SOGNIER, Chief Judge.

Haygood Contracting, Inc. filed suit against Cherokee Falls Investments, Inc. (CFI) and William L. Crolley to recover amounts allegedly owed on a construction contract. CFI answered and filed a counterclaim arising from another construction contract, and Crolley filed an answer denying individual liability. The trial court granted partial summary judgment against Crolley and CFI, and they appeal.

This dispute arises from a contract executed on July 6, 1989, for paving work to be performed by appellee at Chota Hills Subdivision in Cherokee County. The contract comprises a standardized form prepared by appellee with the owner's name, scope of work, and contract price typed in blank spaces on the form. The name "Chota Hills Subdivision" appears in the blank spaces designated for "proposal submitted to" and "job name." The contract was signed by appellant Crolley with no indication of corporate office or title. Appellant CFI's name does not appear on the form. Crolley testified by deposition that he is a majority stockholder and director of CFI, a corporation engaged in the business of buying and selling real estate, and that Chota Hills Subdivision is a residential subdivision owned by CFI. He deposed that he executed the contract at issue on behalf of CFI. Conversely, Scott Coile, appellee's superintendent, deposed that he understood appellee was dealing with Crolley personally.

The contract form specified a price of $29,345 for the work. In October 1989, Crolley and Coile discussed the need for additional work to be performed because of poor soil conditions in some areas of the roadway. Coile testified that he prepared a handwritten estimate indicating that this work would cost $7,275, which Crolley admits initialling on October 6. On the copy of this document entered in the record, there appear below Crolley's initials additional notations delineating $500 for "equipment time" and $7,560 for "extra stone." Coile deposed that these notes were added by appellee's office staff after Crolley initialled the document.

After the parties became embroiled in a dispute over the quality of appellee's performance and the liability of appellants for the extra work, appellee filed this action to recover the contract price plus all amounts shown on the above-referenced document for additional work. The trial court granted partial summary judgment against both appellants for the original contract price, $29,345, plus $7,275 for extra work.

1. Appellants contend the trial court erred by awarding appellee $7,275 for extra work because the contract required a written change order and a fact question remains concerning appellants' authorization of this work and their waiver of the written change order requirement. This enumeration is without merit, as the handwritten proposal prepared by appellee's representative and initialled by appellant Crolley described the work to be performed and stated a sum certain for the performance of the work, and accordingly satisfied the contract change order requirement.

2. Appellants next maintain the grant of summary judgment to appellee on the contract claim was erroneous because it ignored CFI's pending counterclaim. We agree with appellants that the decision in Mock v. Canterbury Realty Co., 152 Ga.App. 872(1), 264 S.E.2d 489 (1980) controls this issue, but we do not agree that Mock requires reversal of the summary judgment entered on a portion of appellee's complaint. The Mock court rejected the notion that summary judgment could not be entered in a case with a valid pending counterclaim, holding instead that the trial court may consider the motion for summary judgment on its merits, weigh the equities of the situation, and grant summary judgment to eliminate extraneous issues from the trial, and yet preserve the counterclaim plaintiff's rights by not issuing final judgment until the counterclaim is concluded. Id. at 878-879, 264 S.E.2d 489. Accordingly, we hold the trial court did not err by holding appellee was entitled to partial summary judgment. See Shedd v. Goldsmith Chevrolet, 178 Ga.App. 554, 556(2), 343 S.E.2d 733 (1986).

3. Finally, appellant Crolley contends the trial court erred by finding him individually liable to appellee, arguing that a fact question remains concerning whether he executed the contract in his representative capacity. Both parties have cited cases decided under Article 3, Section 3-403 of the Uniform Commercial Code (OCGA § 11-3-403). However, Article 3 applies only to negotiable instruments, Barton v. Scott Hudgens Realty, 136 Ga.App. 565, 566, 222 S.E.2d 126 (1975), and the contract at issue does not so qualify. The contract was not a negotiable instrument as defined in OCGA § 11-3-104(1) because it was not "payable on demand or at a definite time," id. at (c), but was "payable only upon an act or event uncertain as to time of occurrence," OCGA § 11-3-109(2)--i.e., when the work was performed. See Barton, supra. Accordingly, we must apply general common law principles rather than the UCC.

Appellant Crolley contends that "Chota Hills Subdivision" is a trade name of CFI, and thus the presence of this CFI trade name on the face of the contract created a fact question concerning whether the principal, CFI, was disclosed to appellee. " 'Where an agent wishes to avoid personal liability, the duty is on him to disclose his agency, and not on the party with whom he deals to discover it'.... [Cits.]" Brown-Wright, etc., Corp. v. Bagen, 112 Ga.App. 300, 302, 145 S.E.2d 294 (1965). Whether the "fact of the agency and identity of the principal were disclosed or known to the other contracting party is a question of fact which may be shown by direct or circumstantial evidence. [Cit.]" Fletcher Emerson, etc., Co. v. Davis, 134 Ga.App. 699, 700-701(1), 215 S.E.2d 725 (1975). On motion for summary judgment, appellee, the movant, had the burden of proving its "lack of knowledge that [Crolley] was acting as an agent [for CFI]." Id. at 701(3), 215 S.E.2d 725.

...

To continue reading

Request your trial
16 cases
  • Security Life Ins. Co. v. St. Paul Fire & Marine Ins. Co., A03A0843.
    • United States
    • Georgia Court of Appeals
    • 3 Octubre 2003
    ...was granted against both defendants. While Crolley's right to partial summary judgment was affirmed by Crolley v. Haygood Contracting, 201 Ga.App. 700, 411 S.E.2d 907 (1991), on remand, Crolley was required to select one of the two defendants against whom judgment was entered and postjudgme......
  • Redi-Floors, Inc. v. Sonenberg Co., A01A1841.
    • United States
    • Georgia Court of Appeals
    • 29 Marzo 2002
    ...are not necessarily sufficient so as to protect the agent from liability. Wojcik, supra, 204 Ga.App. at 304(2), 419 S.E.2d 135; Crolley v. Haygood Contracting.6 "The disclosure of an agency is not complete for the purpose of relieving the agent from personal liability unless it embraces the......
  • Odyssey Travel Center, Inc. v. Ro Cruises, Inc.
    • United States
    • U.S. District Court — District of Maryland
    • 9 Mayo 2003
    ...is not sufficient disclosure of the identity of the principal and of the fact of agency). Similarly, in Crolley v. Haygood Contracting, Inc., 201 Ga.App. 700, 411 S.E.2d 907, 909 (1991), the court stated [w]hile the fact that a trade name was used is a factor to be considered on the issue o......
  • Miles Rich Chrysler-Plymouth, Inc. v. Mass, CHRYSLER-PLYMOUT
    • United States
    • Georgia Court of Appeals
    • 31 Octubre 1991
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT