Bryan Builders Supply v. Midyette

Decision Date23 August 1968
Docket NumberNo. 688,688
PartiesBRYAN BUILDERS SUPPLY, a Corporation v. Norfleet W. MIDYETTE and wife, Shirley K. Midyette.
CourtNorth Carolina Supreme Court

Williamson & Walton, Whiteville, for Bryan Builders Supply, appellants.

No counsel for Norfleet W. Midyette and wife, appellees.

SHARP, Justice.

The basic error in this case is that the evidence was developed upon one theory, and the court submitted it to the jury upon another theory.

Upon Bryan's stipulation that at all times pertinent to this litigation it was not licensed to construct buildings 'where the cost is $20,000.00 or more,' Judge McKinnon correctly dismissed its action against owners for the balance due under the terms of the contract upon which it had sued. McArver v. Gerukos, 265 N.C. 413, 144 S.E.2d 277; Tillman v. Talbert, 244 N.C. 270, 93 S.E.2d 101; Courtney v. Parker, 173 N.C. 479, 92 S.E. 324. He correctly retained owners' counterclaim, which stated a cause of action against Bryan for breach of contract and faulty work.

The purpose of Article 1 of Chapter 87 of the General Statutes, which prohibits any contractor who has not passed an examination and secured a license as therein provided from undertaking to construct a building costing $20,000.00 or more, is to protect the public from incompetent builders. When, in disregard of such a protective statute, an unlicensed person contracts with an owner to erect a building costing more than the minimum sum specified in the statute, he may not recover for the owner's breach of that contract. This is true even though the statute does not expressly forbid such suits. 53 C.J.S. Licenses § 59 (1948); 33 Am.Jur. Licenses §§ 68--72 (1941); Annot., Failure of artisan or construction contractor to procure occupational or business license or permit as affecting validity or enforcement of contract. 82 A.L.R.2d 1429 (1962); 5 Williston Contracts (Revised Edition 1937) § 1630; 6 Williston Contracts, Ibid. § 1766; 6A Corbin on Contracts §§ 1510--1513.

In denying an unlicensed contractor the right to recover upon his contract, the court sometimes terms such contracts 'void,' but this term is too broad to be used in this connection. 'A void contract is no contract at all; it binds no one and is a mere nullity.' 17 Am.Jur.2d Contracts § 7 (1964). Contracts such as the one between owners and Bryan are not totally without legal effect, for the innocent party may maintain an action for damages for breach of a contract entered into between him and an unlicensed contractor. 33 Am.Jur. Licenses § 68 (1968 Cum.Supp. p. 80). See cases collected in Annot., 82 A.L.R.2d 1429, § 3(b) and § 6(b).

In Cohen v. Mayflower Corp., 196 Va. 1153, 86 S.E.2d 860, the Supreme Court of Virginia affirmed a verdict and judgment of $21,000.00, which a landowner had recovered against an unlicensed contractor for breach of his contract. As the Court pointed out, there is nothing immoral or contrary to public policy in a construction contract involving $20,000.00 or more. The statute does not forbid such contracts; it undertakes to protect citizens who expend over and above that amount from incompetent builders. The denial of recovery to an unlicensed contractor rests upon his conduct and not the nature of the transaction. Quoting from 6 Corbin on Contracts § 1510, p. 962, the Court said: "It would be a rare or nonexistent case in which such an innocent person could not maintain some kind of action for a breach of the agreement by the guilty party who has wrongfully engaged in business * * *.'

'This view is based upon the principle that such innocent party is among the class of persons designed to be protected by such statutes, that he is not In pari delicto with the unlicensed party, and is therefore entitled to relief. Or, to state the matter another way, to deny relief to the innocent party in such cases would defeat the purpose of the statute and penalize the person intended to be protected thereby.' Id. at 1162--1163, 86 S.E.2d at 865. (The factual situation in Cohen v. Mayflower Corp. and in the instant case is to be distinguished from the one in which a plaintiff seeks to recover money paid for services on the sole ground that the person who had rendered them was unlicensed. See Comet Theater Enterprises v. Cartwright, 9 Cir., 195 F.2d 80, 30 A.L.R.2d 1229; Annot., 30 A.L.R.2d 1233.)

Owners in this case were clearly entitled to pursue the cross action for damages, which they had alleged against Bryan, and, if they established a breach of its contract with them, they were entitled to recover the damages resulting therefrom. Robbins v. C. W. Myers Trading Post, Inc., 251 N.C. 663, 111 S.E.2d 884. In the alternative, owners could have sued to recover payments made in advance for performance which was not rendered as promised. Golding v. Casstevens, 255 N.C. 200, 120 S.E.2d 436.

Notwithstanding the fact that owners' evidence with reference to their damages, both as to breach of contract and the value of the actual benefit received from Bryan's construction, was minimal, under no theory was Bryan entitled to a judgment of nonsuit. 'In a suit for damages for breach of contract, proof of the breach would entitle the plaintiff to nominal damages at least.' Bowen v. Fidelity Bank, 209 N.C. 140, 144, 183 S.E. 266, 268. In a suit brought under the doctrine which prohibits unjust enrichment, the measure of recovery and the rules governing implied contracts apply. 22 Am.Jur.2d Damages § 78 (1965). Bowen v. Fidelity Bank, supra. '(I)mplied assumpsit (contract) is the basis for recovery on Quantum meruit; and, if such contract was breached (by Bryan), plaintiffs (owners) were entitled at least to nominal damages.' Gales v. Smith, 249 N.C. 263, 267, 106 S.E.2d 164, 168. Upon owners showing a breach of contract or a failure of consideration in any amount, they were entitled to recover nominal damages. Bryan's first assignment of error is overruled.

All other assignments which Bryan has brought forward relate to those portions of the charge which are set out in the statement of facts. Assignment of error No. 9, that the court failed to explain and apply the law to the evidence as required by G.S. § 1--180, is broadside and will be rejected. State v. Webster, 218 N.C. 692, 12 S.E.2d 272. An assignment based on failure to charge should set out the appellant's contention as to what the court should have charged. State v. Malpass and State v. Tyler, 266 N.C. 753, 147 S.E.2d 180. Bryan has no such assignment. However, its contention that the court erred in not instructing the jury that owners had 'accepted the house for occupancy in its defective condition' is totally without merit. The evidence would not support a charge that owners had waived their right to object to the defects.

Owners might well have excepted to, and assigned as error the issues submitted and those portions of the charge which constitute Bryan's assignments of error 3, 4, and 7. Clearly, the judge...

To continue reading

Request your trial
82 cases
  • Sykes v. Health Network Solutions, Inc.
    • United States
    • North Carolina Supreme Court
    • June 14, 2019
    ...declining to enforce contracts entered into by unlicensed professionals. For example, plaintiffs point us to Bryan Builders Supply v. Midyette , 274 N.C. 264, 162 S.E.2d 507 (1968) (recognizing that state law bars an unlicensed contractor from maintaining a breach of contract action against......
  • Richardson v. Bank of America
    • United States
    • North Carolina Court of Appeals
    • April 17, 2007
    ...recovery on quantum meruit." Thompson v. Thompson, 313 N.C. 313, 314-15, 328 S.E.2d 288, 290 (1985) (citing Bryan Builders Supply v. Midyette, 274 N.C. 264, 162 S.E.2d 507 (1968); Lexington Insulation Co. v. Davidson County, 243 N.C. 252, 90 S.E.2d 496 (1955)). "Stated differently, the law ......
  • Comm. to Elect Dan Forest v. Emps. Political Action Comm. (EMPAC)
    • United States
    • North Carolina Supreme Court
    • February 5, 2021
    ...for breach of contract can, in some circumstances, proceed on a theory of nominal damages. See, e.g., Bryan Builders Supply v. Midyette , 274 N.C. 264, 271, 162 S.E.2d 507 (1968) (explaining that in a contract action proof of breach alone is enough to avoid judgment of nonsuit). Even in a c......
  • Crescent University City Venture, LLC v. AP Atlantic, Inc.
    • United States
    • Superior Court of North Carolina
    • August 8, 2019
    ... ... is no underlying injury sounding in tort, citing Kaleel ... Builders, Inc. v. Ashby , 161 N.C.App. 34, 587 S.E.2d 470 ... (2003). Sears and ... Construction, LLC v. Stock Bldg. Supply, LLC , No ... 5:14-CV-537-BR, 2016 U.S. Dist. LEXIS 109490 (E.D. N.C ... "to nominal damages at least." Bryan Builders ... Supply v. Midyette , 274 N.C 264, 271, 162 S.E.2d 507, ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT