City of Boulder v. Sherrelwood, Inc., s. 78-565

Decision Date21 June 1979
Docket NumberNos. 78-565,78-998,s. 78-565
Citation604 P.2d 686,42 Colo.App. 522
PartiesCITY OF BOULDER, Colorado, Plaintiff-Appellant, v. SHERRELWOOD, INC., Defendant-Appellee. . II
CourtColorado Court of Appeals

Steven D. Barnett, Acting City Atty., Jane W. Greenfield, Asst. City Atty., Boulder, for plaintiff-appellant.

Guy A. Hollenbeck, Boulder, for defendant-appellee.

PIERCE, Judge.

Plaintiff, the City of Boulder, appeals from the trial court's order construing a consent decree which plaintiff entered into with defendant, Sherrelwood, Inc. We affirm.

Defendant owns a tract of real property in the City of Boulder. In 1969, the City approved defendant's Planned Residential Development (PRD) and final site plan for the property, subject to the then-existing land use regulations and ordinances. The approval also provided that the project was to be completed by April 1974, though subsequent negotiations extended this date to July 1974.

Defendant's preliminary plat map was approved by the City engineer on May 2, 1973. In April of 1974, defendant requested a two year extension for the PRD, arguing that it had mistakenly construed the time limitation to mean only that construction on the project had to be Started by July 1974. The City's Planning Board denied the request for an extension on the grounds that defendant had failed to begin the project and that the PRD would violate certain zoning, subdivision, and land use regulations promulgated in 1971.

In May of 1974, the City filed a declaratory judgment action against defendant seeking a declaration that the PRD had expired. During the course of the trial, the parties agreed to resolve their dispute by requesting the trial court to enter a consent decree. The decree, entered in November of 1975, provided that the PRD was valid, and that defendant had a right to proceed with the project according to certain conditions and pursuant to a schedule attached to the decree. The schedule called for defendant to file a program development plan with the court by January 7, 1976, which plan was to include a description of all "reasonable and feasible" financing arrangements which defendant had made.

Defendant submitted its proposed program development plan within the time required by the consent decree, but the City filed objections to the plan, claiming that it violated time limitations contained in the decree. A series of hearings and orders followed, culminating in the trial court's order of April 20, 1978, which provided the following:

1) By June 14, 1978, defendant would file a loan commitment and an affidavit showing adequate financing to complete the project within 480 days of the start of construction.

2) Within five days of filing the above, defendant would file the subdivision plat and landscape plan with the City for its approval, after which the City would notify defendant if all of the conditions had been met for obtaining a building permit.

3) Within ten days of the above approval, defendant would file its building permit applications. Construction would be deemed to have "commenced" when the building permits for three specified units had been issued. Then defendant would, at least 15 days before construction of any succeeding unit, and according to the original time table attached to the decree, file its building permit for that unit.

The order further provided that should defendant fail to perform any of these obligations, the PRD would be immediately terminated.

I.

The City appeals from this order, arguing that the trial court erred in failing to rule that the consent decree contained a time limitation on the project, and therefore in failing to declare that the PRD had expired some time in 1978 for defendant's lack of adequate financing and failure to commence construction. Contrary to the City's arguments, we hold that the trial court's order properly effectuated the parties' intent as it was expressed in the consent decree.

The decree represents an agreement by the parties on two fundamental issues: 1) Defendant's PRD is valid and 2) defendant will be permitted to proceed with the project subject to the trial court's continued jurisdiction and active supervision. These two broad thrusts belie the City's argument that the decree should be interpreted as placing any fixed time limit on the completion of the project. It is true that Paragraph 3 of the decree states that defendant should be "restored to the same essential position and circumstances as existed . . . as of the date of the commencement of this litigation . . . ." And, while this language, standing alone, might lead to the conclusion that a time limit parallel to the original July 1974 limit was contemplated by the decree, language in the very same sentence indicates otherwise:

"(D)efendant (shall) be permitted to proceed with the construction of the approved project Pursuant to a court approved and supervised time schedule and development plan." (emphasis added)

We must review the consent decree as a whole, and look at all of its provisions and their interrelationships. See Crosby v. Gateway Motel, Inc., 163 Colo. 384, 431 P.2d 23 (1967). When viewed in this manner, it is clear that the decree vests a great deal of discretion in the...

To continue reading

Request your trial
2 cases
  • Warner Co. v. Sutton
    • United States
    • New Jersey Superior Court — Appellate Division
    • 24 Junio 1994
    ...Tp. Taxpayers Ass'n v. Summit Tp. Board of Supervisors, 49 Pa.Cmwlth. 459, 411 A.2d 1263, 1266 (1980); City of Boulder v. Sherrelwood, Inc., 42 Colo.App. 522, 604 P.2d 686, 689 (1979); Attman/Glazer P.B. Company v. Mayor and Aldermen of Annapolis, 314 Md. 675, 552 A.2d 1277, 1282-83 (1989);......
  • Leidy's, Inc. v. H2O Engineering, Inc., 90SC515
    • United States
    • Colorado Supreme Court
    • 20 Mayo 1991
    ...with Garrow v. Garrow, 152 Colo. 480, 382 P.2d 809 (1963), and decisions of the court of appeals in Boulder v. Sherrelwood, Inc., 42 Colo.App. 522, 525, 604 P.2d 686, 689 (1979), 2 and McNeece v. McNeece, 39 Colo.App. 160, 165, 562 P.2d 767, 770 (1977). In Garrow v. Garrow, 152 Colo. at 484......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT