City of New Haven v. Nat'l Steam Economizer Co.
Decision Date | 05 March 1907 |
Citation | 79 Conn. 482,65 A. 959 |
Parties | CITY OF NEW HAVEN v. NATIONAL STEAM ECONOMIZER CO. et al. |
Court | Connecticut Supreme Court |
Appeal from Superior Court, New Haven County; Milton A. Shumway, Judge.
Action by the city of New Haven against the National Steam Economizer Company and another to recover on a bond executed by defendant, with defendant the American Surety Company as surety. From a judgment on the bond, plaintiff and defendant American Surety Company both appeal. Affirmed.
November 11, 1901, the defendant the National Steam Economizer Company, as contractor, entered into a written contract with the plaintiff as owner to install certain heating and ventilating apparatus in the latter's high-school building for the contract price of $22,708. Article 10 of the contract provided that this contract price, subject to such additions and deductions as were provided for, should be paid to the contractor in monthly payments, to be made on the 15th day of each month, to the amount of 85 per cent. of labor and materials actually in place, upon certificates from the architects delivered to the owners on or before the 5th day each month, stating that the work has been done in accordance with the terms of the contract, that the final payment should be made within 10 days after the contract should be performed and the building accepted, and that all payments should be made upon written certificates of the architects to the effect that they had become due. Two of the articles read as follows:
Another article provided that all work to be done by the contractor should be seasonably done and as required by the specifications, and that the contractor was to have direction and superintendence of all work connected with the erection of its apparatus for the operation of which it was to be held responsible.
On November 15th said contractor, as principal, and the defendant the American Surety Company, as surety, entered into the bond in suit to the plaintiff in the penal sum of $15,000, conditioned that said contractor should faithfully and fully perform said contract. Prior to July 1, 1902, said contractor began work under said contract, and thereafter continued to prosecute it until December 27, 1902. At that date, the contractor not having prosecuted the work with diligence and being in default in the performance of its agreements, and the architects having given the required certificate, the plaintiff terminated the contractor's employment, entered upon the premises, took possession of the work and materials, and thereupon assumed charge of the work. Prior to this date the plaintiff had paid the contractor the sum of $14,516.76; the same having been paid in several installments, and all upon architects' certificates certifying that the several amounts paid were due. The following table shows the times and amounts of these payments and the dates of the architects' certificates pursuant to which each payment was made:
Dates of Certificates.
Date of Payment
Amount
July 1, 1902.
Sept. 11, 1902.
$1,892 70
Sept. 15, 1902.
Sept. 19, 1902.
2,190 30
Sept. 26, 1902.
Sept 27, 1902.
1,700 00
Oct 10, 1902.
Oct 15, 1902.
1,972 00
Nov. 5, 1902.
Nov. 7, 1902.
2,186 76
Nov. 28, 1902.
Nov. 28, 1902.
3,100 00
Dec. 20, 1902.
Dec 20, 1902.
Before the architects' certificates were issued, the contractor in each case submitted to the architects detailed statements or estimates of the work and labor claimed to have been furnished and to be in place, with the value thereof. These estimates were examined, and the actual cost to the contractor estimated as nearly as possible at current prices for the work and labor actually in place, and the certificates given were in each case for not more than 85 per cent. of such costs so determined. Some of the work required was electrical and mechanical apparatus, which could only be obtained from certain manufacturing companies dealing specially therein. The architects had no means of knowing or ascertaining, other than by inquiry of the contractor, or of said companies, at what price this apparatus could be or had been purchased, or what portion of the contract price was figured by the contractor therefor or for labor. It did not appear that such inquiry was made, save as already stated. In estimating, as stated, the probable cost of labor and materials actually in place, and in giving the certificates upon which payments were made, the architects acted in good faith and in the belief that the sums certified by them were no more than the contractor was entitled to receive under the terms of the contract, and said sums did not in fact exceed 85 per cent of the value of labor and materials actually in place at the time the several certificates were issued, at the probable actual cost to the contractor, as nearly as the same could then be ascertained by the architects in the manner aforesaid. On December 27th, when the contractor's employment was terminated, between one-third and one-half only in value of the total work required by the contract was completed. On January 16, 1903, the plaintiff employed another corporation to complete the work required by the contract, which was thus completed June 29, 1903. Under this employment the plaintiff paid $21,022.83 to the new company, of which about $600 was for the removal and replacement of defective work. On July 27, 1903, the architects audited said payments, and gave a certificate that the expense incurred by the plaintiff in the completion of the work was truly shown thereby.
Judgment was rendered for the excess of the total payments made by the plaintiff as aforesaid over and above the contract price of $22,798.
Leonard M. Daggett and James Kingsley Blake, for plaintiff. George D. Watrous and Henry P. Parmelee, for defendant the American Surety Company.
PRENTICE, J. (after stating the facts). Confessedly the defendant surety company, as the surety...
To continue reading
Request your trial-
City of Montpelier v. National Surety Co
... ... Equitable ... Surety Co. , 269 Pa. 411, 112 A. 551; New Haven ... v. National Steam Economizer Co. , 79 Conn. 482, 65 ... A. 959; ... ...
-
City of Montpelier v. Nat'l, 448.
...Pa. 208, 80 Atl. 62, Ann. Cas. 1912B, 1085; M. E. Church v. Equitable Surety Co., 269 Pa. 411, 112 Atl. 551; New Haven v. National Steam Economizer Co., 79 Conn. 482, 65 Atl. 959; Guaranty Co. v. Pressed Brick Co., 191 U. S. 416, 24 Sup. Ct. 142, 48 L. Ed. 242; Cambridge Sav. Bk. v. Hyde, 1......
-
Sanders v. Keller
... ... Law Rep. 926, 111 S.W. 686; New ... Haven v. Nat. Steam Economizer Co., 79 Conn. 482, 65 A ... 959; ... ...
-
National Loan & Exchange Bank of Greenwood v. Gustafson
... ... as for labor. The court held that it did; that the city was ... interested in the protection of both laborers and ... 766; 9 ... C.J. 794, § 135; City of New Haven ... C.J. 794, § 135; City of New Haven v. National Steam ... ...