Butterfield v. Byron

Decision Date19 May 1891
PartiesBUTTERFIELD v. BYRON.
CourtUnited States State Supreme Judicial Court of Massachusetts Supreme Court
COUNSEL

Robinson & Robinson, for plaintiff.

Geo. M Stearns, for defendant.

OPINION

KNOWLTON J.

It is well established law that where one contracts to furnish labor and materials, and construct a chattel, or build a house, on land of another, he will not ordinarily be excused from performance of his contract by the destruction of the chattel or building without his fault before the time fixed for the delivery of it. Adams v. Nichols, 19 Pick 275; Wells v. Calnan, 107 Mass. 514; Dermott v Jones, 2 Wall. 1; School-Dist. v. Bennett, 27 N.J.Law, 513; Tompkins v. Dudley, 25 N.Y. 272. It is equally well settled that where work is to be done under a contract on a chattel or building which is not wholly the property of the contractor, or for which he is not solely accountable, as where repairs are to be made on the property of another, the agreement on both sides is upon the implied condition that the chattel or building shall continue in existence, and the destruction of it without the fault of either of the parties will excuse performance of the contract, and leave no right of recovery of damages in favor of either against the other. Taylor v. Caldwell, 3 Best & S. 826; Lord v. Wheeler, 1 Gray, 282; Manufacturing Co. v. Butler, 146 Mass. 82, 15 N.E. 76; Bank v. Beal, 141 Mass. 566, 6 N.E. 742, and cases there cited; Dexter v. Morton, 47 N.Y. 62; Walker v. Tucker, 70 Ill. 527. In such cases, from the very nature of the agreements as applied to the subject-matter, it is manifest that, while nothing is expressly said about it, the parties contemplated the continued existence of that to which the contract relates. The implied condition is a part of the contract as if it were written into it, and by its terms the contract is not to be performed if the subject-matter of it is destroyed, without the fault of either of the parties, before the time for complete performance has arrived.

The fundamental question in the present case is, what is the true interpretation of the contract? Was the house, while in the process of erection, to be in the control and at the sole risk of the defendant, or was the plaintiff to have a like interest as the builder of a part of it? Was the defendant's undertaking to go on and build and deliver such a house as the contract called for, even if he should be obliged repeatedly to begin anew on account of the destruction again and again of a partly completed building by inevitable accident, or did his contract relate to one building only, so that it would be at an end if the building, when nearly completed, should perish without his fault? It is to be noticed that his agreement was not to build a house, furnishing all the labor and materials therefor. His contract was of a very different kind. The specifications are incorporated into it, and it appears that it was an agreement to contribute certain labor and materials towards the erection of a house on land of the plaintiff, towards the erection of which the plaintiff was to contribute other labor and materials, which contributions would together make a completed house. The grading, excavating, stone-work, brick-work, painting, and plumbing were to be done by the plaintiff. Immediately before the fire, when the house was nearly completed, the defendant's contract, so far as it remained unperformed, was to finish a house on the plaintiff's land, which had been constructed from materials and by labor furnished in part by the plaintiff and in part by himself. He was no more responsible that the house should continue in existence than the plaintiff was. Looking at the situation of the parties at that time, it was like a contract to make repairs on the house of another. His undertaking and duty to go on and finish the work was upon an implied condition that the house, the product of their joint contributions, should remain in existence. The destruction of it by fire discharged him from his contract. The fact that the house was not in existence when the contract was made is immaterial. Howell v. Coupland, 1 Q.B.Div. 258. It seems very clear that after the building was burned, and just before the day fixed for the completion of the contract, the defendant could not have compelled the plaintiff to do the grading, excavating, stone-work, brick-work, painting, and plumbing for another house of the same kind. The plaintiff might have answered: "I do not desire to build another house, which cannot be completed until long after the date at which I wished to use my house. My contract related to one house. Since that has been destroyed without my fault, I am under no further obligation." If the plaintiff could successfully have made this answer to a demand by the defendant that he should do his part towards the erection of a second building, then certainly the defendant can prevail on a similar answer in the present suit. In other words, looking at the contract from the plaintiff's position, it seems manifest that he did not agree to furnish the work and materials required of him by the specifications for more than one house, and, if that was destroyed by inevitable accident just before its completion, he was not bound to build another, or to do anything further under his contract. If the plaintiff was not obliged to make his contribution of work and materials towards the building of a second house, neither was the defendant. The agreement of each to complete the performance of the contract, after a building, the product of their joint contributions, had been partly erected, was on an implied condition that the building should continue in existence. Neither can recover anything of the other under the contract; for he has not performed the contract so that its stipulations can be availed of. The case of Cook v. McCabe, 53 Wis. 250, 10 N.W. 507, was very similar in its facts to the one at bar, and identical with it in principle. There the court, in an elaborate opinion, after a full consideration of the authorities, held that the contractor could recover of the owner a pro rata share of the contract price for the work performed and the materials furnished before the fire. Clark v. Franklin, 7 Leigh, 1, is of similar purport.

What are the rights of the parties in regard to what has been done in part performance of a contract in which there is an implied condition that the subject to which the contract relates shall continue in existence, and where the contemplated work cannot be completed by reason of the destruction of the property without fault of either of the parties, is in dispute, upon the authorities. The decisions in England differ from those of Massachusetts and of most of the other states of this country. There the general rule, stated broadly, seems to be that the loss must remain where it first falls, and that neither of the...

To continue reading

Request your trial
1 cases
  • Butterfield v. Byron
    • United States
    • United States State Supreme Judicial Court of Massachusetts Supreme Court
    • May 19, 1891
    ...153 Mass. 51727 N.E. 667BUTTERFIELDv.BYRON.Supreme Judicial Court of Massachusetts, Hampden.May 19, Report from superior court, Hampden county; JAMES M. BARKER, Judge. Action by Alonzo M. Butterfield, for the benefit of the London & Lancashire Insurance Company and the Commercial Union Assu......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT