Badger v. Brooklyn Canal Co.

Decision Date07 July 1998
Docket NumberNo. 970269,970269
Citation966 P.2d 844
Parties347 Utah Adv. Rep. 3 Wesley BADGER and Utah Land Inc., Plaintiffs and Appellants, v. BROOKLYN CANAL COMPANY and Robert L. Morgan, State Engineer, Defendants and Appellees.
CourtUtah Supreme Court

Rehearing Denied Sept. 9, 1998.

Paul M. Durham, Mark J. Gibb, Salt Lake City, for plaintiffs.

Jan Graham, Att'y Gen., Michael M. Quealy, John H. Mabey, Jr., Asst. Att'ys Gen., Salt Lake City, and Ken Chamberlain, Richfield, for defendants.

DURHAM, Associate Chief Justice:

Wesley Badger and Utah Land Inc. ("private well plaintiffs") appeal from the district court's grant of summary judgment in favor of the Brooklyn Canal Company and the State Engineer. The district court found that plaintiffs did not make known the nature of their private well rights in a protest hearing before the State Engineer and therefore waived the right to claim any impairment to private well rights. We affirm.

Brooklyn Canal Company is a nonprofit mutual water corporation formed for the purpose of delivering water to its Sevier County shareholders. Brooklyn draws a majority of its water directly from the Sevier River, with a small portion coming from artesian wells. In 1992, 72% of Brooklyn's shareholders approved a change in their irrigation system from a flood method to a high-pressure sprinkler method. Switching to a pressurized sprinkler system required Brooklyn to move its diversion point several miles upstream on the Sevier River in order to connect to the new underground pipes that service the sprinkler system and to abandon its artesian wells. Pursuant to Utah Code Ann. § 73-3-3 (1989), Brooklyn applied to the State Engineer for approval of the change in diversion point. A group of Brooklyn shareholders protested the change application. The State Engineer held a hearing on May 11, 1993, in Richfield, Utah. After hearing testimony from Brooklyn and the protesters, the State Engineer issued a memorandum decision approving the change in diversion point.

Following the memorandum decision, some of the protesters filed a petition for de novo review in the district court pursuant to Utah Code Ann. §§ 73-3-14 and 63-46b-15 (1989). Thereafter, Brooklyn moved for summary judgment claiming that plaintiffs had no standing to bring the suit and that the rights of the private well plaintiffs would not be adversely affected by a change in the diversion point. The district court granted Brooklyn's motion for summary judgment on the grounds that (1) the shareholder plaintiffs did not have standing to challenge Brooklyn's change application; (2) switching irrigation methods does not require a change application; and (3) there were no disputed material facts as to whether the diversion would impair the private well plaintiffs' rights. Plaintiffs appealed the district court's grant of summary judgment.

On appeal, we affirmed the district court's decision with respect to its holding that the Brooklyn shareholders did not have standing to challenge Brooklyn's change application, but remanded for a determination of whether the private well plaintiffs had properly raised their claims either in the protest or in the hearing before the State Engineer. Badger v. Brooklyn Canal Co., 922 P.2d 745, 753 (Utah 1996) (Badger I ). Due to an inadequate record, we were unable to determine in that appeal whether the private well plaintiffs raised their claims before the State Engineer. See id. at 751-52. The State Engineer had submitted official tape recordings of the hearing and a transcript of the tapes, but the tapes and transcripts contained gaps and otherwise appeared incomplete. See id.

We further found in Badger I that the district court had erroneously assumed that the private well plaintiffs' claims were properly before it and had improperly addressed the merits of whether the change application would adversely impact the private wells. See id. at 752. The district court had concluded that the diversion would not adversely impact the private wells, but we reversed and remanded because the district court based its conclusion on insufficient facts. See id. at 752-53.

On remand, the State Engineer moved for summary judgment, claiming that there were no disputed material facts as to whether the private well plaintiffs had raised the private well rights at the earlier hearing and that they had therefore waived any claimed impairment to their private wells. The State Engineer attached to his motion for summary judgment a corrected and complete transcript of the May 11, 1993, hearing. The State Engineer argued that the corrected transcript clearly shows that none of the protesters raised the issue of private wells at any time during the hearing and that the protests themselves do not reveal any claimed injury to private well rights.

The private well plaintiffs responded by asserting that the written protests and the hearing transcript adequately raised their private well claims. Plaintiffs further argued that even if the written protests and the hearing transcript did not reflect that they raised their private well claims, a dispute of material fact existed as to whether the issue was identified during the inaudible moments or gaps in the tape. In support of their claim, the private well plaintiffs submitted affidavits in which their prior counsel and one of the private well plaintiffs, Wesley Badger, asserted that they raised the private well issue at the hearing. Alternatively, the private well plaintiffs contended that even if they failed to raise their private well claims at the hearing or in the written protests, the State Engineer had constructive notice of the private well claims through its official water rights registry. Brooklyn countered that there was no dispute regarding the completeness of the transcripts and that the short gaps in the tape, which occurred during the time the tape was being turned over, were not adequate for plaintiffs to have raised their private well claims.

The district court granted Brooklyn's motion for summary judgment, finding that the private well plaintiffs did not make known the nature of their private well rights nor the nature of their claims either during the hearing or through their written protests. The private well plaintiffs then brought this appeal.

Summary judgment is appropriate only when there are no disputed issues of material fact and the moving party is entitled to judgment as a matter of law. Higgins v. Salt Lake County, 855 P.2d 231, 235 (Utah 1993). In reviewing the district court's grant of summary judgment, we view the facts and inferences therefrom in the light most favorable to the nonmoving party. United Park City Mines Co. v. Greater Park City Co., 870 P.2d 880, 885 (Utah 1993). We review the district court's conclusions of law for correctness. Id.

Viewing the facts in the light most favorable to the private well plaintiffs, we conclude that they failed to adequately raise the issue of impairment to their private wells before the State Engineer. In a trial setting, to preserve an issue for appellate review, a party must first raise the issue in the trial court. DeBry v. Cascade Enters., 935 P.2d 499, 501 (Utah 1997). That is, a trial court must be offered an opportunity to rule on an issue. Katz v. Pierce, 732 P.2d 92, 95 (Utah 1986) (citing Meyer ex rel. Meyer v. Bartholomew, 690 P.2d 558 (Utah 1984)). A trial court has the opportunity to rule if the following three requirements are met: (1) "the issue must be raised in a timely fashion;" (2) "the issue must be specifically raised;" and (3) a party must introduce "supporting evidence or relevant legal authority." Hart v. Salt Lake County Comm'n, 945 P.2d 125, 130 (Utah Ct.App.1997) (citations and internal quotations omitted). The purpose of such requirements is to "put[ ] the judge on notice of the asserted error and allow [ ] the opportunity for correction at that time in the course of the proceeding." Broberg v. Hess, 782 P.2d 198, 201 (Utah Ct.App.1989). Issues not raised at trial are usually deemed waived. See State v. Labrum, 925 P.2d 937, 939 (Utah 1996).

Similarly, a party seeking review of agency action must raise an issue before that agency to preserve the issue for further review. See Pease v. Industrial Comm'n, 694 P.2d 613, 616 (Utah 1984). It is well settled that "persons aggrieved by decisions of administrative agencies 'may not, by refusing or neglecting to submit issues of fact to such agencies, by-pass them, and call upon the courts to determine ... matters properly determinable originally by such agencies.' " S & G, Inc. v. Morgan, 797 P.2d 1085, 1087 (Utah 1990) (quoting People v. Keith Ry. Equip. Co., 70 Cal.App.2d 339, 161 P.2d 244, 249 (1945)). However, as we noted in Badger I, "it may be inappropriate to impose the same level of strict waiver analysis that we have applied to issues or objections not raised before a trial court." Badger I, 922 P.2d at 751. Thus, this court does not apply a stringent waiver analysis to informal hearings before the State Engineer but instead will adopt a "level of consciousness" test, requiring a plaintiff to bring an issue to the fact finder's...

To continue reading

Request your trial
27 cases
  • Manzanares v. Byington (In re Baby B.)
    • United States
    • Supreme Court of Utah
    • January 27, 2012
  • Manzanares v. Byington (In re Adoption Baby B.)
    • United States
    • Supreme Court of Utah
    • June 15, 2012
    ...issue because it was not asserted in the proceedings below and accordingly was not preserved for appeal. See Badger v. Brooklyn Canal Co., 966 P.2d 844, 847 (Utah 1998) (party must give trial court an opportunity to rule on an issue to preserve it for appellate review). 5. The second except......
  • Searle v. Searle, No. 20000274-CA
    • United States
    • Court of Appeals of Utah
    • December 6, 2001
    ...that court an opportunity to rule on the issue." State v. Maguire, 1999 UT App 45, ¶ 6, 975 P.2d 476 (quoting Badger v. Brooklyn Canal Co., 966 P.2d 844, 847 (Utah 1998)). The District Court then "`has the opportunity to rule if the following three requirements are met: (1) "the issue must ......
  • Markham v. Bradley
    • United States
    • Court of Appeals of Utah
    • November 23, 2007
    ...presented to the trial court in such a way that the trial court has an opportunity to rule on that issue." (citing Badger v. Brooklyn Canal Co., 966 P.2d 844, 847 (Utah 1998))). Although Sellers argued to the trial court that the REPC was "unenforceable, and . . . therefore [Buyers] are not......
  • Request a trial to view additional results