D. Wilson Const. Co., Inc. v. McAllen Independent School Dist., 13-92-422-CV

Decision Date31 December 1992
Docket NumberNo. 13-92-422-CV,13-92-422-CV
Citation848 S.W.2d 226
Parties81 Ed. Law Rep. 1138 D. WILSON CONSTRUCTION CO., INC., Appellant, v. McALLEN INDEPENDENT SCHOOL DISTRICT, Appellee.
CourtTexas Court of Appeals

Roger W. Hughes, Leo C. Salzman, Adams & Graham, Harlingen, for appellant.

Travis Hiester, Charles W. Hury, Kristen Clark, Atlas & Hall, McAllen, for appellee.

Before DORSEY, KENNEDY and SEERDEN, JJ.

OPINION

DORSEY, Justice.

This is an interlocutory appeal from a trial court's refusal to compel arbitration of a construction contract. Wilson Construction Company contracted with McAllen Independent School District to build certain improvements for the District. A dispute under the contract arose between the parties, and the construction company sought arbitration. The trial court refused to refer the matter to arbitration and this appeal resulted.

Appellant relies on two statutes to compel arbitration: the Federal Arbitration Act, 9 U.S.C.A. § 1, et seq. (West 1970 & Supp.1991) and the Texas Arbitration Act, TEX.REV.CIV.STAT.ANN. art. 224, et seq. (Vernon 1973 & Supp.1993). Texas Courts of Appeals obtain their jurisdictional authority to hear appeals from interlocutory orders from statutes. While the Texas Arbitration Act authorizes interlocutory appeals to Texas Courts, the Federal Act cannot. We have no jurisdiction to review by appeal an order denying arbitration under the Federal Act. Jack B. Anglin Co., Inc. v. The Honorable Arthur Tipps, 842 S.W.2d 266, 271-73 (1992). A party must seek a writ of mandamus to complain of a stay of arbitration when rights under the Federal Arbitration Act are asserted. Accordingly, all points of error founded on the right to compel arbitration under the Federal Arbitration Act are overruled for want of jurisdiction.

Our review of the court's order will be based on the application of the Texas Arbitration Act.

In 1987, the School District planned to build a new facility that included a gymnasium and an indoor swimming pool. The District hired Rike-Ogden, an architectural firm, to design the facility. Rike-Ogden placed a construction contract, with building specifications, up for public bid; Wilson responded with the winning bid. The parties entered into a contract and Wilson began construction.

The School District approved a certificate of substantial completion for the gymnasium and swimming pool facility on October 23, 1990. Soon thereafter, the School District found deficiencies and attempted to resolve these with Wilson. The parties were unable to resolve the problems concerning the swimming pool, although discussions continued from October 1990 to October 1991. The School District filed suit against Rike-Ogden, Wilson, and others as a result of the deficiencies in construction. Wilson filed a plea in abatement, contending that the contract it entered into with the School District contained an arbitration agreement and that the case should be disposed of accordingly.

The School District moved to stay arbitration and Wilson moved to compel. After a hearing, the trial court denied Wilson's motion and granted the District's. Wilson appeals from these actions.

The central issue on appeal is the validity of the arbitration provisions in the contract between Wilson and the School District. The construction contract consisted of several separate documents. That document calling for arbitration of disputes was entitled "General Conditions." The District maintains that it never received the General Conditions document and that Wilson never discussed arbitration when the parties negotiated the contract. On this basis, the District contends that it did not agree to those arbitration provisions and cannot be held to them. In the alternative, the School District contends that the agreement is invalid or unenforceable because it is contained in a document incorporated into the contract, that fraud, estoppel, and/or waiver apply to bar the arbitration, and that Wilson's act of including the arbitration agreement into the contract was unconscionable.

A written agreement to submit a controversy to arbitration is valid, enforceable, and irrevocable unless grounds for revocation of the contract in law or in equity arise. TEX.REV.CIV.STAT.ANN. art. 224 (Vernon Supp.1993). Moreover, any agreement to submit a controversy to arbitration that is unconscionable at the time the agreement was made is not enforceable. TEX.REV.CIV.STAT.ANN. art. 224. When one party moves to compel arbitration and the other party refuses, the court shall order arbitration; however, if the opposing party denies the existence of an arbitration agreement, the court shall determine the existence of such an agreement and compel arbitration if one is found or deny it if one is not so found. TEX.REV.CIV.STAT.ANN. art. 224 (Vernon 1973).

By its first three points of error, Wilson contends that the trial court erred by staying arbitration and refusing to compel it because the agreement is valid and enforceable. By point six, Wilson contends that no evidence of fraud, estoppel, or waiver exists so as to bar enforcement of the arbitration agreement. By point eight, Wilson maintains that there is no evidence that its act of including the arbitration agreement into the contract was unconscionable.

Under the Texas Arbitration Act, if grounds exist at law or in equity to revoke the contract, or if the arbitration provision is deemed unconscionable, arbitration must not proceed. TEX.REV.CIV.STAT.ANN. art. 224. Applying this mandate, the District essentially contends that no agreement to arbitrate existed here, and that Wilson's inclusion of the arbitration provision in this agreement was unconscionable.

The creation of the District's contract with Wilson is critical here. The District invited Rike-Ogden to be the architect on this project. The contract between the two provided that the architect would prepare, for approval by the District, drawings and specifications for the construction of the new facility, including the necessary bidding information. The architect would also assist the District in the preparation of bidding forms, the Conditions of the Contract, and the form of the agreement between the District and the contractor.

