Chandler-Simpson, Inc. v. Gorrell

Decision Date30 January 1970
Docket NumberINC,No. 3800,CHANDLER-SIMPSO,3800
Parties, a Corporation, Appellant (Defendant below), v. Floyd D. GORRELL, Trustee in Bankruptcy for Paul Eugene Gillett, a Bankrupt, Appellee (Plaintiff below).
CourtWyoming Supreme Court

Harold Joffe, of Scott & Joffe, Worland, Thomas M. Burns and Peter J. Wall, of Burns & Wall, Denver, Colo., for appellant.

Floyd D. Gorrell, Worland, for appellee.

Before GRAY, C. J., and McINTYRE, PARKER, and McEWAN, JJ.

Mr. Justice McINTYRE delivered the opinion of the court.

In a suit on contract, the district court found for plaintiff, Floyd D. Gorrell, trustee in bankruptcy for Paul Eugene Gillett, Judgment was entered against defendant, Chandler-Simpson, Inc., in the amount of $10,812.37.

Chandler-Simpson appeals and claims the district court's judgment should be reversed for these reasons:

1. According to the construction placed by the parties themselves on their written agreement, nothing was owing on the contract.

2. The evidence demonstrates that Gillett was on the verge of bankruptcy and for this reason was not in a position to perform his part of the contract; and this excused defendant from its obligation to perform.

3. Gillett violated his duty to mitigate damages and his trustee should not be allowed to recover.

4. If the right of appellee to recover is sustained, interest prior to the date of the judgment should not be included because the claim was unliquidated.

We are inclined to think plaintiff's claim was unliquidated and that interest prior to the judgment should not have been included. Except for this, however, we find no reversible error in connection with any of the points urged by appellants.

Contract Interpretation

The contract here involved is one wherein Gillett as owner and lessor leased certain construction equipment to Chandler-Simpson as lessee. The lease agreement was to remain in effect for an indefinite term, but either party had a right to terminate the contract at any time by giving 15 days' written notice to the other party.

Along with other equipment, the lease covered as item (b) a Mack diesel powered truck and trailer, and as item (c) a D-8 bulldozer. The rental on the Mack truck was to be $12 per hour, and the rental on the D-8 bulldozer was to be $16 per hour. The lease provided, however, that:

'* * * the minimum monthly rental for the diesel powered truck referred to in (b) above will be $800 and the minimum monthly rental for the bulldozer referred to in (c) above will be $1200.'

Attorneys for Chandler-Simpson seek to interpret the provision just quoted as if it provided for a minimum monthly rental of $2,000 on item (b) and item (c) together. They say the provision can be so interpreted; that the contract is ambiguous; and that the courts should therefore look to evidence of how the parties, by actual billings, payments, and other procedures, have interpreted their written agreement.

There obviously is no ambiguity in the portion of the contract we have thus far quoted. It clearly provides for a monthly minimum of $800 on the truck and for a monthly minimum of $1200 on the bulldozer.

Before lookint to other provisions of the lease for the presence or absence of ambiguity, let us be sure we have in mind the rule on construction of contracts which will apply.

Such rule is, where the terms of a contract taken as a whole are plain and unambiguous, the meaning of the contract is to be deduced from its language alone; and where the language is ambiguous, the intent of the parties may be searched out by resort to extrinsic inquiry. Hastings v. Continental Food Sales, Inc., 60 Wash.2d 820, 376 P.2d 436, 438; Cave Construction, Inc. v. United States, 10 Cir., 387 F.2d 760, 762.

Inasmuch as the trial court has found and we likewise find the contract of the parties in this case not to be ambiguous, uncertain or indefinite, it is not subject to construction by act of the parties. Sinclair Oil & Gas Company v. Huffman, Okl., 376 P.2d 599, 601. See also United States, for Use of Moseley v. Mann, 10 Cir., 197 F.2d 39, 40; and Crestview Cemetery Association v. Dieden, 54 Cal.2d 744, 8 Cal.Rptr. 427, 356 P.2d 171, 177.

Following the provision in the lease which calls for a monthly minimum of $800 on the diesel powered truck (item (b)) and for a monthly minimum of $1200 on the D-8 bulldozer (item (c)), the agreement then provides:

'This minimum monthly rentals will apply regardless of whether the equipment is actually used by the Lessor 1, however, should Lessor 2 pay under this minimum rental provision for equipment which was not actually used during any month, it may apply this excess rental payment to the use of the equipment during succeeding months, subject to its obligation that in each month at least the minimum monthly rates as defined in this paragraph be paid. It is understood that the minimum monthly payments herein provided shall not apply to the gasoline powered truck referred to in (a) above nor the roadgrader referred to in (d) above.'

