Buffalo Elec. Co. v. State
Decision Date | 23 February 1961 |
Docket Number | No. 32217,32217 |
Citation | 212 N.Y.S.2d 269,27 Misc.2d 527 |
Parties | BUFFALO ELECTRIC CO., Inc., Claimant, v. STATE of New York. Claim |
Court | New York Court of Claims |
William E. Miller, Lockport, Warner F. Thompson, Lockport, of counsel, for claimant.
Louis J. Lefkowitz, Atty. Gen., James L. Magavern, Asst. Atty. Gen., of counsel, for the State.
Confronted with a release clause in claimant's contract with the State of New York, in essence no different from that examined, considered and upheld in several instances both by the Court of Appeals and by other Courts, and applying what we believed to be decisive law to the fact that claimant had signed the contract with full knowledge that it contained such a clause; to the further fact that claimant had accepted final payment for the work done by it pursuant to its contract, we dismissed claimant's suit. Buffalo Electric Co., Inc. v. State, 1956, 4 Misc.2d 172, 158 N.Y.S.2d 265. In doing so, we were aware, too, of the fact that claimant's president by an endorsement on the check intended to, and believed that he did, reserve for claimant its right to proceed to recover for additional costs for work allegedly performed by it. Such additional costs, if proved, were incurred for something 'done or furnished for or relating to the work,' or for some 'act of omission' on the State or its agents, to borrow the phraseology of the contract document. That fact cannot be controverted.
There were other facts before us; clauses of the contract, letters from the State architect to the claimant, letters from the claimant to the State architect. These are quoted in pertinent part in our opinion reported as above cited. Our dismissal was effected by the granting of the Attorney General's motion that, under the contract, the acceptance of the final payment by the claimant operated as a release of the claim it now asserts which is for damages based upon delays and interferences and for extra work. That motion was not one for summary judgment as was the motion in Fredburn Construction Corporation v. City of New York, 1939, 280 N.Y . 402, 21 N.E.2d 370, but was granted after the development upon a trial of the facts hereinabove reviewed. Indeed, this Court, recognizing the doctrine of the Fredburn case, not only permitted claimant full opportunity to develop the facts during an extended trial but, a long time after its completion, permitted a reopening and received in evidence many documents then presented.
Upon appeal the case was remitted. Buffalo Electric Co., Inc. v. State of New York, 1959, 9 A.D.2d 372, 194 N.Y.S.2d 72, 74. The direction to this Court was:
'to decide the underlying question of fact as to whether both parties intended and understood that the check was to be a 'last payment' in full of all claims.'
The direction to us to make appropriate findings gave the parties to the suit the option of resting upon the proof already in the record, or of presenting additional proof. No additional proof has been offered by either party. Our search for intent must be made in the field already explored in our previous opinion. See Mace v. State, 1960, 12 App.Div.2d 702, 208 N.Y.S.2d 756.
At the outset we note that, although there is a comment in the Per Curiam opinion of the Fourth Department to the effect that, absent a consideration, a unilateral mistake by the one who releases may vitiate a release, the direction to us is that we should resolve the question of the intent and understanding of both parties. Consideration there was. It was mutually given in the original contract of which the release clause was a part. Claimant's president could not alter that contract by unilateral action. Granted that it was his intent to do so, who expressed the intent of the other party--the State of New York? Shall we say that the State architect did it? His letters, in essential part, are quoted in our previous opinion. He consistently held to a position in strict adherence to the terms of the contract. He had, in fact, no authority to do otherwise. He had, in law, no authority to make a new contract for the State of New York unless the decisions in Cauldwell-Wingate Co. v. City of New York, 1935, 269 N.Y. 539, 199 N.E. 524, and Nicholas v. City of New York, 1944, 293 N.Y. 704, 56 N.E.2d 587, and Oakhill Contracting Co. v. City of New York, 1941, 262 App.Div. 530, 30 N.Y.S.2d 567, 570 are all to be overruled and set aside. In the words of the last cited authority: 'What was said in such transactions was overridden by what was done in accepting payment.' Cf. Raleigh Associates, Inc . v. Henry, 1951, 302 N.Y. 467, 473, 99 N.E.2d 289, 291, Wilson Sullivan Co., Inc. v. International Paper Makers Realty Corporation, 1954, 307 N.Y. 20, 25, 119 N.E.2d 573, 574.
The heart of the matter lies in the much earlier case of MacArthur Bros. Co. v. City of New York, 1917, 177 App.Div. 725, 164 N.Y.S. 753, 754, affirmed 224 N.Y. 629, 121 N.E. 877. That was an appeal from a directed verdict for the defendant. For ready reference we quote from the opinion as follows:
...
To continue reading
Request your trial-
Buffalo Elec. Co. v. State
...on this question, the Court of Claims indicated its disagreement with the reasoning of this court and again dismissed the claim (27 Misc.2d 527, 212 N.Y.S.2d 269). In these circumstances, we are constrained to reverse the judgment of the Court of Claims and to make a final disposition of th......
-
FERRO CONCRETE CONSTRUCTION CO. v. Kentucky Utilities Co., 1314.
...629, 121 N.E. 877 (1917); Oakhill Contracting Co. v. City of New York, 262 App.Div. 530, 30 N.Y.S.2d 567 (1941); Buffalo Electric Co. v. State, 27 Misc.2d 527, 212 N.Y.S.2d 269. The authorities relied upon by the plaintiff appear to be distinguishable and Let an order be entered in conformi......
-
Buffalo Elec. Co. v. State
...the opinion of the court (9 A.D.2d 372, 194 N.Y.S.2d 72). On the second trial the Court of claims again dismissed the claim (27 Misc.2d 527, 212 N.Y.S.2d 269) and the Appellate Division again reversed, this time 'on the law and facts', and, holding the defense of release insufficient, remit......
-
Tufano Contracting Corp. v. Port of New York Authority
...judgment on the first cause of action to be final payment under the release clause of the contract. (Buffalo Elec. Co. v. State of New York, 27 Misc.2d 527, 531, 212 N.Y.S.2d 269, 272.) The current practice, in the Court of Claims, under similar circumstances has been to sever that part of ......