Commercial Standard Ins. Co. v. United States
Decision Date | 15 May 1954 |
Docket Number | No. 4766.,4766. |
Parties | COMMERCIAL STANDARD INS. CO. v. UNITED STATES for Use of CRANE CO. |
Court | U.S. Court of Appeals — Tenth Circuit |
C. J. Watts, Oklahoma City, Okl. (Looney, Watts, Ross, Looney & Nichols, Oklahoma City, Okl., on the brief), for appellant.
J. B. McClelland, Jr., Oklahoma City, Okl. (Bruce McClelland, L. G. Kneeland, and Robert O. Bailey, Oklahoma City, Okl., on the brief), for appellee.
Before BRATTON, HUXMAN and PICKETT, Circuit Judges.
Crane Co., a corporation, as use plaintiff, brought this action against O. K. Sprinkler and its surety, Commercial Standard Insurance Company, to recover the balance due for materials furnished Sprinkler under a contract with the United States. The bond of the surety was required by the Miller Act, 40 U.S. C.A. § 270a. The trial court held that the material was used in the prosecution of the work provided for in the contract and was covered by the bond. The question presented on appeal is whether such a bond covers material which was furnished to a contractor and which was not actually used in the performance of a contract, but which replaced identical material taken from the contractor's inventory and used on the contract job.
The material facts are not in dispute. In August, 1951, Sprinkler entered into a contract for the installation of an automatic sprinkler system in government buildings at Ft. Sill, Oklahoma. For the purpose of acquiring materials to complete the job, the contract was assigned a priority rating by the National Production Authority. Sprinkler placed an order for a quantity of black steel pipe with Crane. Relying upon the priority order, Crane agreed to fill the order. The purchase order showed that the pipe was to be used in the Ft. Sill contract and that it was to be shipped to the Field Office Location of Sprinkler in Oklahoma City, Oklahoma. Sprinkler maintained its shop in Oklahoma City where it kept an inventory of materials including the identical kind of pipe which it ordered from Crane. All material for the Ft. Sill job was to be fabricated in the Oklahoma City shop. Before the Crane pipe was delivered, Sprinkler, for its own convenience, took pipe from its inventory, fabricated it to meet the specifications of its contract, and then transported it to Ft. Sill where it was installed in the performance of the contract. A short time later, Crane delivered the pipe pursuant to the order, which was of the same kind, grade and quantity installed by Sprinkler in accordance with the plans and specifications of the contract job. When the order arrived, Sprinkler put the pipe in its inventory to replace that which had been taken out to complete the contract. Under these facts, Commercial urges that the material was not furnished in the prosecution of the work provided for in the contract, and that there can be no recovery under the Miller Act bond.
The relevant provisions of the Miller Act are:
The provisions of the Miller Act are to be liberally construed to carry out its purposes. In Standard Accident Insurance Co. v. United States, for Use and Benefit of Powell, 302 U.S. 442, 444, 58 S.Ct. 314, 315, 82 L.Ed. 350, it was said in referring to this Act: "And we are committed to the doctrine that it should be liberally construed in aid of the evident public object — security to those who contribute labor or material for public works".1 See also Clifford F. MacEvoy Co. v. United States, 322 U.S. 102, 64 S.Ct. 890, 88 L.Ed. 1163; Brogan v. National Surety Co., 246 U.S. 257, 38 S.Ct. 250, 62 L.Ed. 703; Illinois Surety Co. v. John Davis Co., 244 U.S. 376, 37 S.Ct. 614, 61 L.Ed. 1206; United States Fidelity and Guaranty Co. v. United States ex rel. Bartlett, 231 U.S. 237, 34 S.Ct. 88, 58 L.Ed. 200; Title Guaranty & Trust Co. of Scranton, Pa. v. Crane Co., 219 U.S. 24, 31 S.Ct. 140, 55 L.Ed. 72; Glassell-Taylor Co. v. Magnolia Petroleum Co., 5 Cir., 153 F.2d 527. These cases also recognize the rule that the Miller Act does not require that the labor or material which has been furnished be actually used in or incorporated into the contract work. A recovery is permitted when the work or materials have been "furnished * * * in the prosecution of the work".2
In Glassell-Taylor Co. v. Magnolia Petroleum Co., supra, the Fifth Circuit carried the rule a step further. It was there held that where the use plaintiff in good faith supplied the contractor with materials indispensable to the...
To continue reading
Request your trial-
United States v. Fire Association of Philadelphia
...inventory expended in the performance of the bonded contract, it has been conclusively rejected. Commercial Standard Ins. Co. v. United States, for Use of Crane Co., 10 Cir., 213 F.2d 106; Glassell-Taylor Co. v. Magnolia Petroleum Co., 5 Cir., 153 F.2d 527; Montgomery v. Unity Electric Co.,......
-
Fanderlik-Locke Co. v. United States
...Indem. Co. v. United States, 10 Cir., 238 F.2d 917; Fourt v. United States, 10 Cir., 235 F.2d 433; Commercial Standard Ins. Co. v. United States, 10 Cir., 213 F.2d 106. The benefits of the Act are not intended for the prime contractor who is required by the Act to furnish a bond to effectua......
-
United States v. Malan Construction Corporation
...137; United States for Use and Benefit of Jones Contracting Co. v. Skilken, D.C. N.D.Ohio, 53 F.Supp. 14; Commercial Standard Insurance Co. v. United States, 10 Cir., 213 F.2d 106; and United States ex rel. Crowder v. Fidelity & Deposit Company of Maryland, D.C.W.D.La., 144 F.Supp. This is ......
-
TF Scholes, Inc. v. United States, 6650.
...the effectuation of such purpose. MacEvoy Co. v. United States, 322 U.S. 102, 64 S.Ct. 890, 88 L.Ed. 1163; Commercial Standard Insurance Co. v. United States, 10 Cir., 213 F.2d 106; St. Paul-Mercury Indemnity Co. v. United States, 10 Cir., 238 F.2d Not having any contractual relationship wi......