It is significant that plurals are used as they are in the provision last quoted. The reference to minimum monthly 'rentals' can only refer to the $800 minimum rental and the $1200 minimum rental. It negatives any idea of a single minimum rental, such as $2,000 per month for both items (b) and (c).

Again, the expressed obligation that in each month at least the minimum monthly 'rates' are to be paid can only mean at least $800 must be paid on truck (b) and $1200 must be paid on bulldozer (c). It cannot mean that one total 'rate' of $2,000 is required for both items of equipment.

The same is true in the last sentence quoted above. The reference to the minimum monthly 'payments' once again denotes that two minimum payments of $800 and $1200 are intended rather than one minimum payment of $2,000.

The unpaid balance which plaintiff has sued for in this case is the difference between what defendant had paid for the use of the bulldozer (item (c)) and what the minimum monthly rental on such bulldozer would amount to. Chandler-Simpson says actual payments made for use of the truck (item (b)) would exceed the minimum monthly rental for such truck far more than the shortage on the bulldozer. It seeks to apply the overpayments on the truck to the underpayments on the bulldozer.

If the contract had provided for one minimum of $2,000 on both pieces of equipment, appellant would be correct; but the contract clearly provides for one minimum on the truck and one minimum on the bulldozer. Therefore, payments for use of the truck in excess of the minimum there applicable cannot be applied to make up a deficiency in the minimum on the bulldozer.

Effect of Bankruptcy

Appellant argues under its point 2 that it was excused from performance because Gillett was on the verge of bankruptcy and not in a position to perform. In this connection appellant states, when Gillett first asserted his claim for minimum payments, in October of 1964, he was in financial jeopardy; his creditors were closing in, and all of his equipment 'was about to be taken away from him.'

It is true the contract provides, when lessor (meaning lessee) pays under the minimum rental provision for equipment not actually used during any month, it may apply the excess rental payment to the use of the equipment during succeeding months. Appellant points to the fact that the time came when Gillett was no longer able to furnish equipment and thus Chandler-Simpson was denied the right to use the bulldozer during future months in excess of the minimum and then apply past unused minimums to the excess in future months.

Appellan...

To continue reading

Request your trial
16 cases
  • Hollabaugh v. Kolbet
    • United States
    • Wyoming Supreme Court
    • January 11, 1980
    ...(1977); Mauch v. Ballou, Wyo., 499 P.2d 591, 593-594 (1972); Craig v. Gudim, Wyo., 488 P.2d 316, 319 (1971); Chandler-Simpson, Inc. v. Gorrell, Wyo., 464 P.2d 849, 851 (1970); Flora Construction Company v. Bridger Valley Electric Association, Inc., Wyo., 355 P.2d 884, 885 (1960); and Barlow......
  • Rissler & McMurry Co. v. Atlantic Richfield Co.
    • United States
    • Wyoming Supreme Court
    • January 12, 1977
    ...computation. Zitterkopf v. Roussalie, Wyo.1976, 546 P.2d 436; Mader v. James, Wyo.1976, 546 P.2d 190; Chandler-Simpson, Inc. v. Gorrell, Wyo.1970, 464 P.2d 849, 853 (see Wyoming cases there cited); United Pacific Insurance Company v. Martin and Luther General Contractors, Incorportated, Wyo......
  • State v. BHP Petroleum Co., Inc., 90-40
    • United States
    • Wyoming Supreme Court
    • January 14, 1991
    ... ... Zitterkopf v. Roussalis, Wyo.1976, 546 P.2d 436; Mader v. James, Wyo.1976, 546 P.2d 190; Chandler-Simpson, Inc. v. Gorrell, ... Page 676 ... Wyo.1970, 464 P.2d 849, 853 (see Wyoming cases there cited); United Pacific Insurance Company v. Martin and ... ...
  • Northern Gas Co. v. Town of Sinclair
    • United States
    • Wyoming Supreme Court
    • April 2, 1979
    ...Wyo., 560 P.2d 730 (1977); Mauch v. Ballou, Wyo., 499 P.2d 591 (1972); Craig v. Gudim, Wyo., 488 P.2d 316 (1971); Chandler-Simpson, Inc. v. Gorrell, Wyo., 464 P.2d 849 (1970); Flora Construction Company v. Bridger Valley Electric Association, Inc., Wyo., 355 P.2d 884 (1960); Barlow v. Marke......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT