Carr v. Trotta

Decision Date06 May 1986
Docket NumberNo. 4017,4017
Citation508 A.2d 799,7 Conn.App. 272
PartiesJohn F. CARR, Jr. v. Nicholas TROTTA.
CourtConnecticut Court of Appeals

Michael Feldman, with whom, on brief, were Elliott B. Pollack and Melvin A. Simon, Hartford, for appellant (defendant).

Wesley W. Horton, with whom were David B. Losee, Hartford, and, on brief, Kimberly A. Knox, Law Student Intern, for appellee (plaintiff).

Before BORDEN, SPALLONE and BIELUCH, JJ.

SPALLONE, Judge.

The defendant is appealing from the judgment of the trial court confirming an arbitration award in favor of the plaintiff.

The plaintiff brought this action to confirm the award which was rendered after a hearing on the matter which the defendant did not attend. At the close of the hearing, the arbitrator declared that the hearing would be completed when he received a transcript of the proceedings. The hearing was held on November 26, 1984. The arbitrator received the transcript on December 20, 1984, and he rendered his award on January 18, 1985. The award was made fifty-two days from the date of the hearing but within thirty days of the receipt of the transcript. By application dated January 25, 1985, the plaintiff moved to confirm the award pursuant to General Statutes § 52-417.

At the hearing on the application to confirm the award, the defendant testified and objected to the confirmation of the award. He claimed (1) that he did not receive sufficient notice of the arbitration hearing, (2) that the underlying contract providing for arbitration was cancelled by him, and (3) that the arbitrator did not render his award within thirty days of the completion of the hearing as is required by General Statutes § 52-416(a). 1

The trial court expressly found that the defendant had notice of the hearing and had not cancelled the contract. In addition, the trial court concluded that no motion to vacate the award had been filed by the defendant within thirty days after his receipt of notice of the award, as required by General Statutes § 52-420(b). On February 27, 1985, the court granted the application and confirmed the award.

On appeal, the defendant claims as error the trial court's conclusion that the arbitrator had the authority to extend the close of an arbitration hearing without the consent of the parties. The defendant claims further that the trial court erred in confirming an arbitration award rendered beyond the statutory deadline prescribed in § 52-420(b). We find no merit to these claims.

The plaintiff, citing Vail v. American Way Homes, Inc., 181 Conn. 449, 452-53, 435 A.2d 993 (1980), Local 1078 v. Anaconda American Brass Co., 149 Conn. 687, 690-91, 183 A.2d 623 (1962), and Kilby v. St. Paul Ins. Co., 29 Conn.Sup. 22, 25-26, 269 A.2d 295 (1970), claims that because the defendant failed to raise his issues on a motion to vacate the award, the trial court properly confirmed the award. We disagree.

The defendant's challenge of the arbitrator's award questions the legality of the award. It is in effect an attack upon the jurisdiction of the arbitrator to render an award beyond the thirty-day limit. The question of subject matter jurisdiction may be raised at any time. General Statutes § 52-416 clearly states that "[a]n award made after that time [thirty days after hearings are concluded or thirty days from receipt of additional material] shall have no legal effect unless the parties expressly extend the time in which the award may be made by an extension or ratification in writing." (Emphasis added.) This provision can only be interpreted to mean that the arbitrator under those conditions lacks the power to enter an award because he no longer has subject matter jurisdiction. We find these circumstances to be analogous to the situation where the trial judge renders a judgment in excess of 120 days after the close of a trial absent consent or waiver of the parties. See Practice Book § 145; Gordon v. Feldman, 164 Conn. 554, 556, 325 A.2d 247 (1973); Bogaert v. Zoning Board of Appeals, 162 Conn. 532, 536, 294 A.2d 573 (1972); Spelke v. Shaw, 117 Conn. 639, 644, 169 A. 787 (1933). In these cases, the rendering of late judgments was erroneous.

Although we conclude that the defendant has standing to question the arbitrator's power to render an untimely award, we disagree with his assertion that, in this case, the arbitrator's action was untimely. General Statutes § 52-416(a) provides alternate conditions that trigger the thirty day period. As referenced above, one such alternative provides that the award shall be rendered "within thirty days from the date the hearing or hearings are completed...."

In the present action, the arbitrator declared that he was extending the completion date of the hearing until the date he received a transcript of the proceedings. There is no requirement that he seek the consent of the parties before instituting this procedure. Frank v. Streeter, 192 Conn. 601, 604, 472 A.2d 1281 (1984); C. iF. Wooding Co. v. Middletown Elk's Home Corporation, 177 Conn. 484, 486-87, 418 A.2d 904 (1979). Although we have no cases to guide us, it is apparent to us that we should test the arbitrator's decision by whether it was reasonable, under the circumstances in this case, to extend the completion date of the hearing until the transcript was to be received. We conclude that a transcript aids the trier in the same manner as a brief does, and that it is wholly consistent with good trial practice, when the trier feels the need, to request a transcript of the proceeding before rendering the decision. Our Supreme Court has affirmed the declaration of an arbitrator that the hearing would be closed upon the receipt of briefs. C.F. Wooding Co. v. Middletown Elk's Home Corporation, supra.

Here, there has been no showing that the request for a transcript was made for the purpose of delay, nor has there been any indication of prejudice to the defendant. The reliance of the dissent on a showing of prejudice to the defendant, arising from the late submission of the bill for legal fees, is inexplicable in this case. Although at the beginning of his brief in this court, the defendant makes an unsubstantiated, and subsequently unargued, assertion that he was "prejudiced by the extension of the hearing, the posthearing admission of evidence and the untimely award," at oral argument in this court he specifically disclaimed any prejudice to him flowing from the claimed statutory violation which is the basis of his appeal. Moreover, even if there were such prejudice, it would only extend to the award of $1184.39 in legal fees, which we note is less than 10 percent of the entire award. The dissent would have the tail wag the dog.

The gist of the defendant's appeal is not that the arbitrator erred by permitting the legal fees for the arbitration proceeding to be submitted late. It is, instead, that the arbitrator had no power to extend the hearing termination date to the receipt of the transcript. Yet, even if the defendant had notice of that action of the arbitrator, it would not have helped him any way. Short of claiming an inaccuracy in the transcript, which he does not claim and which, considering his voluntary absence from the hearing, he is no position to claim, there would have been nothing that he could have done at that point to protect his interests any further.

Thus, the reliance of the dissent on Bonner v. American Financial Marketing Corporation, 181 Conn. 57, 434 A.2d 323 (1980), is inapt. First, in Bonner, the defendant had appeared in the case, the default was entered for failure to appear at a deposition, and the court entered the default and a subsequent judgment without any such motions before it and without, therefore, any prior notice to the defendant. Second, Bonner is based on a specific rule of practice requiring a motion for judgment to be filed following a default. T hird, as Bonner indicates, the 'effect of the entry of the default was to preclude the defendant from making any defense to liability in the action,' and even after a default the defendant would habe been entitled, at a hearing in damages, to raise prior defenses. Id., 58, 434 A.2d 323. No such considerations are present in this case.

We hold that the arbitrator had the authority to declare that the hearing would be deemed completed upon his receipt of the transcript. See Frank v. Streeter, supra; C.F. Wooding Co. v. Middletown Home Elk's Corporation, supra.

The decision of the trial court to confirm the award is correct, but not for the reason that the defendant failed to file a motion to vacate. As we concluded above, the defendant had standing to question the subject matter jurisdiction of the arbitrator upon the court's consideration of the plaintiff's motion to confirm. Where the trial court reaches a correct decision on incorrect grounds, that decision will be sustained if correct grounds exist to support it. Johnny Cake, Inc. v. Zoning Board of Appeals, 180 Conn. 296, 301, 429 A.2d 883 (1980); Royce v. Freedom of Inofrmation Commission, 177 Conn. 584, 588, 418 A.2d 939 (1979); Favorite v. Miller, 1796 Conn. 310, 317, 407 A.2d 974 (1978).

There is no error.

In this opinion, BORDEN, J., concurred.

BIELUCH, Judge, dissenting.

I dissent because I do not agree that the arbitrator's unilateral agreement with the plaintiff without notice to the defendant to close the hearing upon receipt at an indefinite date of a transcript of the hearing permitted an extension of the statutory time for rendering his award. General Statutes § 52-416(a) provides two alternate periods of limitation. Either the award must be made (1) within thirty days of the completion of the hearing, or (2) within thirty days from the date fixed by the arbitrator for the receipt of additional material to be submitted by the parties after the hearing. The award here was untimely by either standard.

The following facts are relevant: The arbitration hearing was...

To continue reading

Request your trial
13 cases
  • Remax Right Choice v. Aryeh, 26571.
    • United States
    • Connecticut Court of Appeals
    • April 10, 2007
    ...parties' dispute and to issue an award. We do not agree. In support of his argument, the defendant relies primarily on Carr v. Trotta, 7 Conn.App. 272, 508 A.2d 799, cert. denied, 200 Conn. 806, 512 A.2d 229 (1986). Specifically, the defendant refers to the following language from that case......
  • Benistar Emp'r Servs. Trust Co. v. Benincasa, AC 40081
    • United States
    • Connecticut Court of Appeals
    • April 23, 2019
    ...date] by whether it was reasonable, under the circumstances ... to extend the completion date of the hearing ...." Carr v. Trotta , 7 Conn. App. 272, 276, 508 A.2d 799, cert. denied, 200 Conn. 806, 512 A.2d 229 (1986).In Carr , this court concluded that it was reasonable for the completion ......
  • Benistar Employer Services Trust Company v. Benincasa, HHDCV136042110S
    • United States
    • Connecticut Superior Court
    • January 17, 2017
    ...512 A.2d 229 (1986) is the appropriate standard for addressing the appropriateness of such a decision. As a matter of first impression, the Trotta court a standard of reasonableness to review an arbitrator's decision to establish the completion date of a hearing. " At the close of the heari......
  • All Seasons Services, Inc. v. Guildner
    • United States
    • Connecticut Court of Appeals
    • February 28, 2006
    ...was bound to consider the clarification, is a matter of law that is subject to plenary review by this court. See Carr v. Trotta, 7 Conn.App. 272, 274-75, 508 A.2d 799, cert. denied, 200 Conn. 806, 512 A.2d 229 (1986). Although the parties based their arguments regarding that issue solely on......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT