Capital Elec. Power Ass'n v. Mississippi Power & Light Co., 45104

Decision Date09 December 1968
Docket NumberNo. 45104,45104
Citation216 So.2d 428
CourtMississippi Supreme Court
PartiesCAPITAL ELECTRIC POWER ASSOCIATION v. MISSISSIPPI POWER & LIGHT COMPANY.

Hedgepeth & Hedgepeth, Jackson, for appellant.

Wise, Carter & Child, Jackson, for appellee.

ETHRIDGE, Chief Justice:

This case involves the validity of an order of the Public Service Commission pertaining to two electric utilities, and the question of whether under the existing facility rule the Commission had substantial evidence to justify it in authorizing Mississippi Power and Light Company, appellee (hereinafter called MP ), to construct on its own rights-of-way an electric line to provide standby auxiliary service for its properly authorized substation, which is located in an area certificated to Capital Electric Power Association. We hold that it had, and therefore affirm the decree of the Chancery Court for the First Judicial District of Hinds County, which in turn had affirmed the Commission's order.

In 1959 Capital Electric, appellant, obtained from the Commission a grandfather certificate of public convenience and necessity including the area in which is located MP 's substation. MP had an arrangement with other electric utility companies in the central south and with the TVA for the interchange of electric power. In order to provide for interchanges of large blocks of power, MP found it necessary to construct transmission lines of extra high voltage (EHV) and the necessary substations to step down power from high voltage to 115 KV. In 1963 (amended in 1965) the Commission granted MP a certificate to construct an EHV transmission system of 500 KV in certain areas of the state, including Hinds County. A part of this transmission system authorized by the Commission was the Ray Braswell 500 KV EHV substation located in Hinds County. Its purpose is to provide a point where the power, received from those with whom the company has interchange arrangements, may be transformed into the voltage required to utilize it in the Jackson and central Mississippi areas.

These orders of the Commission were not appealed from and are now final. The Braswell substation is located in the western part of Hinds County, within the area certificated to Capital Electric, which had notice of the application and hearing but did not protest construction of the substation at the present site. Because of these interchange arrangements, the Braswell substation is a vital and essential part of the EHV transmission system in the middle south, handling up to 2000 megawatts of power and transferring it from one area of the South to another. It is also a vital and essential part of MP 's electric system for the furnishing of adequate service to consumers in the Jackson and central Mississippi area.

Operation of the Braswell substation requires that certain auxiliary electric power be furnished to it in order to maintain an adequate level of temperature in the circuit breakers of the substation, which cost $250,000 each, to provide air-conditioning for the control house on the substation site and electronic equipment in it, and to furnish lighting on the substation for certain DC battery chargers. These are essential to continue its operation. The auxiliary power must be available constantly. The substation cannot be without such auxiliary power for a period of more than one and one-half hours without serious damage to MP 's system. Auxiliary power is that used on the substation site for purposes of maintaining the facility, which in turn provides a source of power for MP 's system. It is furnished by using certain extra power in the transformers located in the substation.

The purpose of the approximately 6,000 feet of 13.8 KV...

To continue reading

Request your trial
8 cases
  • Mississippi Public Service Com'n v. Mississippi Power Co., 54059
    • United States
    • Mississippi Supreme Court
    • March 23, 1983
    ...determine the weight of the evidence, the reliability of estimates and the credibility of witnesses. Capital Electric Power Ass'n v. Mississippi Power & Light Co., 216 So.2d 428 (Miss.1968); and Southern Bell T. & T. Co. v. Mississippi Pub. Serv. Com'n., 237 Miss. 157, 113 So.2d 622 (1959).......
  • Mississippi Public Service Com'n v. South Cent. Bell Telephone Co., 55347
    • United States
    • Mississippi Supreme Court
    • December 5, 1984
    ...Mississippi Public Service Commission v. Mississippi Power Company, 337 So.2d 936 (Miss.1976); Capital Electric Power Association v. Mississippi Power & Light Company, 216 So.2d 428 (Miss.1968); and Southern Bell Telephone & Telegraph Company, v. Mississippi Public Service Commission, 237 M......
  • Mississippi Public Service Commission v. Mississippi Power Co.
    • United States
    • Mississippi Supreme Court
    • October 5, 1976
    ...determine the weight of the evidence, the reliability of estimates and the credibility of witnesses. Capital Electric Power Ass'n v. Mississippi Power & Light Co., 216 So.2d 428 (Miss.1968); and Southern Bell T. & T. Co. v. Mississippi Pub. Serv. Com'n,237 Miss. 157, 113 So.2d 622 (1959). 3......
  • State ex rel. Pittman v. Mississippi Public Service Com'n, 55540
    • United States
    • Mississippi Supreme Court
    • November 27, 1985
    ...Co., 429 So.2d 883 (Miss.1983); Miss. Pub. Ser. Comm. v. Miss. Power Co., 337 So.2d 936 (Miss.1976); Capital Electric Power Assoc. v. Miss. Power & Light Co., 216 So.2d 428 (Miss.1968); and Southern Bell Telephone & Telegraph Co. v. Miss. Pub. Ser. Comm., 237 Miss. 157, 113 So.2d 622 In the......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT