Sanders v. Keller

Decision Date04 October 1910
PartiesW. T. SANDERS, Doing Business Under the Firm Name and Style of RUBY CREEK LUMBER CO., Appellant, v. MINNIE KELLER et al., Respondents
CourtIdaho Supreme Court

BUILDING CONTRACT-SURETY-MATERIALMAN'S LIEN-WAIVER OF LIEN BY SURETY-ADMISSION OF PRINCIPAL BINDING ON SURETY.

(Syllabus by the court.)

1. Where S. subscribes his name to a contract executed by B. and K., and no mention of S.'s name appears in the body of the contract and no reference to his liability is made in the contract, held, that S. signed as surety and should be held as such.

2. Where a building contract was indefinite or uncertain in certain particulars and the principal obligor placed his own construction and interpretation on the contract and erected the building in accordance therewith, and there does not appear to have been any fraud or collusion between the contractor and the owner of the building, held, that the surety will be bound by the construction placed on the contract by his principal.

3. The surety for a contractor on a building contract cannot maintain an action for the foreclosure of a lien for materials furnished in the carrying out of the contract and erection of the building, where it appears that the full contract price has been paid to the contractor, or on his order, prior to any claim being made by the surety or notice being given to the owner of the building.

4. An admission made by the contractor in the course of the performance of his contract or upon the completion thereof as to having no claims for extras against the owner of the building, held, admissible against the surety in an action where the surety seeks to foreclose a materialman's lien for materials furnished in the construction of the building.

APPEAL from the District Court of the Third Judicial District in and for Ada County. Hon. Fremont Wood, Judge.

Action by the plaintiff to foreclose a materialman's lien. Judgment for defendant and plaintiff appealed. Affirmed.

Judgment affirmed, with costs in favor of respondent.

William B. Davidson, and Harry Keyser, for Appellant.

A covenant against liens must be an expressed covenant, or must arise as a necessary implication from the language employed. (Miles v. Coutts, 20 Mont. 47, 49 P. 393; Nice v. Walker, 153 Pa. 123, 34 Am. St. 688, 25 A. 1065; Aste v. Wilson, 14 Colo. App. 323, 59 P. 846; Blyth v. Torre (Cal.), 38 P. 640.)

If the bond is void from the beginning, or has been discharged by the act of the owner, the sureties may assert mechanics' liens on their own behalf. (Boisot Mech. Liens, sec. 753; Deitz v. Leete, 28 Mo.App. 540; Hartman v. Berry, 56 Mo. 487.)

No estoppel can exist against appellant's claim of lien in this case, for even though he signed the bond as surety, he has been released by the act of the principal and owner. ( Oneale v. Long, 4 Cranch, 60, 2 L.Ed. 550; Leggett v. Humphreys, 21 How. 66, 16 L.Ed. 50; United States v. Tillotson, 1 Paine, 305, F. Cas No. 16,524; Smith v. United States, 2 Wall. 219, 17 L.Ed. 788; McMicken v. Webb, 6 How. 292, 12 L.Ed 443; United States v. Boyd, 15 Pet. 187, 10 L.Ed. 706.)

The surety is released by material alteration of the contract between the principal and the owner, to which he has not consented. (2 Brandt, Suretyship and Guaranty, sec. 747, and the cases there cited; Barrett-Hicks Co. v. Glas, 9 Cal.App. 491, 99 P. 856.)

Richards & Haga, for Respondents.

While appellant in the case at bar is not named in the body of the contract, he is nevertheless as firmly bound as if he were named therein. (Thompson v. Coffman, 15 Ore. 631, 16 P. 713; Pequawkett Bridge v. Mathes, 7 N.H. 230, 26 Am. Dec. 737; Smith v. Crooker, 5 Mass. 538; Holmes v. State, 17 Neb. 73, 22 N.W. 232; Leith v. Bush, 61 Pa. 395; Scheid v. Leibshultz, 51 Ind. 38; General Electric Light Co. v. Gill, 127 F. 241, 129 F. 349.)

When the owner of a building has paid the contractor the amount due on the contract, the contractor's surety is not entitled to foreclose a lien for materials furnished the contractor in carrying out his contract. (McHenry v. Knickerbocker, 128 Ind. 77, 27 N.E. 430; Rynd v. Pittsburg Natatorium, 173 Pa. 237, 33 A. 1041; 2 Brandt, Suretyship and Guaranty, sec. 754, and authorities cited; Blyth v. Robinson, 104 Cal. 239, 37 P. 904; Kent Lumber Co. v. Ward, 37 Wash. 60, 79 P. 485; Ganahl v. Weir, 130 Cal. 237, 62 P. 512; Dietz v. Leete, 28 Mo.App. 540; Stephens v. Elver, 101 Wis. 392, 77 N.W. 737; Kiewit v. Carter, 25 Neb. 460, 41 N.W. 286; Eakins v. Frank, 21 Mont. 192, 53 P. 538.)

