Caroline County v. Dashiell
Decision Date | 11 February 2000 |
Docket Number | No. 81,81 |
Citation | 747 A.2d 600,358 Md. 83 |
Parties | COUNTY COMMISSIONERS OF CAROLINE COUNTY, Maryland v. J. ROLAND DASHIELL & SONS, INC. |
Court | Maryland Court of Appeals |
Anthony L. Meagher (Brett Ingerman, Piper, Marbury, Rudnick & Wolfe, LLP, on brief), Baltimore, for petitioner.
J. Edward Martin (Law Office of J. Edward Martin, P.A.), Towson; Russell D. Dashiell, Jr. (Widdowson & Dashiell, on brief), Salisbury, for respondent.
On July 10, 1997, J. Roland Dashiell & Sons, Inc. (Dashiell), respondent, filed a complaint in the Circuit Court for Caroline County against the County Commissioners of Caroline County (County), petitioner, and Greenhorne & O'Mara, Inc. (Greenhorne), claiming damages in excess of $2,000,000.00 for the alleged extra cost of work and delays and seeking the payment of $326,621.00 withheld by the County as liquidated damages pursuant to the Standard Form of Agreement Between Owner and Contractor dated February 22, 1994 (Dashiell Contract).
On August 5, 1997, respondent filed an amended complaint. On August 26, 1997, petitioner filed a Motion to Dismiss on the ground that respondent's claims under the Dashiell Contract were barred by its failure to file them in a timely manner as required by that contract and that any quasi-contractual claims were barred because of the express written contract between the parties. Respondent responded with a Second Amended Complaint on September 11, 1997, arguing that the County had waived that defense by its conduct. On September 17, 1997, respondent filed an untimely Answer to petitioner's Motion to Dismiss, which attached the Affidavit of Donald Dashiell. On October 6, 1997, petitioner filed a Second Motion to Dismiss or, in the alternative, for Summary Judgment and on January 26, 1998, the Circuit Court entered judgment in favor of the County and granted Greenhorne's Motion to Dismiss for failure to state a claim upon which relief could be granted. As part of this ruling, the trial court ruled that the Affidavit of Donald Dashiell was defective for want of a verification on personal knowledge. On February 3, 1998, respondent resubmitted the Affidavit of Donald Dashiell replacing the words, "according to my best knowledge, information and belief" with "upon personal knowledge." Respondent's Motion for Reconsideration was denied on February 25, 1998.
Respondent appealed to the Court of Special Appeals.1 In an unreported opinion, the intermediate appellate court affirmed the circuit court's decision as to the contract claims, holding that respondent's failure to comply with the Dashiell Contract's claim provisions barred its claims for breach of contract. That court also affirmed the circuit court's decision that respondent's quasi-contractual claim for quantum meruit was barred because there was an express contract between the parties. Neither of these two issues were the subject of a Petition for Writ of Certiorari. Accordingly, they are not before us.
The Court of Special Appeals, however, did reverse the circuit court's decision to grant summary judgment on Dashiell's quasi-contractual claim for unjust enrichment.2 Additionally, the Court of Special Appeals disagreed with the trial court's finding that the defective Affidavit was fatal to respondent's claims. The County, seeking review of these last two holdings, presents the following questions to this Court:
I. Does the express, written contract between the County and [respondent] bar [respondent]'s quasi-contractual claim for unjust enrichment?
II. Was [respondent]'s claim for unjust enrichment properly dismissed because the Affidavit of Donald Dashiell in opposition to the County's Motion for Summary Judgment was inadequate as a matter of law?
In November 1989, as a first step in the process of renovating and adding to the County's correctional facility, petitioner entered into a Standard Form of Agreement Between Owner and Architect with Greenhorne for improvements to the Caroline County Detention Center (Greenhorne Contract). Respondent was not a party to this agreement. Pursuant to it, Greenhorne, an architectural firm, was responsible for designing the renovation and for providing supervision and monitoring services during the actual construction of the building addition. The project consisted of a 7,000 to 7,700 square foot, three-story addition to the existing Caroline County Detention Center located in Denton, Maryland, and a 3,700 to 4,200 square foot renovation of the original facility.
On February 22, 1994, the County entered into the Dashiell Contract with respondent for construction of the proposed renovation. For a total sum of $3,075,383.00, respondent agreed to furnish all labor, equipment, materials, and services, and perform all of the work necessary to renovate and expand the detention center by a date no later than 425 calendar days after the date of commencement. Section 3.2 of the Dashiell Contract specifically provides that liquidated damages of $500 per calendar day would be assessed if Dashiell failed to complete the project within the 425 calendar-day period.
