Bruce v. Berg

Decision Date30 December 1879
Citation8 Mo.App. 204
PartiesLAWRENCE BRUCE, Respondent, v. GEORGE BERG ET AL., Appellants.
CourtMissouri Court of Appeals

1. The lien law contemplates running accounts for materials furnished, and one may have a lien for materials furnished under an implied contract.

2. A building was contracted to be finished on September 1st, and stone was furnished on open account by the subcontractor from time to time from May to September 21st, and then, after an interval of four months, the building being apparently complete, stone steps which the architect had refused to accept were by the subcontractor replaced with others, which constitute the last item of the subcontractor's account. Held, that this item was sufficiently connected with the others, there being evidence tending to show that all the items were furnished under one contract, express or implied.

APPEAL from the St. Louis Circuit Court.

Affirmed.

JEFF. CHANDLER, for the appellants: Petition must allege that the materials were furnished under a contract.--Ph. on Liens, sect. 120; 55 Ind. 502; 45 Ind. 260; 4 Gray, 289; 29 Barb. 20; 36 Mo. 578; 40 Mo. 561. That the materials were actually put into the building is not sufficient.-- House v. Thompson, 36 Mo. 450.

C. M. WHITNEY, for the respondent, cited: Vollmer v. Papin, post, p. --; Fitzgerald v. Thomas, 61 Mo. 499; Garnett v. Berry, 3 Mo. App. 197.

HAYDEN, J., delivered the opinion of the court.

This is an action brought by a material-man against Berg and his partner, subcontractors; Eagleson, contractor; and Crawford, owner of the property against which a special judgment is asked. There was a judgment below enforcing a mechanic's lien, and Eagleson and Crawford have appealed.

It is first contended that the petition is insufficient, as not showing that the materials were furnished under any contract with the subcontractors. By this, evidently, is meant express contract, as it is again contended that the contract must precede the beginning of the work on the building. If by this is meant that no material-man or day-laborer can have a lien under our statute where a special contract has not been made with him before the commencement of the work, the position is obviously untenable. As a matter of course, there must be a contract, express or implied; and the original contract, to be the foundation of subcontracts, must have some degree of definiteness about it. Hause v. Carroll, 37 Mo. 578. But the contract need not be an express contract; nor do the terms of our statute admit of such construction as was put upon the Massachusetts act in Parker v. Anthony, 4 Gray, 289, or upon the New York law in Hatch v. Coleman, 29 Barb. 201. Wag. Stats. 907, sects. 1, 5, 11. Our statute clearly contemplates running accounts for materials furnished and work done under implied as well as express contracts. The question of agency, and of the power of a contractor or subcontractor to bind the owner's property by implied contracts of a given extent or kind, is another and distinct question.

Here Berg and his partner had a subcontract for the furnishing of the cut-stone work, and ordered stone of the plaintiff, which the latter furnished at a given rate, but, as he says, “on open account.” This account runs from May 4, 1877, to September 21, 1877, inclusive. On appellants' part it was testified that the stone-work of the buildings was completed in July, and that, under the contract, the buildings were to be completed by the 1st of...

To continue reading

Request your trial
8 cases
  • Minnehoma Financial Co. v. Pauli
    • United States
    • Wyoming Supreme Court
    • June 14, 1977
    ...Horn Lumber Co. v. Davis, 14 Wyo. 455, 84 P. 900, reh. den. 14 Wyo. 455, 85 P. 1048, 7 Ann.Cas. 940. We cited therein the case of Bruce v. Berg, 8 Mo.App. 204, for the proposition While we were not construing the same statute in Big Horn Lumber, we, nevertheless, believe the holding points ......
  • Big Horn Lumber Company v. Davis
    • United States
    • Wyoming Supreme Court
    • April 2, 1906
    ...Squires v. Fithian, 27 Mo. 134; Carson v. Steamboat, 16 Mo. 256; Stine v. Austin, 9 Mo. 558; Ring v. Jameson, 2 Mo. App., 584; Bruce v. Berg, 8 Mo. App., 204; Fire Co. v. Schwartz, 165 Mo. 171; 20 Ency. L. (2nd Ed.), 401, 402.) The phrase "after the indebtedness accrues" means after it had ......
  • Voightman & Co. v. Southern Ry. Co.
    • United States
    • Tennessee Supreme Court
    • November 19, 1910
    ...completion of which reserved work it was held by the court that the time began to run for the whole contract. The two cases of Bruce v. Berg, 8 Mo. App. 204, and Bruns v. Braun, 35 Mo. App. 337, we have not had access to. We are of the opinion, however, in what has already been said we have......
  • Denniston & Partridge Co. v. Howell
    • United States
    • Iowa Supreme Court
    • October 2, 1920
    ...Stock Yards v. O'Reilly, 85 Ill. 546. An omission supplied will extend (Id.; Avery v. Butler, 30 Or. 287, 47 Pac. at 708;Bruce v. Berg, 8 Mo. App. 204;Scott v. Cook, 8 Mo. App. 193;Worthen v. Cleaveland, 129 Mass. 570;Harrison v. Assoc., 134 Pa. 558, 19 Atl. 804, 19 Am. St. Rep. 714;Jeffers......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT