Carey v. Westinghouse Elec. Corp., AFL-CI

Decision Date21 November 1961
Docket NumberP,AFL-CI
Citation15 A.D.2d 7,221 N.Y.S.2d 303
Parties, 49 L.R.R.M. (BNA) 2225, 43 Lab.Cas. P 50,396 James B. CAREY, as President of International Union of Electrical, Radio and Machine Workers,etitioner-Appellant-Respondent, v. WESTINGHOUSE ELECTRIC CORPORATION, Respondent-Respondent-Cross-Appellant.
CourtNew York Supreme Court — Appellate Division

Isadore Katz, New York City, of counsel (Lieberman, Katz & Aronson, New York City, and Benjamin C. Sigal), Washington, D. C., for petitioner-appellant-respondent.

John F. Hunt, Jr., New York City, of counsel (John D. Calhoun, New York City, with him on the brief, Cravath, Swaine & Moore, New York City), for respondent-respondent-cross-appellant.

Before BOTEIN, P. J., and VALENTE, STEVENS, EAGER and STEUER, JJ.

STEUER, Justice.

Petitioner, a labor union, instituted this proceeding to compel respondent to arbitrate four grievances. As to one of these, the disposition of Special Term has been acquiesced in by the parties and is not before the Court. Special Term directed arbitration on two of the grievances and dismissed the petition as to the other. Both parties appeal from the decision in so far as it is adverse to their contentions.

The first grievance, numbered 2079-A, arose in the company's East Pittsburgh plant. For many years the company had an incentive pay program in connection with which it established time values for various operations. From time to time these time values were changed in accordance with changing conditions of operation. The collective bargaining agreement contains the provision: 'Management recognizes that time values should be revised as soon as possible after the changes have been completed.' (Agreement, Section VIII, 8 E(2)(c).) In October, 1957, a major change in the time value of a molding operation was put into effect. The union claims that the change embraced variances which had accumulated over a period of several years. The union protests the change on the ground it was not timely made in accordance with the Agreement. Special Term ordered arbitration.

The equivocal wording of the phrase relied on, not constituting an agreement, is understood when another clause of the bargaining agreement is considered:

'Notwithstanding any other provisions of this Agreement, no arbitrator shall * * * be authorized to:

* * *

* * *

'(2) Establish or modify any wage or salary rate * * * or any time value under the incentive system.' (Section XIV--A, D)

When both these provisions are taken into consideration the contractual intent stands revealed. This is the primary guide to the solution of the problem presented (Steelworkers v. Warrior & Gulf Navigation Co., 363 U.S. 574, 80 S.Ct. 1347, 4 L.Ed.2d 1409). The intent is that incentive pay, like all other rates of wage, being the result of completed negotiations, is not subject to further adjustment by arbitration. While the company expressed a policy of implementing the time values to operating changes as soon as possible, there is no undertaking in that regard. Actually the delay favored the workers. Improvement in processes reduced time values. But until the change was reflected in the reduced time value the worker enjoyed the rate still in effect. When the change was reflected in the incentive pay, the demand to arbitrate followed promptly. But the contract leaves nothing for the arbitrator to determine. What the union really wants determined is that the change in time value--reflecting as it does several minor changes of long standing--should not be allowed to stand because of the delay in effectuating it. But such a decree the arbitrator cannot render.

There is a school of thought, to which Special Term subscribed, that prior to the award the court should not concern itself with what the arbitrator may decide but that this should be made to await an application to confirm the award. For example, here, if the arbitrator does change the time value, his award may be vacated on such a motion. We believe that whether court action should precede or succeed the arbitrator's award is not subject to unbending rule but presents a question requiring consideration of the nature of the objection and the scheme of the agreement providing for arbitration. The Agreement here provides (Section XIV-A, C(5)) that if either party notifies the American Arbitration Association (which is the body designated to implement arbitrations under the Agreement) that no arbitrable issue is raised, the said Association cannot proceed to process the arbitration until the court has finally determined that there is an arbitrable issue. This provision shows an intent that such questions should be determined before, not after, arbitration has been had. Evidently the parties regarded the saving in time and energy as more important to them than the therapeutic value which the processing of even frivolous claims may have (Steelworkers v. American Manufacturing Co., 363 U.S. 564, 568, 80 S.Ct. 1347, 4 L.Ed.2d 1409). Here no basis can be found for vitiating the expressed and implemented intent of the parties. As the arbitration cannot result in an effectual award, the demand to arbitrate must be denied.

The second grievance is numbered 1971-C. It arose in the company's plant at Mansfield, Ohio. An employee suffered a protracted illness. After she was away from the plant for a year the company dropped her name from its rolls, thereby effectuating a discharge. About a month later she applied for a position and was given a physical examination by a company doctor who reported that her condition was not such as to warrant her being hired. An examination by her own physician resulted in an opposite opinion. Some months later the union filed this grievance. In the interim the company doctor who had made the examination died.

There is no doubt that a discharge is subject to arbitration (Carey v. Westinghouse, 6 A.D.2d 582, 180 N.Y.S.2d 203, affd. 6 N.Y.2d 934, 190 N.Y.S.2d 1003, 161 N.E.2d 216). Nor can there be any dispute but that the grounds and method of discharge have never been assented to by the union. So, on its face, the demand for arbitration is unexceptionable. The company raises two objections. The first is that the union does not really object to the discharge but only to the failure to rehire, which is evidenced by the fact that no protest followed the discharge but only eventuated when the former employee's application for a position was rejected. The failure to hire any individual is neither a grievance nor arbitrable. The second objection is that the demand is unavailable because of laches, and the delay is claimed to be prejudicial due to the death of the medical witness.

These objections are mutually contradictory. If the arbitration is confined to the discharge, the failure to rehire and the reasons therefor do not constitute issues. The union argues that in any event laches is a matter for the arbitrator to consider. Undoubtedly this would be so if the laches was a failure to make a timely demand for performance of the contract (Matter of Lipman [Haeuser Shellac Co.], 289 N.Y. 76, 43 N.E.2d 817, 142 A.L.R. 1088). Where the laches is asserted to bar the exercise of the right to arbitrate, the question is not so clear. The court must always decide whether there is an agreement to arbitrate and, ordinarily, this necessity would include a determination of whether the agreement has terminated, either by its terms or the interpretation put upon it by the parties. But where the agreement is in effect, the disposition of whether the particular claim has been shown to be abandoned by the failure to assert it is a matter of defense for the arbitrator to decide.

The other objection is based upon the presumption that the arbitrator will not pass upon the question of discharge but will adjudicate on the question of failure to rehire. This is an assumption that the court may not indulge in. We agree with Special Term that this grievance should proceed to arbitration.

The remaining grievance is 2286-G and arose in the Baltimore plant. It appears that the company has three classes of employees. One class, composed of clerical help, guards, etc., are not members of either the petitioner union or the Federation of Westinghouse Independent Salaried Unions (herein Federation) and are not involved in any way on this application. Of the others, some are engaged in production and maintenance work on a time basis and are members of petitioner union. The balance are engaged in experimental work, are salaried, and are members of Federation. It should be observed that the distinction between production and maintenance on the one hand and experimental work on the other is not so much a distinction in operative procedures as it is in the purpose for which the work is performed. Generally speaking, while in many instances the same operation is performed at the machines, the experimental work is deemed finer and the designation of an employee to the salaried division is described in the papers as a promotion.

The grievance stated is that certain employees doing certain work at Wilkens...

To continue reading

Request your trial
4 cases
  • Carey v. Westinghouse Electric Corporation
    • United States
    • U.S. Supreme Court
    • January 6, 1964
    ...Court of New York for an order compelling arbitration. That court refused. The Appellate Division affirmed, one judge dissenting, 15 A.D.2d 7, 221 N.Y.S.2d 303. The Court of Appeals affirmed, one judge dissenting, holding that the matter was within the exclusive jurisdiction of the Board si......
  • INTERNATIONAL U. OF E., R. & M. WKRS. v. Westinghouse Elec. Corp.
    • United States
    • U.S. District Court — Southern District of New York
    • May 16, 1963
    ...27652, 315 F.2d 499, cert. applied for. 14 While it is true that the New York State Court of Appeals in Carey v. Westinghouse Elec. Corp., 15 A.D.2d 7, 221 N.Y.S.2d 303 (1st Dept. 1961), aff'd, 11 N.Y.2d 452, 230 N.Y.S.2d 703, 184 N.E.2d 298 (1962), cert. granted, 372 U.S. 957, 83 S.Ct. 101......
  • Ramsey v. NLRB
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • February 12, 1964
    ...Court of New York for an order compelling arbitration. From a refusal by that court and an affirmance by the Appellate Division, 15 A.D.2d 7, 221 N.Y.S. 2d 303, the union appealed to the New York Court of Appeals, which affirmed, holding that the matter was within the exclusive jurisdiction......
  • Carey v. Westinghouse Electric Corporation
    • United States
    • New York Court of Appeals Court of Appeals
    • February 27, 1964
    ...Court of Appeals of New York. Feb. 27, 1964. Appeal from Supreme Court, Appellate Division, First Department, 15 A.D.2d 7, 221 N.Y.S.2d 303. Union brought proceeding to compel employer to arbitrate four grievances. The Special Term, Owen McGivern, J., directed arbitration on two of the grie......