CherCo Properties, Inc. v. Law, Snakard & Gambill, P.C., 2-97-131-CV

Citation985 S.W.2d 262
Decision Date28 January 1999
Docket NumberNo. 2-97-131-CV,2-97-131-CV
PartiesCHERCO PROPERTIES, INC., Appellant, v. LAW, SNAKARD & GAMBILL, P.C. and Calhoun & Stacy, f/k/a Calhoun, Gump, Spillman & Stacy, P.C., Appellees.
CourtCourt of Appeals of Texas

Gary F. Deshazo & Associates, Gary F. Deshazo, Jerome J. Schiefelbein, Austin, for Appellant.

Law, Snakard & Gambill, P.C., Ed Huddleston, Dabney Bassel, Lynn Johnson, Barlow & Garsek, P.C., James Barlow, Shannon, Gracey, Ratliff & Miller, Kleber Miller, J. Wade Birdwell, Fort Worth, for Appellees.

Before DAY, DAUPHINOT, and BRIGHAM, JJ.

OPINION

SAM J. DAY, Justice.

This appeal results from a judgment rendered in accordance with the terms of a written settlement agreement between the parties to this suit, Appellant CherCo Properties, Inc. (CherCo), and Appellees Law, Snakard & Gambill, P.C., (Law) and Calhoun & Stacy f/k/a Calhoun, Gump, Spillman & Stacy, P.C. (Calhoun). Because the trial court did not err in rendering judgment on the parties' settlement agreement and in granting summary judgment in favor of Appellees, we affirm.

I. BACKGROUND

CherCo sued Appellees for legal malpractice for their work on a lawsuit involving several oil and gas wells in Cherokee County, Texas. On December 12, 1995, before the malpractice trial began, the parties announced to the trial court and in front of the jury that they had reached a settlement. That same day, the settlement was reduced to writing and signed by each party. The parties' written agreement, which was handwritten by CherCo's attorney, read in its entirety as follows:

Parties:

a) Calhoun & Stacey, P.C.

b) Law Snakard & Gambill, P.C.

c) CherCo Properties, Inc., & Ayers related companies

Consideration:

a) Calhoun & Stacey, P.C. pays CherCo $15,000.00

b) Law Snakard & Gambill pays CherCo $30,000.00 & returns CherCo's $ sanctions check of $5,560.00

c) All parties bear their own costs and attys fees

d) All parties execute mutual releases including a release of Ralph Ayers & related companies as to any and all claims

e) All parties agree to indemnify one another for any claims that could have been brought by through or under them

The agreement was dated December 12, 1995 and signed by representatives of CherCo and Appellees. Law returned the $5,560 sanctions check to CherCo that same day. 1

On March 8, 1996, Law drafted a formal settlement document incorporating the terms of the agreement and sent it to CherCo for approval. CherCo, however, did not approve, and a flurry of correspondence ensued regarding additional terms the parties wanted to include in the final document. In May 1996, CherCo threatened to file a motion to enforce the agreement. Instead of following through on its threat, CherCo waited until September 13, 1996 and filed a motion to set the matter for trial on the jury docket, contending that the settlement had failed and it had withdrawn its consent to the agreement. CherCo also asserted that the written settlement agreement was unenforceable because it did not include a time for performance.

A week later, Law filed the parties' handwritten settlement agreement with the trial court. On November 8, Law sent another draft of the final agreement to CherCo and tendered payment of $30,000. Several days later, CherCo returned the check and notified Law that the formal agreement was still unacceptable and it was proceeding to have the matter reset for trial.

On December 18, 1996, Law filed a counterclaim alleging that CherCo had breached the written settlement agreement and asking the trial court to specifically enforce the agreement. On December 19, 1996--more than one year after the parties signed the settlement agreement--Law filed a motion to enforce the agreement or alternatively, a motion for summary judgment. Attached to the motion was the parties' handwritten agreement and evidence that CherCo had accepted the sanctions check returned by Law on December 12, 1995, and that Law had tendered a check for $30,000 to CherCo in November 1996 that CherCo refused to accept.

After a hearing, the trial court found that no genuine issue of material fact existed and granted Law's motion to enforce. The trial court rendered judgment in accordance with the terms of the parties' December 12th agreement and assessed attorney's fees, future attorney's fees, costs, and pre-judgment interest against CherCo.

II. THE SETTLEMENT AGREEMENT

In its first four points, CherCo contends that the parties' settlement agreement was unenforceable under Texas law and raises the following issues:

(1) What was the effect of CherCo withdrawing its consent to the parties' agreement?

(2) Did the omission of a time for performance render the agreement unenforceable (in other words, was time of performance a material term)?

(3) Was the trial court precluded from implying a reasonable time for performance?

(4) Under the circumstances of this case, was Law's performance within a reasonable time as a matter of law?

A. Rule 11

Under Rule 11 of the Texas Rules of Civil Procedure, no agreement between the attorneys or parties to a suit is enforceable unless it is in writing, signed, and filed with the papers as part of the record, or unless it is made in open court and entered of record. See TEX.R. CIV. P. 11. A settlement agreement must comply with Rule 11 to be enforceable. See Padilla v. LaFrance, 907 S.W.2d 454, 460 (Tex.1995). To satisfy the "in writing" provision of Rule 11, the same contract principles apply that are used to determine when a "writing" satisfies the statute of frauds. See id. Thus, a Rule 11 settlement agreement is not enforceable unless it is complete within itself as to every material detail and contains all the essential elements of the agreement so the contract can be ascertained from the writing, without resort to oral testimony. See id.

B. Applicable Case Law

Padilla is dispositive in this case. In Padilla, the parties had exchanged a series of letters regarding terms of a settlement while a lawsuit was pending against Enrique Padilla. See id. at 455. Padilla contended that the letters represented a written settlement between the parties and asked the trial court to enforce the agreement. See id. at 457. The plaintiffs contended that there was no written agreement between the parties. Furthermore, plaintiffs argued, even if there had been an agreement, it could not be enforced because (1) they had withdrawn their consent before judgment had been rendered on the agreement, and (2) Padilla had failed to file the letters until after plaintiffs had withdrawn their consent. See id.

The Texas Supreme Court held that Rule 11 does not require a writing to be filed in the trial court before the other party withdraws its consent. Rather, the purpose of the filing requirement is satisfied "so long as the agreement is filed before it is sought to be enforced." Id. at 461. Moreover, regarding the plaintiffs' contentions that they were entitled to withdraw their consent to the agreement, the Padilla court explained:

[Plaintiffs] confuse the requirements for an agreed judgment with those for an enforceable settlement agreement. Although a court cannot render a valid agreed judgment absent consent at the time it is rendered, this does not preclude the court, after proper notice and hearing, from enforcing a settlement agreement complying with Rule 11 even though one side no longer consents to the settlement. The judgment in the latter case is not an agreed judgment, but rather is a judgment enforcing a binding contract.

Id. (emphasis added).

Finally, the court noted that the letters between the parties constituted a settlement agreement because they contained all of the material terms of the agreement: an agreement to pay a specified sum of money in exchange for the settlement of all claims. See id. "Rather than requiring actual payment by a particular deadline, [the plaintiffs] accepted Padilla's agreement to pay...." Id. at 460 (first and second emphasis added). The court thus held that Padilla's evidence established an enforceable settlement agreement as a matter of law. See id. at 462.

Likewise, although withdrawal of CherCo's consent to the agreement may have been fatal to an agreed judgment, it has no affect on Law's motion to enforce the settlement agreement as a contract. See id. In addition, under the facts of this case, a time for performance is not a material term, and thus its omission does not render the parties' settlement agreement unenforceable. The parties' settlement agreement contained all the material terms of the agreement: Law agreed to pay $30,000 to CherCo and return CherCo's sanctions check, and Calhoun agreed to pay $15,000 to CherCo, both in exchange for CherCo's release of liability. See id. at 461. Accordingly, the trial court did not err in impliedly holding that the parties' agreement contained all the material terms and CherCo's withdrawal of consent had no effect on the enforceability of the contract.

CherCo also argues that Law was required to tender the $30,000 as a condition precedent to CherCo's duty to sign a final settlement document. Furthermore, CherCo contends that the timeliness of Law's performance was a question of fact for the jury and that the trial court was precluded under Tinney v. Willingham, 897 S.W.2d 543 (Tex.App.--Fort Worth 1995, no writ) from implying a reasonable time for performance. Finally, CherCo argues that Law's contractual performance included the duty to tender a final settlement document that was agreeable to all parties. We disagree on each count.

Generally, where no time for performance is stated in a contract, the law will imply a reasonable time. See Moore v. Dilworth, 142 Tex. 538, 179 S.W.2d 940, 942 (1944); Fitzsimmons v. Anthony, 716 S.W.2d 719, 720 (Tex.App.--Corpus Christi 1986, no writ). What is reasonable depends on the facts and circumstances as they existed at the date of the contract. See Solomon v. Greenblatt, 812 S.W.2d 7, 15 (Tex.App....

To continue reading

Request your trial
50 cases
  • Daimlerchrysler Motors Co. v. Manuel
    • United States
    • Texas Court of Appeals
    • February 24, 2012
    ...Co. v. Benchmark Elecs., Inc., 142 S.W.3d 554, 563 (Tex.App.-Houston [14th Dist.] 2004, pet. denied); CherCo Props., Inc. v. Law, Snakard & Gambill, P.C., 985 S.W.2d 262, 266 (Tex.App.-Fort Worth 1999, no pet.). What is a reasonable time depends upon the facts and circumstances as they exis......
  • West Beach Marina, Ltd. v. Erdeljac
    • United States
    • Texas Court of Appeals
    • December 5, 2002
    ...a settlement agreement complying with Rule 11 even though one side no longer consents to the settlement."); CherCo Prop., Inc. v. Law, Snakard & Gambill, P.C., 985 S.W.2d 262, 265 (Tex.App.-Fort Worth 1999, no pet.). West Beach's argument is thus without B. Alternative Dispute Resolution Pr......
  • Gen. M v. John Stergiou & Main Marine Repair & Indus. Cleaning Co.
    • United States
    • Texas Court of Appeals
    • July 28, 2014
    ...(noting that material terms of Rule 11 settlement agreement include payment and release of claims); see also CherCo Props., Inc. v. Law, Snakard & Gambill, P.C., 985 S.W.2d 262, 266 (Tex.App.-Fort Worth 1999, no pet.) (holding settlement agreement that included terms of payment and statemen......
  • Gen. Metal Fabricating Corp. v. Stergiou
    • United States
    • Texas Court of Appeals
    • February 14, 2013
    ...(noting that material terms of rule 11 settlement agreement include payment and release of claims); see also CherCo Props., Inc. v. Law, Snakard & Gambill, P.C., 985 S.W.2d 262, 266 (Tex. App.—Fort Worth 1999, no pet.) (holding settlement agreement that included terms of payment and stateme......
  • Request a trial to view additional results
6 books & journal articles
  • Discovery
    • United States
    • James Publishing Practical Law Books Archive Texas Employment Law. Volume 2 - 2014 Part VIII. Selected litigation issues
    • August 16, 2014
    ...Dept. of Public Safety , 346 S.W.2d 138, 140 (Tex. App.—Dallas 1961, no writ); CherCo Properties, Inc. v. Law, Snakard & Gambill, P.C. , 985 S.W.2d 262, 267 (Tex. App—Fort Worth 1999, n.w.h.) (legal malpractice suit in which plaintiff was sanctioned for failure to make reasonable inquiry be......
  • Discovery
    • United States
    • James Publishing Practical Law Books Archive Texas Employment Law. Volume 2 - 2016 Part VIII. Selected Litigation Issues
    • July 27, 2016
    ...Dept. of Public Safety , 346 S.W.2d 138, 140 (Tex. App.—Dallas 1961, no writ); CherCo Properties, Inc. v. Law, Snakard & Gambill, P.C. , 985 S.W.2d 262, 267 (Tex. App—Fort Worth 1999, n.w.h.) (legal malpractice suit in which plaintiff was sanctioned for failure to make reasonable inquiry be......
  • Discovery
    • United States
    • James Publishing Practical Law Books Texas Employment Law. Volume 1 Part VIII. Selected litigation issues
    • May 5, 2018
    ...Law 40-38 Safety , 346 S.W.2d 138, 140 (Tex. App.—Dallas 1961, no writ); CherCo Properties, Inc. v. Law, Snakard & Gam-bill, P.C. , 985 S.W.2d 262, 267 (Tex. App—Fort Worth 1999, n.w.h.) (legal malpractice suit in which plaintiff was sanctioned for failure to make reasonable inquiry before ......
  • Discovery
    • United States
    • James Publishing Practical Law Books Archive Texas Employment Law. Volume 2 - 2017 Part VIII. Selected litigation issues
    • August 19, 2017
    ...Dept. of Public Safety , 346 S.W.2d 138, 140 (Tex. App.—Dallas 1961, no writ); CherCo Properties, Inc. v. Law, Snakard & Gambill, P.C. , 985 S.W.2d 262, 267 (Tex. App—Fort Worth 1999, n.w.h.) (legal malpractice suit in which plaintiff was sanctioned for failure to make reasonable inquiry be......
  • Request a trial to view additional results