O'brien v. Mayer
Decision Date | 21 December 1886 |
Citation | 23 Mo.App. 648 |
Parties | JOHN O'BRIEN ET AL., Respondents, v. A. B. MAYER, Appellant. |
Court | Missouri Court of Appeals |
APPEAL from the St. Louis Circuit Court, SHEPARD BARCLAY, Judge.
Reversed and remanded.
MUENCH & CLINE, for the appellant: The contract is an entirety, and is not to be treated as a succession of contracts, each item furnishing a separate and distinct cause of action. Railroad v. Levy, 17 Mo. App. 508, and cases cited; 2 Parsons on Contracts [5 Ed.] 517. The respondents must sue either on the contract, or plead and prove circumstances such as to raise a new contract and give them a remedy on a quantum meruit. 2 Parsons on Contracts [5 Ed.] 522. The appellant has a right to such a judicial determination of this matter as to prevent the respondents from suing him hereafter, when they perform the next item, or each succeeding item, of work called for by the contract. Mansur v. Botts, 80 Mo. 651, 651; Stone v. St. Louis Trib. Co., 52 Mo. 342, 347.
FISHER & ROWELL, for the respondents: The court below properly refused the declaration of law asked by the defendant. It did not follow without condition, that the plaintiffs could not recover if they had agreed to put up the machinery sued for in lieu of similar machinery they had agreed to put up at another point. They might, under the conditions shown at the trial, abandon the contract and sue for the value of the chimney, breeching, etc. Yates v. Ballentine, 56 Mo. 530; Haysler v. Owen, 61 Mo. 275; Eyerman v. Mt. Sinai Cem. Ass'n, 61 Mo. 491; Davis v. Brown, 67 Mo. 314; 2 Parson's Cont. [7 Ed.] 522-3; Mansur v. Botts, 80 Mo. 655.
The plaintiffs and the defendant entered into the following contract:
“ST. LOUIS, May 8, 1883.
A. B. Mayer, Esq.
JOHN O'BRIEN & CO.
Accepted May 15, 1883.
A. B. MAYER,
Per F. MAYER.”
The plaintiffs thereupon entered upon the performance of their contract, put up one complete set of boilers, smoke stack, and attachments at the Lowell factory, and received the old machinery at said factory, the punching and shearing machine, and the sum of three hundred dollars in cash.
After this was done the Lowell factory was destroyed by fire, and the plaintiffs at the defendant's request put up a chimney and breaching at said factory, the reasonable value of which, including two man-heads, is shown to have been worth $218.50. The plaintiffs demanded payment of this amount from the defendant, but the defendant refused to pay it, claiming that all the work was covered by the contract between them, except the item of $6.50 for man-heads, for which item the defendant made a tender to the plaintiffs in cash.
The plaintiffs thereupon instituted suit against the defendant, before a justice of the peace, on the following account; which was the only statement of their cause of action:
“ST. LOUIS, July 22, 1884.
M. A. B. Mayer & Son, to John O'Brien & Co., Dr. 2 Manheads, 10x15, at $3.25 $ 6.50 1 Chimney, 42” dia. x50' high, 1925 lbs., at 6c
$115.50 1 Breeching, 894 lbs., at 7c 62.58 1 Combing, 152 lbs., at 6c 9.12
...Putting same up, 54 1/2 hours,
To continue reading
Request your trial