Buffalo Forge Co v. Southern Ry. Co
Citation | 159 S.E. 301,43 Ga.App. 445 |
Decision Date | 15 June 1931 |
Docket Number | No. 21024.,21024. |
Parties | BUFFALO FORGE CO. v. SOUTHERN RY. CO. et al. |
Court | United States Court of Appeals (Georgia) |
Syllabus by the Court.
While it is true that a materialman who furnishes material to a subcontractor for the improvement of real estate is not entitled to a lien upon the property so improved, where the subcontractor has no contractual relation with the owner of such realty, still, under the evidence in this case, it appeared as a matter of law that the material was furnished to a contractor of the owner, and not merely to a subcontractor; and, the right of the lien as claimed by the materialman being otherwise established, a judgment of foreclosure should have been entered in the plaintiff's favor. The appellate division of the municipal court of Atlanta correctly reversed the judgment of the trial court denying such lien, and the superior court erred in sustaining the certiorari and reversing the judgment of the appellate division.
Error from Superior Court, Fulton County; G. H. Howard, Judge.
Suit by the Buffalo Forge Company against the Southern Railway Company and others. Judgment for plaintiff was reversed by the superior court, and plaintiff brings error.
Reversed.
On March 14, 1928, a contract was entered into between Southern Railway Company, of the one part, and United Engineers & Constructors, Inc., of the other part, for the erection of additions to buildings of the Southern Railway Company on Spring street in the city of Atlanta. On June 18, 1928, United Engineers & Constructors, Inc., made a contract with the Seeley Company, Inc., by which the Seeley Company, Inc., agreed to install a heating system in the building for the sum of $22,875. This company then purchased certain material from Buffalo Forge Company at a cost of $1,850, for which the forge company duly filed and had recorded its claim as a materialman. This amount was not paid according to agreement, and the forge company brought suit in the municipal court of Atlanta against the Seeley Company, Inc., as con-tractor, and Southern Railway Company, as owner, to recover a judgment against the former and to foreclose its materialman's lien against the latter upon this claim. The trial court rendered judgment in favor of the plaintiff against the Seeley Company, Inc., but exonerated the owner, the Southern Railway Company. The appellate division reversed the judgment of the trial court as to the Southern Railway Company, and rendered a final judgment against both the defendants, as contended for by the plaintiff. The Southern Railway Company then carried the case by certiorari to the superior court, which reversed the judgment of the appellate division and held with the trial judge that the plaintiff was not entitled to a lien against the real estate improved; whereupon Buffalo Forge Company excepted.
The parties will be referred to as the railway company, the engineers company, the Seeley company, and the forge company, respectively.
Underwood, Haas & Gambrell and R. Emerson Gardner, all of Atlanta, for plaintiff in error.
McDaniel, Neely & Marshall and W. O. Wilson, all of Atlanta, for defendants in error.
BELL., J. (after stating the foregoing facts).
A materialman who furnishes material to B subcontractor for the improvement of real estate is not entitled to a lien upon the properly so improved, where the subcontractor has no contractual relation with the owner of the realty. General Supply Co. v. Hunn, 126 Ga. 615 (1), 55 S. E. 957. The question for decision in this ease is whether the Seeley company was a subcontractor. If so, the judgment of the superior court was correct, but if this company was a contractor, and not a mere subcontractor, the plaintiff was entitled to its lien, and the court erred in sustaining the certiorari. The solution of this question will depend upon the nature of the contract between the railway company, as owner, and the engineers company by which the contract was made with the Seeley company for the installation of the heating system. If the en' gineers company was itself the contractor, then the Seeley company was a subcontractor, but, if the engineers company was made the agent of the railway company for the erection of the building, the Seeley company became the contractor, and the plaintiff's claim of lien should have been established.
The following is a statement of the material portions of the contract between the railway company and the engineers company:
To continue reading
Request your trial