Christiansen Const. Co. v. A. J. Hiller Enterprises, Inc., 39337

Decision Date23 May 1974
Docket NumberNo. 39337,39337
Citation192 Neb. 37,218 N.W.2d 439
PartiesCHRISTIANSEN CONSTRUCTION CO., Appellee, v. A. J. HILLER ENTERPRISES, INC., Appellant.
CourtNebraska Supreme Court

Syllabus by the Court

It is well settled that a simple receipt is only prima facie evidence of the truth of the statements recited therein, and that oral evidence is admissible for the purpose of explaining, varying, or modifying its terms.

Michael A. Swanson, Lincoln, for appellant.

Moodie & Moodie, West Point, for appellee.

Heard before WHITE, C.J., and SPENCER, BOSLAUGH, McCOWN, NEWTON, CLINTON and BRODKEY, JJ.

SPENCER, Justice.

The sole issue presented in this appeal is whether a lien waiver which acknowledges receipt of the unpaid balance may be explained or contradicted by parol evidence. The trial court permitted the introduction of such evidence. We affirm.

Christiansen Construction Company, plaintiff, entered into a written contract with A. J. Hiller Enterprises, Inc., to construct a building for defendant in Norfolk, Nebraska. The total cost of the building was $68,364.61. On October 29, 1968, plaintiff made application for final payment of $6,963.91, and on the same date Norman Christiansen executed a waiver of lien which included an acknowledgment of receipt of the final payment due on the contract. On January 3, 1969, the architect executed a certificate for final payment. On June 2, 1969, George H. Moyer, as trustee, forwarded a check in the amount of $4,700 to apply on the balance due. No other payments were made and this action resulted.

Defendant answered plaintiff's petition with a general denial, and subsequently was allowed to amend its answer by pleading additionally that the amounts prayed for by the plaintiff had been fully paid on approximately the 29th day of October 1968. There is no evidence in the record except the receipt embodied in the lien waiver that the total amount due has been paid. The plaintiff and the architect testified that only $4,700 of the amount due has been paid.

The testimony indicated that the lien waiver was requested by the architect and was submitted by plaintiff at the architect's request. The record would indicate this is often done to permit the owner of a project to complete the financing. All the correspondence shown in the record indicated that the money had not been paid. Several of these letters were written by agents of the defendant and there is absolutely no indication or suggestion in any of them that the obligation of the defendant had been satisfied.

Plaintiff cites Waters v. Phelps (1908), 81 Neb. 674, 116 N.W. 783, for the...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT