Ark-Mo. Zinc Co. v. Patterson
Decision Date | 02 July 1906 |
Citation | 96 S.W. 170,79 Ark. 506 |
Parties | ARK-MO. ZINC COMPANY v. PATTERSON |
Court | Arkansas Supreme Court |
Appeal from Marion Chancery Court; T. H. Humphreys, Chancellor reversed.
STATEMENT BY THE COURT.
The plaintiff, G. M. Patterson, instituted this suit in the chancery court of Marion County against the defendant, Ark-Mo Zinc Company, a New Jersey corporation doing business in this State, to recover the contract price for the erection of a concentrating and ore-dressing plant at the "Climax" zinc mine in Marion County, owned and operated by the defendant, and to enforce a statutory mechanics' lien therefor. An unpaid balance of $ 892.33 is claimed on the original contract price, and the further sum of $ 781.36 for extras, making a total of $ 1,673.69 alleged to be due and unpaid.
The contract between the parties, whereby the plaintiff undertook to construct the plant, contained the following clauses viz.:
The specifications attached to the contract set forth in detail the kind of machinery to be furnished and the manner in which the plant should be constructed, and concluded with the following provisions, viz.:
The defendant filed its answer denying that the plaintiff had complied with the contract by constructing the plant in accordance with the terms of the contract and specifications, alleging that the plant had not come up to the test provided in the contract; that it was so defective as to be practically of no use, and was not satisfactory to said W. N. Allen or defendant, and had been rejected, and that defendant had paid to the plaintiff the sum of $ 3,207.20 on said contract price. The answer was made a cross-complaint against the plaintiff and the sureties on his bond, with prayer for recovery of said sum advanced and also damages on account of the plaintiffs' alleged failure to comply with the contract. Alleged defects in the plant are set forth in detail in the answer as follows:
'The boiler is improperly and defectively set, the inside walls in the fire box having fallen in, and being in a dangerous condition; that all steam connections are faulty and so arranged that, when it became necessary to close down any one department of the mill, all must be closed; the engine is defective in its connections, and did not work at all satisfactorily, and had a decided pound in the cylinder, and would wear it out in a very short time. The follower catches and hammers at each revolution. The rolls are not set on a solid foundation, and are insecure and dangerous. The crusher is not set on a solid foundation or anchored, and is not true upon its base, and is insecure and dangerous. The screen is hung insecurely, and is dangerous. The main line shaft is not property set, and is unable to stand the strain that operation would cause. The elevator is improperly constructed, and permits a constant waste of ore. The ore bin is improperly constructed, and would not sustain the weight it was intended to sustain, and is broken. The hoister house is improperly and insecurely constructed; the vibrations, when the hoister is in operation, being so great that it renders it difficult for the hoisterman to perform his duties. The steam connections on the hoister are so leaky that it is impossible to operate it on account of escaping steam, without wrapping the joints with cloth; and the building is improperly and defectively constructed. That it will not crush and properly clean in ten hours or less at least 50 tons of ore from appellant's mine, or ore of a similar character to that of said mine, and that there are many other defects in the construction of said plant. That, after a test of said plant by appellee and said plant being defective and not according to contract, the same was rejected, and was not satisfactory to said W. N. Allen or appellant, and, although promptly notified of such defects the appellee refused to remedy same, and said plant was closed and tendered to appellee, and appellant still tenders same to them."
The chancellor made the following findings of the facts, viz.:
...
To continue reading
Request your trial-
Gudmundson v. Thingvalla Lutheran Church
... ... 222 Mo. 613, 121 S.W. 805; Sanders v. Baggerly, 96 ... Ark. 117, 131 S.W. 49; Ark-Mo Zinc Co. v. Patterson, ... 79 Ark. 506, 96 S.W. 170; Jones, Ev. § 266 and cases ... ...
-
United States Fidelity & Guaranty Company v. Board of Commissioners Sewer Improvement District No. 1 of Blytheville
... ... it would then be determined whether the contract had been ... complied with. Ark. Mo. Zinc Co. v ... Patterson, 79 Ark. 506, 96 S.W. 170; ... Blackburn v. Texarkana G. & E. Co., 102 ... ...
-
Sanders v. Baggerly
... ... or gross mistake. Ark.-Mo. Zinc Co. v ... Patterson, 79 Ark. 506, 96 S.W. 170, and cases ... cited. So with church ... ...
- Hollingsworth v. Leachville Special School District