Beuttas v. United States

Decision Date05 June 1944
Docket NumberNo. 44978.,44978.
Citation60 F. Supp. 771,101 Ct. Cl. 748
PartiesBEUTTAS et al. v. UNITED STATES.
CourtU.S. Claims Court

COPYRIGHT MATERIAL OMITTED

COPYRIGHT MATERIAL OMITTED

COPYRIGHT MATERIAL OMITTED

COPYRIGHT MATERIAL OMITTED

COPYRIGHT MATERIAL OMITTED

COPYRIGHT MATERIAL OMITTED

P. J. J. Nicolaides, of Washington, D. C. (William F. Kelly, of Washington, D. C., on the brief), for plaintiff.

Donald B. MacGuineas, of Washington, D. C., and Francis M. Shea, Asst. Atty. Gen., for defendant.

Before WHALEY, Chief Justice and LITTLETON, WHITAKER, JONES, and MADDEN, Judges.

WHITAKER, Judge.

Plaintiffs sue to recover extra costs incurred due to a suspension of the work for 69 days during which a change in the plans and specifications was being considered. It is stipulated that they are entitled to recover $8,727.44 on this account.

They also sue to recover for increased wages which they were required to pay common laborers, carpenters, cement finishers, and hoisting engineers.

Plaintiffs had a contract for the construction of the foundations of the Jane Addams Houses in Chicago. It was a relief project; it was intended to relieve unemployment, to provide a living wage for laborers and so to increase their purchasing power. What a living wage was, was fixed by the contract. The contractor was required to pay a minimum wage for common laborers of 82½ cents an hour, and for carpenters, cement finishers, and hoisting engineers of $1.31¼ cents an hour. It was recognized, however, that the cost of living might increase during the progress of the work or for some other reason that the Government might find it desirable that even higher wages should be paid, and so it was provided in article 19 of the specifications that if the Federal Emergency Administrator of Public Works "establishes different wage rates, the contract price shall be adjusted accordingly. * * *"

The contract was entered into on November 26, 1935, but defendant held up the work until February 17, 1936, when it gave plaintiffs notice to start work; however, work was not begun until February 28, 1936, due to bad weather. While the work was under suspension the defendant on February 15, 1936, asked for bids on the construction of the building above the foundation. (Plaintiffs' contract was for the foundation only.) This advertisement for bids required bidders to pay a minimum wage to the before-mentioned laborers higher than was provided for in plaintiffs' contract. A successful bidder on this part of the building could not pay common laborers less than 95 cents an hour, instead of the 82½ cents on the foundation contract, and could not pay carpenters, cement finishers, and hoisting engineers less than $1.50 per hour, instead of the minimum of $1.31¼ on the foundation contract.

Whereas on November 26, 1935, the Government thought not less than $1.31¼ was a fair wage for carpenters, cement finishers, and hoisting engineers, and 82½ cents for common laborers, by February 15, 1936, conditions had changed to such an extent that it no longer considered these fair wages and demanded of the superstructure contractor the payment of higher wages.

Plaintiffs' work did not commence until after this change in the wage rate. So, when they offered to pay their carpenters, cement finishers, and hoisting engineers $1.31¼ and common laborers 82½ cents, these men very naturally said, no, the Government has said that no less than $1.50 and 95 cents is fair; and when plaintiffs would pay no more, they struck. In order to induce them to work plaintiffs had to pay the $1.50 and 95 cents.

All the proof goes to show the laborers would not have struck except for the Government's action in establishing a higher minimum wage on the very same building on which plaintiffs' laborers were employed.

That they should have struck was well-nigh inevitable. They had no contract with plaintiffs to work at any fixed wage and, so, when their Government said that the least that ought to be paid for such labor was more than plaintiffs offered, of course they demanded the amount fixed by the Government as fair and refused to work for less.

So, while the defendant did not expressly demand of these plaintiffs that they pay a higher minimum wage on their contract, it nevertheless brought about conditions that made this almost inevitable, and it must have known that this would be the necessary consequence of its act. Just as effectively as though it had directly ordered plaintiffs to pay a higher wage, it indirectly required them to do so.

In LeVeque et al. v. United States, 96 Ct.Cls. 250, we held that the establishment by the Government of higher wages on another project in another part of the city did not require it to pay plaintiffs the increased wages they had to pay on their project. In that case we concluded the increase in wages paid by plaintiffs was not a necessary result of defendant's act. Here we think it was. The increased wages in this case were on the very same building on which plaintiffs were working. The Administrator did not directly establish different minimum rates to be paid by plaintiffs, but this was the necessary consequence of what he did. He did indirectly that which if done directly would have rendered the Government liable. We are of opinion that the defendant in fact established different wage rates on plaintiffs' job, and, therefore, it is obligated to pay the increase under article 19.

But whether or not this is so, it is an implied condition of every contract that neither party will hinder the other in his discharge of the obligations imposed upon him, nor increase his cost of performance. Restatement of the Law of Contracts, sec. 315(1); Williston on Contracts, sec. 1293A; Anvil Mining Co. v. Humble, 153 U.S. 540, 551, 14 S.Ct. 876, 38 L.Ed. 814. It was an implied condition of this contract that the Government would not do any act that as a necessary consequence would make performance by the plaintiffs more expensive. The Government breached that implied condition by increasing the minimum wage to be paid on a part of this building, which as a necessary consequence required plaintiffs to pay more wages than those specified.

It follows that the defendant is liable for the increased wages plaintiffs had to pay.

It is said, however, that the contracting officer and head of the department have decided that the Government has fully performed its obligations under the contract, and that this decision is final under article 15 of the contract and that, therefore, this court has no jurisdiction to determine the matter.

The defendant's position, otherwise stated, is that the parties agreed in advance of the dispute to waive their right to sue for this breach of the contract and to leave the final determination of the controversy to the decision of one of the contracting parties.

We do not think the parties intended article 15 to have such broad scope. If they did, it is clearly illegal under numerous decisions of the Supreme Court of the United States and of other Federal courts and of the State courts. It has long been settled that any agreement made in advance of the controversy which deprives a party of recourse to the courts is contrary to public policy and, therefore, void. Home Ins. Co. v. Morse, 20 Wall. 445, 450, 22 L.Ed. 365, et seq.; Doyle v. Continental Ins. Co., 94 U.S. 535, 537, 24 L.Ed. 148; Guaranty Trust & Safe Deposit Co. v. Green Cove R. R., 139 U.S. 137, 142, 11 S.Ct. 512, 35 L.Ed. 116; Martin v. Baltimore & O. R. R., 151 U.S. 673, 684, 14 S.Ct. 533, 38 L.Ed. 311; Terral v. Burke Construction Co., 257 U.S. 529, 42 S.Ct. 188, 66 L.Ed. 352, 21 A. L.R. 186. See also cases cited in 13 Corpus Juris, p. 455, notes 3, 5 and 8; 17 C. J.S., Contracts, § 229, p. 603, notes 58-66.

In Insurance Co. v. Morse, supra, there was involved a statute of Wisconsin which imposed on foreign insurance companies, as a condition to doing business in the State, an agreement to submit to the exclusive jurisdiction of the Wisconsin courts and to forego removal of a case to the Federal courts. It was held that the statute was unconstitutional and void, because "a man may not barter away his life or his freedom, or his substantial rights."

The statement of this principle was somewhat amplified in Doyle v. Continental Ins. Co., supra, in commenting on the Morse decision. It was there said, 94 U.S. on page 538, 24 L.Ed. 148:

"It was held, first, upon the general principles of law, that although an individual may lawfully omit to exercise his right to transfer a particular case from the State courts to the Federal courts, and may do this as often as he thinks fit in each recurring case, he cannot bind himself in advance by an agreement which may be specifically enforced thus to forfeit his rights. This was upon the principle that every man is entitled to resort to all the courts of the country, to invoke the protection which all the laws and all the courts may afford him, and that he cannot barter away his life, his freedom, or his constitutional rights."

The majority of the court, however, held that, while a State could not impose this condition on an insurance company's entering into business, it nevertheless had the right to revoke its license, even though a breach of the condition may have been the reason for the revocation. Justices Bradley, Swayne, and Miller dissented on the ground that the same reason that prevented the imposition of such a condition prevented the revocation of the license for its breach. Both the majority and minority agreed, however, that a condition in a contract prohibiting resort to a tribunal otherwise having jurisdiction of the subject matter and the parties was illegal.

Fifty years later, this view was approved by the Supreme Court in the case of Terral v. Burke Construction Co., 257 U.S. 529, 42 S.Ct. 188, 66 L.Ed. 352, 21 A.L.R. 186, and we understand it to be the law today. Section 558 of Restatement of the Law of Contracts reads:

"A...

To continue reading

Request your trial
17 cases
  • Utah Construction and Mining Company v. United States
    • United States
    • U.S. Claims Court
    • March 12, 1965
    ...States, 77 F.Supp. 209, 111 Ct.Cl. 252 (1948); Langevin v. United States, 100 Ct.Cl. 15 (1943); Beuttas Trading as B-W Construction Co. v. United States, 60 F.Supp. 771, 101 Ct.Cl. 748 (1944); reversed in part on other grounds, United States v. Beuttas et al., 324 U.S. 768, 65 S.Ct. 1000, 8......
  • Dorsey v. Oregon Motor Stages
    • United States
    • Oregon Supreme Court
    • January 23, 1948
    ...36 F. Supp. 686, Affd. C.C.A. 124 F.2d 147; Mechanical Ice Tray Corp. v. General Motor's Corp. C.C.A.N.Y. 144 F.2d 720; Beuttas v. U.S. Ct. Cl. 60 F. Supp. 771; Universal Sales Corporation v. California Press Mfg. Co. 29 Cal.2d 751, 128 P.2d 383; Brawley v. Crosby Research Foundation, 73 Ca......
  • Fort Sill Gardens, Inc. v. United States
    • United States
    • U.S. Claims Court
    • January 21, 1966
    ...62 F.Supp. 546, 103 Ct.Cl. 613 (1945), cert. denied, 327 U.S. 784, 66 S.Ct. 700, 90 L.Ed. 1011 (1946), and Beuttas v. United States, 60 F.Supp. 771, 101 Ct.Cl. 748 (1944). Discussion of these cases in unnecessary. It is sufficient to mention that the relevant part of the judgment which this......
  • Bateson-Stolte, Inc. v. United States
    • United States
    • U.S. Claims Court
    • April 8, 1959
    ...Anvil Mining Co. v. Humble, 153 U.S. 540, 14 S.Ct. 876, 38 L.Ed. 814; LeVeque v. United States, 96 Ct.Cl. 250; Beuttas v. United States, 60 F.Supp. 771, 101 Ct.Cl. 748 (rev. on other grounds 324 U.S. 768, 65 S.Ct. 1000, 89 L.Ed. 1354; Sunswick Corp. of Del. v. United States, 75 F.Supp. 221,......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT