Dalhoff Construction Company v. Maurice
Decision Date | 27 April 1908 |
Citation | 110 S.W. 218,86 Ark. 162 |
Parties | DALHOFF CONSTRUCTION COMPANY v. MAURICE |
Court | Arkansas Supreme Court |
Appeal from Arkansas Chancery Court; John M. Elliott, Chancellor reversed.
Judgment reversed and cause remanded.
H. F Auten, for appellant.
Pugh & Wiley, for appellee.
Maurice filed suit in chancery court against the Dalhoff Construction Company, the St. Louis, Iron Mountain & Southern Railway Company and Martin & Boyd, seeking to recover under a contract between Maurice and the Dalhoff Construction Company, and also for material furnished Martin & Boyd, which it was alleged the Dalhoff Construction Company assumed the payment of, and to enforce a lien against the railway company.
The Iron Mountain Railway Company was building a line of railroad in the eastern part of the State, crossing the Arkansas and White rivers near their mouths, and the Dalhoff Construction Company was the contractor. Maurice was a subcontractor under the construction company on trestle work between the Arkansas and White rivers. Maurice sued the construction company, and obtained judgment and a lien on the railroad. This is an appeal by the construction company as to three items allowed, and a cross appeal by Maurice for one item disallowed.
The first item is for $ 1,891.68 for putting on 7,882 lineal feet of capping at 24 cents per lineal foot. So much of the contract as is material to that point reads as follows:
Maurice contended, and was sustained by the chancery court, that he should have twenty-four cents per lineal foot for placing the caps on the piling. The construction company contends that the twenty-four cents included driving and capping the piles, as well as furnishing them. Each party has produced evidence tending to corroborate his theory, but the question depends upon a construction of the contract, and testimony of what was done under it could not be considered unless it was ambiguous. When this testimony is turned to to aid the construction of the contract, it is found to be conflicting, and there is little, if any, light thrown upon the question by it. The contract is not ambiguous, but stipulates that Maurice was to furnish the piles and drive and cap them for twenty-four cents per lineal foot, and that the company was to furnish the caps. These caps were necessarily placed upon the piles after they were driven, and were a part of the permanent structure of the trestle. The court erred in making a separate allowance for the capping.
The next question is as to the interest. The decree was for $ 4,647.34, and the court allowed interest from the time of the last estimate,...
To continue reading
Request your trial-
Brown v. Lemay
...parol testimony tending to vary, change, add to or subtract from the terms of the written instrument. 94 Ark. 130; 88 Ark. 213; 86 Ark. 162, 164; 83 Ark. 163; 80 Ark. 508, 509; 67 Ark. 62; 30 Ark. 186, 197. 2. The first instruction of the court ignores an element vital to plaintiff's case, ......
-
Burel v. East Arkansas Lumber Company
...does not come into court with "clean hands." "There were overcharges and an attempt to skin the owner. No interest should be allowed. 86 Ark. 162. Fuhr & Futrell and Ponder, Gibson & Ponder, for appellee. 1. No personal judgment was intended against Mrs. Burel, and really there is none. 2. ......
-
Hockaday v. Warmack
...Id. 9. This is a memorandum of a sale of land in writing. It was definite, complete, certain and unambiguous and required no explanation. 86 Ark. 162; 95 131; 100 Id. 360; 17 Cyc. 610. To add to the consideration would be to vary its terms. 3. Evidence of what occurred in an effort to compr......
- Bigham v. Dover