Section 9.1.7 of the Dashiell Contract allowed for the incorporation of additional documents intended to form part of the contract documents. The parties agreed to include American Institute of Architects, General Conditions of the Contract for Construction, Document A201 (1987), which contains the provisions of the contract that are the subject of this appeal. The relevant provisions are as follows:
4.3.8 Claims for Additional Time.
On March 22, 1994, respondent received a Notice to Proceed from the County authorizing it to begin work on the project immediately and requiring it to complete all work by May 22, 1995.3 Almost immediately thereafter, respondent began to encounter construction delays for which it requested an extension. By letter dated November 15, 1994, a sixty-day extension of time was granted respondent. The extension was implemented through Contract Change Order No. 24, which was accepted by respondent on November 22, 1994, thereby extending the completion date from May 22, 1995 to July 21, 1995. No further completion date extensions were granted. Ultimately, construction of the project was not completed by the required date of July 21, 1995.
There were a series of preliminary allegations by respondent that a claim for an extension of time due to delays might exist. By letter dated February 23, 1995, Steven P. Dashiell, respondent's executive vice-president, informed Greenhorne that respondent "[was] currently working to develop a claim for lost time due to weather." By letter dated February 16, 1996, Stephen P. Dashiell again contacted Greenhorne stating that "the purpose of this letter is to tender formal notice that J. Roland Dashiell & Sons, Inc. will be preparing a claim against Caroline County as provided under the General Conditions of the Contract for Construction." (Emphasis added.) Dashiell indicated that said claim would be filed by April 1, 1996. Neither of these letters constituted a proper claim in compliance with section 4.3 of the General Conditions of the Contract for Construction....
To continue reading
Request your trial-
St. Michael's Media, Inc. v. Mayor and City Council of Baltimore
... ... " Child Evangelism Fellowship of MD, Inc. v. Montgomery County Public Schools , 457 F.3d 376, 381 (4th Cir. 2006) (quoting 566 F.Supp.3d 361 Forbes , 523 ... , 442 Md. 685, 706, 114 A.3d 676, 688 (2015) (quoting Cnty. Comm'rs of Caroline Cnty. v. Roland Dashiell & Sons, Inc. , 358 Md. 83, 94, 747 A.2d 600, 606 (2000) ). Whether oral ... ...
-
Kantsevoy v. Lumenr LLC
... ... " County Comm'rs for Carroll County v. Forty W. Builders, Inc. , 178 Md. App. 328, 377, 941 A.2d 1181, 1209 ... , 442 Md. 685, 706, 114 A.3d 676, 688 (2015) (quoting Cnty. Comm'rs of Caroline Cnty. v. J. Roland Dashiell & Sons, Inc. , 358 Md. 83, 94, 747 A.2d 600, 606 (2000) ). Whether ... ...
-
Avram v. Samsung Elecs. Am., Inc.
... ... Phillips v. County of Allegheny, 515 F.3d 224, 231 (3d Cir. 2008) (established "reasonable inferences" principle not ... Supp. 2d 703, 708 (D. Md. 2003) (quoting County Comm'rs v. J. Roland Dashiell & Sons, Inc., 358 Md. 83, 95 n. 7, 747 A.2d 600, 607 n. 7 (2000)). North Carolina ... ...
-
James B. Nutter & Co. v. Black
... ... James B. Nutter & Co. (Nutter) appeals from a judgment of the Circuit Court for Baltimore County in favor of Edwina E. Black and David L. Moore, Esquire. Nutter describes itself as one of the ... Id. at 295, 936 A.2d 343 (quoting County Comm'rs v. J. Roland Dashiell & Sons, Inc., 358 Md. 83, 95 n. 7, 747 A.2d 600 (2000) ). Nutter contends that, if it is not ... ...
-
First To File: Issue 4
...to dismiss on those grounds as well. Id. 17 Id. at *4. 18 Id. (quoting Cnty. Comm'rs of Caroline Cnty. V. J. Roland Dashiell & Sons, Inc., 358 Md. 83, 86 (2000) and United States v. DynCorp International, LLC, 253 F. Supp. 3d 89, 114 (D.D.C. 2017)). See also United States ex rel. Mayman v. ......