Before a surety is released from performance of his contract or from liability as surety, he must show that the change in the contract is material and substantial. (Stephens v. Elver, supra; Grafton v. Hinkley, 111 Wis. 46, 86 N.W. 859; 1 Brandt, Suretyship and Guaranty, sec. 445; Cooke v. School Dist., 33 Ky. Law Rep. 926, 111 S.W. 686; New Haven v. Nat. Steam Economizer Co., 79 Conn. 482, 65 A. 959; Benjamin v. Hillard, 64 U.S. 149, 16 L.Ed. 518; Harper v. Nat. Life Ins. Co., 56 F. 281, 5 C. C. A. 505; Fertig v. Bartles, 78 F. 867; Hooper v. Hooper, 81 Md. 174, 48 Am. St. 509, 31 A. 508; Anderson v. May, 10 Heisk. 87; United States v. Freel, 92 F. 301; Cambria Iron Works v. Keynes, 56 Ohio St. 501, 47 N.E. 548; United States v. Walsh, 115 F. 697, 52 C. C. A. 419; Dorsey v. McGee, 30 Neb. 657, 46 N.W. 108; Prescott Nat. Bank v. Head (Ariz.), 90 P. 328; Fuller Co. v. Doyle, 87 F. 687; United States v. Hodge, 6 How. 279, 12 L.Ed. 437.)

Admissions of principal are binding on surety. (2 Wigmore, Evidence, sec. 1077; Jones on Evidence, sec. 239; Elliott on Evidence, sec. 253.)

AILSHIE, J. Sullivan, C. J., concurs.

OPINION

AILSHIE, J.

This action was instituted to foreclose a materialman's lien. A contract was entered into between J. W. Brown and the respondent, Minnie Keller, whereby Brown agreed to furnish all material and construct and complete a dwelling-house according to the draft thereto annexed. The draft annexed to the contract was a drawing and diagram of the floor plan of a dwelling-house, showing the dimensions of the various rooms, doors, windows, etc. In addition to being signed by Brown and Keller, the contract was also signed by W. T. Sanders, the appellant, and one N.H. Hon. No mention was made of the names of Sanders and Hon or of their liability in the body of the contract. It was therefore contended by the respondent, and it was found and held by the trial court, that Sanders and Hon were sureties on the contract. Of the correctness of this holding there can be but little room for doubt. ( Thompson v. Coffman, 15 Ore. 631, 16 P. 713; Neil v. Morgan, 28 Ill. 524; Holmes v. State, 17 Neb. 73, 22 N.W. 232; Leith v. Bush, 61 Pa. 395.)

The contract was signed by Brown and the sureties prior to its submission to and execution by Mrs. Keller. Sanders says that he did not see or examine any exhibits of plans or specifications attached to the contract. The contract itself is vague and uncertain as to the character of building to be constructed and of the manner of construction and detail in general. Brown erected the building, and in doing so apparently procured most of the lumber from his surety, Sanders. Brown placed his own construction and interpretation on the contract, and apparently built the building in accordance with this understanding of the purpose and intent of the contract. Several changes were made from that indicated by the draft and crude specifications attached to the contract. Brown was not present at the trial and did not testify in the case. Mrs. Keller testified that only one change was made by Brown at her instance and request, and that she paid Brown the extra charge for that change over and above the contract price. She also paid a plumber for a change in the plumbing.

About the time of the completion of this work, and when Mrs. Keller was making final settlement for the contract, she procured from Brown a written statement to the effect that he had no charges against her for extras on account of building the house, except for five dollars for putting in a door in place of a window. She thereupon paid the extra five dollars, and paid either to Brown directly or to his order laborers and materialmen the full contract price. Appellant thereafter filed his lien for materials furnished.

The evidence in the case fully sustains the findings made by the trial court to the effect that whatever changes were made in the construction of this building, except as to a door, were made by the contractor himself on his own motion. The record is quite clear to the effect that the building was constructed by the contractor upon his own interpretation and construction of the requirements of the contract and the plans and specifications which accompanied the same. It must be conceded that the contract and plans and specifications were extremely meager and left a great deal to be implied. The appellant, however, as surety for the contractor, should in the absence of a showing of any fraudulent agreement or collusion between the contractor and respondent, be held to the construction and interpretation placed on the contract by appellant's principal, the contractor. The surety signed the contract for a purpose, and he...

To continue reading

Request your trial
3 cases
  • Wilson v. Locke
    • United States
    • Idaho Supreme Court
    • 4 Octubre 1910
  • Weeter Lumber Co. v. Fales
    • United States
    • Idaho Supreme Court
    • 28 Septiembre 1911
    ...v. Nickerson, 13 Idaho 682, 93 P. 24; see, also, Steltz v. Armory Co., 15 Idaho 551, 99 P. 98, 20 L. R. A., N. S., 872; Sanders v. Keller, 18 Idaho 590, 111 P. 350; Jones v. Balsley, 27 Okla. 220, 111 P. Smith v. Wilcox, 44 Ore. 323, 74 P. 708, 75 P. 710; Beach v. Stamper, 44 Ore. 4, 102 Am......
  • Smith v. Easter
    • United States
    • Kansas Supreme Court
    • 10 Marzo 1917
    ...liens filed, exceeds the contract price for both buildings by more than the amount of Agard's claim. A similar case is Sanders v. Keller, 18 Idaho 590, 111 P. 350. the court said: "It is a well-established rule of law that the surety for a contractor on a building contract can not maintain ......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT