Bowen v. Foust, 20320

Decision Date02 May 1996
Docket NumberNo. 20320,20320
Citation925 S.W.2d 211
CourtMissouri Court of Appeals
Parties29 UCC Rep.Serv.2d 825 Joe A. BOWEN and Mary Bowen, Respondents, v. Bob FOUST d/b/a Foust Plumbing, Heating & Cooling, Appellant.

Daniel T. Moore, Poplar Bluff, for appellant.

Karen J. Miller, Spain, Merrell & Miller, Poplar Bluff, for respondents.

CROW, Judge.

Plaintiffs, Joe A. Bowen and Mary Bowen, sued Defendant, Bob Foust (doing business as Foust Plumbing, Heating & Cooling), for breach of contract. 1 The contract was made when Plaintiffs accepted Defendant's bid to sell and install certain heating and cooling equipment at Plaintiffs' home.

Defendant's bid specified four "RHEEM 3 1/2 TON HEAT PUMP SYSTEMS" with a "SEER RATING OF 12." The bid price was $8,159, to be paid "WHEN INSTALLATION IS COMPLETE."

Plaintiffs pled that after paying Defendant the agreed sum, they discovered the equipment Defendant installed was not the equipment specified in the bid and was "incompatible with the existing system and [did] not operate properly."

The trial court heard the case without a jury and awarded Plaintiffs a judgment for $8,159, the specified price.

Defendant appeals, insisting the trial court erroneously ruled for Plaintiffs in that: (1) Plaintiffs failed to meet their burden of proof as to damages in that they "offered no evidence of the cost of repairing the defective work, or the diminution in the value of the home," and (2) Defendant was denied a reasonable opportunity to correct the defects under § 400.2-508, RSMo 1986, a provision of Missouri's "Uniform Commercial Code--Sales."

Our review is governed by Rule 73.01(c), Missouri Rules of Civil Procedure (1996), as construed by Murphy v. Carron, 536 S.W.2d 30 (Mo. banc 1976). The judgment of the trial court will be sustained unless there is no substantial evidence to support it, unless it is against the weight of the evidence, unless it erroneously declares the law, or unless it erroneously applies the law. Id. at 32. We view the evidence and permissible inferences therefrom in the light most favorable to the judgment, disregarding all contrary evidence and inferences, Mehra v. Mehra, 819 S.W.2d 351, 353 (Mo. banc 1991), mindful that credibility of the witnesses and the weight to be given their testimony were matters for the trial court, which was free to believe none, part or all of the testimony of any witness. Herbert v. Harl, 757 S.W.2d 585, 587 (Mo. banc 1988).

So viewed, the evidence demonstrates that in early 1993, Plaintiffs' home had a Carrier heating and cooling system consisting of four outside units and four inside units. Plaintiffs decided to upgrade the system with equipment having a "12 seer rating" to "get more efficiency [so] the house [would] cool and heat better." Plaintiffs solicited and received bids on the project.

After Defendant's bid (dated March 24, 1993) was accepted by Plaintiffs, Defendant replaced the four outside units with Rheem units and replaced the coils in the four inside units. Plaintiffs' daughter, Karen Bowen, a realtor, acted as agent and overseer for Plaintiffs on the project. Karen's testimony included this:

"Q. Was there any discussion at that time as to whether or not the Rheem units were compatible with the Carrier unit that was inside?

A. Yes, ma'am.

Q. What did [Defendant] say?

A. He said they were compatible."

The record does not reveal when Defendant completed the project. However, Plaintiff Mary Bowen testified that around mid-July, 1993, "the compressor went out." Defendant removed it and ordered a replacement. Mary's testimony continued:

"Q. How long did it take you to get another compressor?

A. It took four to six weeks, which was--was the hottest part of the time.

Q. So most of the summer you were without air there?

A. Yes. Uh-huh.

Q. Were there ... any other problems?

A. Yes. The units leaked water all the time, and they frosted up like a Frigidaire would frost up in the house.

....

Q. ... Were there problems with odors in the house?

A. Yes. Uh-huh.

Q. Dust?

A. Yes.

Q. During this period of time, did ... someone contact Mr. Foust? Did--Did someone come out there?

A. Yes, we called him all the time.

Q. And--

A. Probably about four or five months there and he kept telling us that he didn't understand ... why the pipes were freezing--

Q. He didn't know what to do to correct it?

A. Right."

Sometime that fall (1993) another compressor failed. According to Karen Bowen, the compressor was required for both cooling and heating.

In October, when Plaintiffs began needing heat, they discovered the system generated none. At that point, Defendant had not replaced the second compressor that failed.

In an effort to make the system produce heat, Defendant replaced the four inside units and presented Plaintiffs a bill for $1,400. However, according to Karen Bowen: "[W]e still didn't have any heat." Defendant then said "it was [Plaintiffs'] breakers." Karen testified Plaintiffs engaged an electrician to replace the breakers, which cost "200 and some odd dollars." Plaintiffs also installed new thermostats. Those measures also proved futile.

Around November 11, 1993, Defendant told Plaintiffs he had the compressor to replace the second one that had failed. However, he warned Plaintiffs it would not be under Rheem's warranty "if Rheem saw those [units]." Plaintiffs forbade Defendant from installing the compressor.

A few days later, at Karen Bowen's request, one Mike Johnson, a "heat and air man," examined the system installed by Defendant. Johnson's inspection revealed the system "did not have the 12 seer rating." Karen testified that upon learning this: "I called [Defendant] on the telephone and told him we wanted our money back and for him to come and get his units."

Asked how cold it was in the house that winter (1993-94), Karen recounted:

"It was cold enough that we put electric heaters in that house, and we heated the bathrooms with those water heaters. We heated--I brought every electric heater I had from my office and--and that I use in rental property and stuff like that for spares. And my dad wore his coat all the time. We stayed covered up with a blanket all the time. And we hauled wood to place in the fireplaces; it was that cold in that house."

In the spring of 1994, at Karen's request, Stanley Ray Buffington, a heating and cooling ventilation contractor and Carrier dealer, inspected the equipment installed by Defendant. Buffington found four Rheem three-ton units with a seer rating of 10.

Asked whether Carrier systems are compatible with Rheem systems, Buffington answered, "Absolutely not." He then explained why--an explanation we need not attempt to summarize. He also described several instances of substandard workmanship he observed in the installation of the Rheem equipment.

Buffington removed the Rheem units and replaced them with equipment that included heat pumps with larger tonnage and a 12 seer rating. He charged Plaintiffs "probably 15 to 18,000" dollars, which they paid.

Defendant insisted at trial, and maintains here: "It is clear this case involves the sale of 'goods' and is, therefore, governed by Missouri's version of the Uniform Commercial Code." Plaintiffs agree. We shall assume, without deciding, that the parties are correct. 2

Starting with that premise, we address Defendant's first point. As noted earlier, Defendant avers Plaintiffs failed to meet their burden of proof on damages when they presented no evidence of either the cost of repairing the defective work or the diminution in value of their home.

Defendant cites two cases in support of his first point. Neither case applies (or even mentions) any provision of the Uniform Commercial Code ("UCC"), hence neither case is helpful.

As we have seen, upon discovering that the equipment installed by Defendant did not have a 12 seer rating, Plaintiffs (through their agent, Karen) told Defendant to come and get the equipment and refund the purchase price. Plaintiffs maintain they had the right to do so under § 400.2-601, a section of Missouri's UCC. 3 That section provides, in pertinent part:

"... if the goods ... fail in any respect to conform to the contract, the buyer may

(a) reject the whole...."

Plaintiffs emphasize that the Rheem units sold to them by Defendant were "goods" 4 that failed to conform to the contract in that such units were three-ton units with a seer rating of 10, whereas the contract specified three-and-a-half-ton units with a seer rating of 12.

Plaintiffs recognize Defendant may argue that Plaintiffs accepted the goods even though they were nonconforming, hence § 400.2-601, above, does not apply. In that event, say Plaintiffs, § 400.2-608 granted them the right to revoke their acceptance. That section provides, in pertinent part:

"(1) The buyer may revoke his acceptance of a ... commercial unit whose nonconformity substantially impairs its value to him if he has accepted it

(a) ...

(b) without discovery of such nonconformity if his acceptance was reasonably induced either by the difficulty of discovery before acceptance or by the seller's assurances.

(2) Revocation of acceptance must occur within a reasonable time after the buyer discovers or should have discovered the ground for it and before any substantial change in condition of the goods which is not caused by their own defects. It is not effective until the buyer notifies the seller of it.

(3) A buyer who so revokes has the same rights and duties with regard to the goods involved as if he had rejected them."

Plaintiffs assert they did not discover the nonconformity of the Rheem units until months after the units were installed. Furthermore, insist Plaintiffs, they did not know the Rheem units were incompatible with the existing Carrier system until Defendant, after months of futility, admitted "a man at Rheem had misinformed him and that those units were not compatible."

Plaintiffs point out that upon...

To continue reading

Request your trial
6 cases
  • Cooper v. Bluff City Mobile Home Sales
    • United States
    • Missouri Court of Appeals
    • 26 Abril 2002
    ...another provision of the U.C.C. (§ 400.2-508) gives sellers the right to cure a rejection by repair or replacement.7 Bowen v. Foust, 925 S.W.2d 211, 215-16 (Mo.App.1996). Case law explains that the curative tender provision, i.e., § 400.2-508, is designed to counterbalance the perfect tende......
  • Accettura v. Vacationland, Inc.
    • United States
    • Illinois Supreme Court
    • 19 Septiembre 2019
    ...that a seller has no right to cure after a buyer revokes his acceptance under § 2-608(1)(b) of the UCC."); Bowen v. Foust , 925 S.W.2d 211, 215 n.6 (Mo. Ct. App. 1996) ("[T]he rule that a seller has no right to cure when a buyer justifiably revokes his acceptance remains the majority view."......
  • Cooper v. Bluff City Mobile Home Sales, SD24240
    • United States
    • Missouri Court of Appeals
    • 26 Abril 2002
    ...provision of the U.C.C. (section 400.2-508) gives sellers the right to cure a rejection by repair or replacement.7 Bowen v. Foust, 925 S.W.2d 211, 215-16 (Mo.App. 1996). Case law explains that the curative tender provision, i.e., section 400.2-508, is designed to counterbalance the perfect ......
  • Far East Services v. Tracker Marine
    • United States
    • Missouri Court of Appeals
    • 3 Diciembre 2007
    ...(2) Acceptance of a part of any commercial unit is acceptance of that entire unit. 9. Tracker also generally cites us to Bowen v. Foust, 925 S.W.2d 211 (Mo.App. 1996) (revocation of acceptance one year after delivery was reasonable) and Reed & Prince Manufacturing Co. v. Lear, Inc., 78 F.Su......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT