Brownell Imp. Co. v. Critchfield
Decision Date | 19 June 1902 |
Citation | 197 Ill. 61,64 N.E. 332 |
Parties | BROWNELL IMP. CO. v. CRITCHFIELD et al. |
Court | Illinois Supreme Court |
OPINION TEXT STARTS HERE
Appeal from appellate court, First district.
Action by George W. Critchfield against the Brownell Improvement Company. From a judgment affirming a judgment in favor of plaintiff (96 Ill. App. 84), defendant appeals. Affirmed.Gardner & Burns, for appellant.
J. B. Langworthy, F. W. Bentley, W. S. Oppenheim, and Leroy D. Thoman, for appellees.
The following statement of facts as made by the appellate court is sufficiently full and accurate, and is adopted as the statement of this court:
‘Appellees contracted with the city of Chicago on August 26, 1895, to curb, grade, and pave a portion of Wabash avenue, in said city. The written contract provided that the work should be done according to specifications, and that the the work should be approved by the commissioner of public works of the city. On September 17, 1895, appellees entered into a subcontract with appellant to do a part of this work. The contract was in writing, and provided, inter alia, that appellant was to It was also provided by this contract that eighty-five per cent. of the amount to become due to appellant for its work should be paid from time to time as the work progressed, with certain privileges to appellees to pay by promissory notes or by cash.
‘Appellant proceeded to do the work contracted for, and claimed to have completed it in the latter part of November, 1895. At about this time the city had ordered the work suspended until the following spring because of the weather and in accordance with a provision in its contract. In December, 1895, appellant desiring a settlement with appellees, the parties entered into an agreement of conditional settlement, which provided that whereas the said Brownell Improvement Company now desires a settlement for said work, it is agreed between said parties that a temporary settlement shall be made on the following basis: Said Brownell Improvement Company to be paid on a basis of having completed 12,969, square yards of concrete and 7,175.8 feet of curb, it being agreed that when final estimates are made by the city, if the same be less than the amounts herein stipulated, the said improvement company shall refund the difference, if any, and that, if said final measurements show more work than the amounts herein stipulated, the excess, if any, to be paid to said Brownell Improvement Company. It is expressly stipulated and agreed that, if defects of workmanship or material become apparent in said concrete or said combined curb and gutter before the final completion of asphalt wearing surface, or if any portion of said concrete or said combined curb and gutter requires repairs, or any other work would have to be performed on it to make it comply with the requirements of the city authorities before laying said asphalt wearing surface, the said Brownell Improvement Company will make said alterations or repairs, or perform such other or additional work as may be required by said city authorities, free of expense to said parties of the second part. Further recites that nothing in this agreement shall relieve the said Brownell Improvement Company from its guaranty under its bond to said party of the second part for the faithful performance of said contract. This agreement was signed by both parties thereto, and accepted on the bottom thereof by the Mexican Asphalt Paving Company, by its president and secretary. It was executed under seal.
‘After the making of the contract with the city and the subcontract with appellant, the business of appellees was incorporated as the Mexican Asphalt Paving Company, and the contracts of appellees were assigned to the corporation. Under this conditional or ‘temporary’ agreement of settlement the appellees paid appellant for its work, the final payment of $253.75 being made January 2, 1896. The work done was covered, to protect it from the weather, by appellant. In the spring following it was found that the work was not in good condition. There was some conflict as to this condition of the work, but the record discloses evidence which would well warrant the conclusion that the concrete work done by appellant was found in the spring to be soft in many places, and not such work as the contracts required. The commissioner of public works of the city refused to accept this work, and required that the concrete work done by appellant under its contract with appellees, and paid for under the conditional settlement, should be relaid. This, appellant, when requested by appellees, refused to do, and thereupon the representative of the appellees said, ‘Then we will do this work, and charge you with the cost of it, and sue you for the amount,’ to which Mr. Brownell, the representative of appellant, replied: But Mr. Brownell denied any liability of appellant to do the work. Appellees, through the Mexican Asphalt Paving Company, proceeded to relay the concrete work done by appellant to the extent of 8,463 square yards, at a cost of $2,845.11. The remainder of the work, consisting of 3,222 square yards, was ordered done by the city through another company, the Assyrian Asphalt Paving Company, and the cost thereof was deducted from the amount due to appellees from the city.
contract price to cover this entire work. Appellees brought this suit to recover from appellant, for the use of the Mexican Asphalt Paving Company, the amount which it had thus cost them to relay the 8,463, square yards, and the amount deducted by the city for the relaying of ...
To continue reading
Request your trial-
Ark-Mo. Zinc Co. v. Patterson
... ... plant, which is expressly warranted to perform certain work ... Brownell Imp. Co. v. Critchfield, 197 Ill ... 61, 64 N.E. 332; Cornish-Curtis-Green Co. v ... Dairy ... ...
-
Huber v. St. Joseph's Hospital
... ... 333; Moore v. Kerr, 65 Cal ... 519, 4 P. 542; United States v. Walsh, 108 F. 502; ... Brownell Imp. Co. v. Critchfield, 197 Ill. 61, 64 ... N.E. 332; Eldridge v. Fuhr, 59 Mo.App. 44.) "To ... ...
-
Standard Oil Co. v. Daniel Burkhartsmeier Cooperage Co.
...Lumber Co. v. Leonard Lumber Co., 332 Ill. 104, 108, 163 N.E. 416;Smith v. Gray, 316 Ill. 488, 499, 147 N.E. 459;Brownell Imp. Co. v. Critchfield, 197 Ill. 61, 71, 64 N.E. 332;Sterling-Midland Coal Co. v. Great Lakes C. & C. Co., 266 Ill.App. 46, 59. From its demand for indemnification to t......
-
Barber Asphalt Paving Company v. Tomlinson
... ... 88, 16 N.E. 92; Guild v ... Andrews, 137 F. 369; Mobile v. Shea, 127 F ... 521; Brownell Imp. Co. v. Critchfield, 197 Ill. 61, ... 64 N.E. 332; McGregor v. Const. Co., 188 Mo. 611; ... ...