Dan Ogden, the architect principally involved in this project, consulted with Clyde Lyons, the Assistant Superintendent for Business for the School District, dozens of times in the course of preparing the drawings and specifications for this project. Lyons was the person with the primary responsibility within the school district for producing the construction contract in final form. The specifications portion of the contract expressly made reference to "General Conditions" applicable to all phases of the contract and construction. Article Four of these General Conditions, "Administration of the Contract," contains an extensive Arbitration provision, section 4.5. This section discusses the controversies and claims subject to arbitration, when it may be demanded, rules and notices for arbitration, and the like.

Ogden testified that during his frequent discussions with Lyons, Lyons never told him to delete the arbitration provision from the contract. Lyons contends that this is because he never received the General Conditions and therefore was not aware of the arbitration provision. However, he conceded that he did not read the entire proposed contract and never requested a copy of the General Conditions from Rike-Ogden. Nevertheless, he approved the format of the contract and allowed Rike-Ogden to issue it to proposed bidders and contractors.

Lyons stated that when that contract was returned to him, completed by Wilson, although it made reference to the General Conditions of the contract, he did not request or read them. He reviewed the document only to assure that the blanks were properly filled in.

Lyons then sent the contract to the School District's attorney, Travis Heister. Heister, too, reviewed the Wilson/School District contract only to ensure that the blanks were properly filled in. He stated that he did not request or read the General Conditions section of this contract.

Nevertheless, the School District approved the contract documents as prepared by Rike-Ogden and submitted by Wilson, ultimately signing the contract. The District now argues that although the incorporation of General Conditions into this contract is clearly designated on the face of the document, because it never received the General Conditions document, it cannot be bound by the contents of that document. Further, it maintains that any inclusion of the arbitration clause into this contract was unconscionable.

As a general rule, a party who signs a contract is presumed to know its contents; absent a finding of fraud, its failure to read the contract will not discharge its obligations. Eubank v. First Nat'l Bank of Bellville, 814 S.W.2d 130, 134 (Tex.App.--Corpus Christi 1991, no writ); Nautical Landings Marina v. First Nat'l Bank in Port Lavaca, 791 S.W.2d 293, 298 (Tex.App.--Corpus Christi 1990, writ denied); Williams v. Adams, 696 S.W.2d 156, 159 (Tex.App.--Houston [14th Dist.] 1985, writ ref'd n.r.e.). Parties to a contract have an obligation to protect themselves by reading what they sign. G-W-L, Inc. v. Robichaux, 643 S.W.2d 392, 393 (Tex.1982); Thigpen v. Locke, 363 S.W.2d 247, 254 (Tex.1962). This Court has held that a party who signs a contract is charged with notice of its contents as a matter of law. Estate of Degley v. Vega, 797 S.W.2d 299, 304 (Tex.App.--Corpus Christi 1990, no writ).

In this case, the School District is complaining about the contract it prepared. The District attempts to transform its failure to request and review a portion of its contract into an act of deceit and trickery on Wilson's part. The District cannot assert that it was fraudulently induced to accept its own contract provisions or that Wilson should be estopped...

To continue reading

Request your trial
42 cases
  • In re Enron Corp. Securities, Derivative
    • United States
    • U.S. District Court — Southern District of Texas
    • August 1, 2005
    ...Darren Casey Interests, Inc., 46 S.W.3d 417, 420 (Tex.App. — Austin 2001), citing D. Wilson Constr. Co. v. McAllen Indep. Sch. Dist., 848 S.W.2d 226, 240 (Tex.App. — Corpus Christi 1992, writ dism'd w.o.j.). 46. As noted, AEGIS' choice-of-law provision applies the law of the "jurisdiction i......
  • GXG, Inc. v. Texacal Oil & Gas
    • United States
    • Texas Court of Appeals
    • June 18, 1998
    ...signs a contract is charged with notice of its contents as a matter of law. D. Wilson Const. Co., Inc. v. McAllen Indep. Sch. Dist., 848 S.W.2d 226, 229-30 (Tex.App.--Corpus Christi 1992, writ dism'd w.o.j.); Estate of Degley v. Vega, 797 S.W.2d 299, 304 (Tex.App.--Corpus Christi 1990, no w......
  • Vireo, P.L.L.C. v. Cates
    • United States
    • Texas Court of Appeals
    • September 11, 1997
    ...have substantially invoked the judicial process to the opposing party's detriment. D. Wilson Constr. Co. v. McAllen Indep. Sch. Dist., 848 S.W.2d 226, 230 (Tex.App.--Corpus Christi 1992, writ dism'd w.o.j.). The party opposing arbitration bears the burden of proof to show it has suffered pr......
  • Halliburton Energy Servs., Inc. v. Ironshore Specialty Ins. Co.
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • April 17, 2019
    ...w.o.j.) ; see also In re FirstMerit Bank, N.A. , 52 S.W.3d 749, 753 (Tex. 2001) ; D. Wilson Constr. Co., Inc. v. McAllen ISD , 848 S.W.2d 226, 231 (Tex. App.—Corpus Christi 1992, writ dism’d w.o.j.). But that presumption does not govern when the parties dispute who determines arbitrability.......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT