subsequent to her purchase of the washing ... ...
  • Request a trial to view additional results
1 firm's commentaries
  • How To Improve Your Teaming Agreement, Part I
    • United States
    • Mondaq United States
    • 12 Febrero 2015
    ...Regulations (2014). See Recommended Provisions for Teaming Agreements, ibid.; see also ATACS Corp. v. Trans World Commc'ns, Inc., 155 F.3d 659, 666 (3d Cir. See Recommended Provisions for Teaming Agreements, note 2. For example, in ATACS Corp., the team leader obtained lower-cost proposals ......
2 books & journal articles
  • The Aftermath of Catastrophes: Valuing Business Interruption Insurance Losses
    • United States
    • Georgia State University College of Law Georgia State Law Reviews No. 30-2, December 2013
    • Invalid date
    ...Cir. 1980).120. Harbor House Condo. Ass'n v. Mass. Bay Ins. Co., 915 F.2d 316, 318 (7th Cir. 1990); ATACS Corp. v. Trans World Commc'ns, 155 F.3d 659, 669 (3d Cir. 1998) ("[A]n injured party need only prove damages with reasonable certainty."). See also LEE R. RUSS & THOMAS F. SEGALLA, COUC......
  • UNCERTAIN TERMS.
    • United States
    • Notre Dame Law Review Vol. 97 No. 1, November 2021
    • 1 Noviembre 2021
    ...inclusive, do not establish a private right of action against an operator."). (234) See, e.g., ATACS Corp. v. Trans World Commc'ns, Inc., 155 F.3d 659, 666 (3d Cir. 1998) (quoting 1 SAMUEL WILLISTON, A TREATISE ON THE LAW OF CONTRACTS [section] 23 (Walter H.E. Jaeger ed., 3d ed. 1957)) (cit......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT