CARSTENSEN CONT. v. MID-DAKOTA RURAL WATER
Citation | 653 N.W.2d 875,2002 SD 136 |
Decision Date | 13 November 2002 |
Docket Number | No. 22345.,22345. |
Parties | CARSTENSEN CONTRACTING, INC., Plaintiff and Appellee, v. MID-DAKOTA RURAL WATER SYSTEM, INC., Defendant and Appellant. |
Court | South Dakota Supreme Court |
Mark V. Meierhenry of Danforth, Meierhenry & Meierhenry Sioux Falls, South Dakota, Attorneys for plaintiff and appellee.
Timothy M. Engel of May, Adam, Gerdes & Thompson Pierre, South Dakota, Attorneys for defendant and appellant. KONENKAMP, Justice.
[¶ 1.] In this construction contract dispute, we must decide whether a requirement in the contract that the general contractor pay "all claims growing out of the lawful demand of" subcontractors, laborers, mechanics, materialmen, furnishers and suppliers means claims only on which a mechanic's lien has been filed. In granting summary judgment, the circuit court held that the general contractor had no duty to pay the unpaid bills from a bankrupt subcontractor's suppliers, since the suppliers filed no mechanic's liens to secure their claims. Because the filing of a mechanic's lien is not what makes a claim "lawful," we conclude that, under the terms of the contract, the owner had the right to withhold the sums necessary to pay claims against the project, even if no mechanic's lien had been filed to secure those claims. We reverse.
[¶ 2.] This is a contract dispute between Carstensen Contracting, Inc. and Mid-Dakota Rural Water System, Inc. Carstensen, a general construction contractor experienced in the building of rural and municipal water systems, is a Minnesota corporation, authorized to do business in South Dakota. Mid Dakota, a South Dakota nonprofit corporation headquartered in Miller, owns and operates a rural water system that provides potable water to rural and municipal residents of east central South Dakota.
[¶ 3.] The parties stipulated to an extensive set of facts, some of which will be recited here. The documents relevant to this dispute are the Agreement, General Conditions, and Supplemental General Conditions (collectively, the contract documents).1 Mid-Dakota prepared these documents; Carstensen executed them in the form supplied by Mid-Dakota. The contract called for the construction of a rural distribution pipeline and related appurtenances in Hand and Hyde Counties.
[¶ 4.] Carstensen engaged J & M Gravel, Inc., to act as a subcontractor on the project. In the course of its work, J & M incurred certain debts for various items used on, and related to, the project. Such items included rental charges and fuel for equipment, general supplies, food, and housing for J & M's employees. Carstensen alleges that the last date upon which J & M supplied or used services, labor, equipment, or materials was November 2, 2000. Mid-Dakota avers that J & M supplied labor and materials as late as January 29, 2001.
[¶ 5.] No supplier or subcontractor for J & M Gravel filed a mechanic's or materialmen's lien against the project. See generally SDCL Ch. 44-9. However, beginning on January 26, 2001, Mid-Dakota began receiving notices from various suppliers of J & M that it had not paid for items it had used. These claims amounted to nearly $160,000.
[¶ 6.] At least two of J & M's suppliers have alleged that a representative of Carstensen encouraged them not to file mechanic's or materialmen's liens against the project, telling them that Carstensen would "take care of" any unpaid bills owed by J & M. Mid-Dakota's engineers are prepared to testify that, in January of 2001, a representative of Carstensen told them that Carstensen would pay J & M's suppliers out of retainage held by Carstensen on J & M's contract with Carstensen. Carstensen denies that any such promises were made. On February 20, 2001, J & M filed for Chapter 7 bankruptcy.
[¶ 7.] Under these circumstances, Mid-Dakota began to withhold from Carstensen's unpaid compensation an amount Mid-Dakota deemed sufficient to pay claims presented by J & M's suppliers. Carstensen brought suit to recover these withheld funds. Both sides moved for summary judgment on the question whether Carstensen is obliged to pay the unpaid claims of J & M's suppliers for items used on or in connection with the project. The circuit court granted Carstensen's motion for summary judgment and ordered Mid-Dakota to resume payment to Carstensen in accordance with the terms of the contract. Mid-Dakota appeals, raising the following issue: "Whether the trial court erred when it ruled that Carstensen is not liable for debts left unpaid by its subcontractor that subsequently filed for bankruptcy protection?"
[¶ 8.] In interpreting a contract, we seek to ascertain and give effect to the intention of the parties; at the same time, to find the intention of the parties, we rely on the contract language they actually used.2 Malcolm v. Malcolm, 365 N.W.2d 863, 865 (S.D.1985). In a case where, as here, several documents comprise the contract, all are to be read together to learn the parties' intent. Dail v. Vodicka, 89 S.D. 600, 237 N.W.2d 7 (1975). It is a fundamental rule of contract interpretation that the entire contract and all its provisions must be given meaning if that can be accomplished consistently and reasonably. Id. at 603, 237 N.W.2d at 9. However, when provisions conflict and full weight cannot be given to each, "the more specific clauses are deemed to reflect the parties' intentions—a specific provision controls a general one." State v. Greger, 1997 SD 14, ¶ 21, 559 N.W.2d 854, 864. Ordinarily, the plain meaning of the contract language will be followed unless there is some ambiguity or different intent manifested. American State Bank v. Adkins, 458 N.W.2d 807, 809 (S.D.1990).
[¶ 9.] We examine the following provisions in the General Conditions deemed relevant by the circuit court:
[¶ 10.] Mid-Dakota points out that, in accord with § 6.1, the general contractor remains primarily responsible to the owner, even if certain work is subcontracted to third parties. See Brooks v. Hayes, 133 Wis.2d 228, 395 N.W.2d 167, 168 (1986)
. Carstensen argues (and the trial court agreed) that Mid-Dakota ignores the initial caveat in § 6.1: "except as otherwise specifically stated in the contract documents." In particular, Carstensen highlights the word "lawful" in the initial sentence of § 19.6 () and then argues that no lawful demands have been made, nor could be made, because the time for making claims against the surety or for filing mechanics' liens has expired. As Carstensen sees the matter, Mid-Dakota is attempting to convert a moral obligation to pay J & M's suppliers into a legal obligation.4 Carstensen contends that Mid-Dakota has no legal obligation to pay J & M's suppliers, since...
To continue reading
Request your trial-
Parks v. Cooper, 22601.
...229 (citation omitted). The circuit court's conclusions of law are reviewed under the de novo standard. Carstensen Contracting, Inc. v. Mid-Dakota Rural Water System, Inc., 2002 SD 136, ¶ 8, 653 N.W.2d 875, 877, n2. Additionally, the burden of proving navigability and asserting the public t......
-
Lien v. Lien
...Lewis v. Moorhead, 522 N.W.2d 1, 3 (S.D.1994)). We review the trial court's conclusions of law de novo. Carstensen Contracting, Inc. v. Mid-Dakota Rural Water System, Inc., 2002 SD 136, ¶ 8, n. 2, 653 N.W.2d 875, 877 n. 2.... Our standard of review for cases in equity is abuse of discretion......
-
Hofeldt v. Mehling, 22380.
...Lewis v. Moorhead, 522 N.W.2d 1, 3 (S.D.1994)). We review the trial court's conclusions of law de novo. Carstensen Contracting, Inc. v. Mid-Dakota Rural Water System, Inc., 2002 SD 136, ¶ 8, 653 N.W.2d 875, 877 n. 2. Unjust enrichment is an equitable concept. Our standard of review for case......
-
Thacker v. Timm
...¶ 12, 639 N.W.2d 184, 187 ). "We review the [circuit] court's conclusions of law de novo." Id. (citing Carstensen Contracting, Inc. v. Mid-Dakota Rural Water Sys., Inc. , 2002 S.D. 136, ¶ 8 n.2, 653 N.W.2d 875, 877 n.2 ). [¶23.] The Estate argued that a fiduciary relationship existed betwee......